Resolved
It was agreed that the reports be noted. Resolved – That the reports from the scheme promoter and the Independent Assessor be noted.
Berkshire Local Transport Body agreed this item on Wednesday 15 July 2020. Below is the council's own wording, with the papers it was decided on.
Resolved
It was agreed that the reports be noted. Resolved – That the reports from the scheme promoter and the Independent Assessor be noted.
1. At your meeting in March 2017, you approved guidance for the preparation of one- and five-year- on impact reports for BLTB funded local transport schemes.
2. This report introduces the impact report for scheme 2.22 Slough: Burnham Station Access.
3. You are recommended to note the reports from the scheme promoter and the independent assessor.
Other Implications
Financial
4. There are no direct financial implications of this report.
5. The government requires all LEPs to have Assurance Frameworks which set out governance arrangements and financial procedures. One of the specific requirements for transport schemes is to require scheme promoters to submit impact reports one and five years post implementation.
Human Rights Act and Other Legal Implications
6. Slough Borough Council will provide legal support for the BLTB should any questions arise on the application of the Assurance Framework.
Supporting Information
7. Slough Borough Council received £2.0m towards the £2.1m cost of this scheme.
8. The one-year on impact report is attached at Appendix 2; and the independent assessor’s report is attached at Appendix 1.
Item 13: BLTB 15 July 2020 Scheme 2.22 Slough: Burnham Station Access – One Year Evaluation Report Conclusion
9. The Burnham Station Access one-year impact report represents a well-constructed and balanced document. It is considered to meet a number of requirements for a one-year impact report, relating to what and how the scheme has been delivered; however, there are limitations in the quantified assessment of the outcomes.
10. The report provides a good overview of the scheme that has been delivered and the positive impacts that have been generally reported in terms of traffic management and enhanced access to the station by a wide variety of different modes. There is some secondary evidence to support the case that traffic congestion may have reduced, and that road safety could be improving as a result of the measures.
11. At this stage, it is unclear the extent to which the scheme is having any influence over mode choice, either in terms of individuals choosing to travel by train, or in terms of how they choose to access the station. It is clear, however, that the options for accessing the station have improved and, alongside the Network Rail/GWR station works, will have significantly improved the attractiveness of rail travel from the station.
12. The scheme was delivered to budget but was delayed in its completion by two years, from the initial forecast. There is a limitation in the available data to understand how outturn costs evolved in relation to forecast costs. Overall, however, the budgeting process appears to have been robust. It is clear that improvements could have been made to the overall delivery of the project, particularly in terms of the overall length of time taken to deliver the project. In terms of the actual outputs, the traffic management measures appear to be working well and the station environment is much improved, subject to further surveys of demand and travel times.
13. The FBC highlighted a number of areas where monitoring and evaluation would take place, and these are not considered to have been undertaken. Furthermore, the case for investment was justified on the basis of journey time benefits, traffic decongestion, rail demand uplifts, car park revenues generated, and health benefits, and yet there is limited reference to many of these issues within the evaluation report.
14. To enhance the understanding of the impact of the project, as well as to maximise future outcomes, there is a clear requirement to conduct the following additional quantified survey work:
• Traffic counts and journey time surveys;
• Car parking usage counts;
• Cycle parking / docking station usage; and
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
2.22 Slough: Burnham Station Access: One Year Evaluation ReportReport | 219 KB | DownloadRead as text |
Follow Berkshire Local Transport Body at Slough and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 9 Nov 2023 | Minutes of the Meeting held on 13th July 2023Resolved – That the minutes of the meeting held on 13 th July 2023 be approved as a correct record. | Approved | Open |
| 9 Nov 2023 | Thames Valley Berkshire Capital Programme UpdateResolved – (a) That the progress made on schemes previously given programme entry status as set out in the report and... | Noted | Open |
| 9 Nov 2023 | One Year Evaluation ReportResolved – That the one-year impact report for Scheme 2.42 – South Wokingham Distributor Road – Eastern Gateway be no... | Noted | Open |
| 9 Nov 2023 | Approach to developing aspirations for prioritised strategic transport infrastructure schemes across BerkshireResolved – That the proposed approach to develop a list of prioritised strategic transport schemes across Berkshire t... | Agreed | Open |
| 13 Jul 2023 | Introduction to Berkshire Local Transport Body - Its Role and PurposeResolved – That the introduction to BLTB and a vote of thanks to Councillor Page be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.