Resolved
Resolved – That the reports from the scheme promoter and the Independent Assessor be noted.
Berkshire Local Transport Body noted this item on Wednesday 15 July 2020. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved – That the reports from the scheme promoter and the Independent Assessor be noted.
1. At your meeting in March 2017, you approved guidance for the preparation of one- and five-year- on impact reports for BLTB funded local transport schemes.
2. This report introduces the impact report for scheme 2.09.1 Slough: A4 Cycle Route NCN422.
3. You are recommended to note the reports from the scheme promoter and the independent assessor.
Other Implications
Financial
4. There are no direct financial implications of this report.
5. The government requires all LEPs to have Assurance Frameworks which set out governance arrangements and financial procedures. One of the specific requirements for transport schemes is to require scheme promoters to submit impact reports one and five years post implementation.
Human Rights Act and Other Legal Implications
6. Slough Borough Council will provide legal support for the BLTB should any questions arise on the application of the Assurance Framework.
Supporting Information
7. Slough Borough Council received £483k in LGF towards the cost of this £930k scheme.
8. The one-year on impact report is attached at Appendix 1; and the independent assessor’s report is attached at Appendix 2.
Item 12: BLTB 15 July 2020 - Scheme 2.09.2 Slough: A4 Cycle Route NCN422 One Year Evaluation Report Conclusion
9. The Independent Assessor concludes that the A4 Cycle Route one-year impact report represents a well-constructed and balanced document. It is considered to meet many of requirements for a one- year impact report, relating to what and how the scheme has been delivered; however, there are significant limitations in the quantified assessment of the outcomes.
10. The report provides a good overview of the scheme that was delivered and the positive impacts that have occurred in terms of enhanced walking and cycling provision and the effect this has had upon overall cycling amenity. There is some secondary evidence to indicate that cycling levels may have increased as a result of the scheme and direct evidence that the scheme is having a positive influence on accident levels.
11. At this stage, it is unclear whether any significant mode shift has resulted and whether private car trips have reduced at all as a result of the scheme. In addition, it is unclear what mechanisms the scheme sought to address gender inequalities in cycling and no data was collected before or after the scheme implementation that would permit this to be assessed.
12. The scheme was delivered close to budget (+2%) but was substantially delayed in its completion by nearly two years. There is no data presented to understand how outturn costs evolved in relation to forecast costs; however, overall, the budgeting process appears to have been reasonably robust. Clearly substantial improvements could have been made to the overall delivery of the project in terms of the programme; however, the actual standard of the outputs appears to be good and the scheme elements appear to be working well and has delivered the broad outcomes required, albeit this cannot be verified by quantified data on usage and mode shift.
13. It is noted that the original monitoring and evaluation plan stated that before and after surveys would be undertaken for the 1 and 5-year evaluations, however, it would appear this has not come to fruition. This has placed significant limitations on the evaluation process. Furthermore, the case for investment was justified on the basis of a range of benefits to cyclist and highway users. Whilst some of these are referenced within the evaluation report, others (e.g. health benefits) are not specifically referenced.
14. To enhance the understanding of the impact of the project, as well as to maximise future outcomes, there is a clear requirement to conduct the following quantified survey work:
• Cycle counts along the route;
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
2.09.2 Slough: A4 Cycle Route NCN422: One Year Evaluation ReportReport | 1.7 MB | DownloadRead as text |
Follow Berkshire Local Transport Body at Slough and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 9 Nov 2023 | Minutes of the Meeting held on 13th July 2023Resolved – That the minutes of the meeting held on 13 th July 2023 be approved as a correct record. | Approved | Open |
| 9 Nov 2023 | Thames Valley Berkshire Capital Programme UpdateResolved – (a) That the progress made on schemes previously given programme entry status as set out in the report and... | Noted | Open |
| 9 Nov 2023 | One Year Evaluation ReportResolved – That the one-year impact report for Scheme 2.42 – South Wokingham Distributor Road – Eastern Gateway be no... | Noted | Open |
| 9 Nov 2023 | Approach to developing aspirations for prioritised strategic transport infrastructure schemes across BerkshireResolved – That the proposed approach to develop a list of prioritised strategic transport schemes across Berkshire t... | Agreed | Open |
| 13 Jul 2023 | Introduction to Berkshire Local Transport Body - Its Role and PurposeResolved – That the introduction to BLTB and a vote of thanks to Councillor Page be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.