CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
London Borough of Southwark
Cabinet (decommissioned, for the Executive after, Thursday 28 May 2026 at 4.00pm

Disposal of Site A - 5 Nunhead Green, London SE15

Agreed Executive 2 papers

AI summarySouthwark Cabinet authorised sale of the freehold at 5 Nunhead Green, SE15 3QQ and delegated terms to the head of property. A capital receipt is expected, and an alternative bidder may be used if the recommended purchaser does not contract, subject to best consideration. [D] [P2] [P3] [P21] [P37]

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeAgreedHead of property may agree terms and negotiate necessary items. [D] [P2]
MoneyCapital receipt expected [P37]Financial implications are in the closed version of the report. [P47]
What happens nextNot stated
Who it affectsHousing and community facilities [P15] [P23]Consent includes eight houses, six flats and a community centre. [P15]

What was decided

Cabinet approved disposal of the council's freehold interest in Site A, 5 Nunhead Green, SE15 3QQ, as shown edged black on the Appendix 1 plan, on the terms set out in the closed report. Report P2, P47, P51

The head of property may agree the detailed transaction terms and negotiate any other necessary items. Report P2

If the recommended purchaser does not contract within a reasonable period, the property may be sold to an alternative bidder if the transaction continues to represent the best consideration reasonably obtainable. Report P3, P21

Why

Section 123 of the Local Government Act 1972 requires disposal for the best consideration that could reasonably be obtained. The head of property confirmed that the recommended price meets this requirement. Report P21, P44

The transaction would implement the planning consent within a suitable period, with safeguards requiring the developer to build the consented scheme. Report P19

Redevelopment would bring the vacant property back into beneficial use and provide new housing for the local community. The capital receipt would support the council's capital programme and key priorities. Report P23, P25, P29

What happens next

The head of property will agree the detailed transaction terms and negotiate any other necessary items. Report P2

An alternative bidder may be used if the recommended purchaser does not enter contracts within a reasonable period, provided the transaction continues to represent the best consideration reasonably obtainable. Report P3

The property is to be sold with full vacant possession before completion. The capital receipt is expected in 2014/15. Report P24, P37

The money

  • The costs of obtaining the planning consent and s.106 and Mayoral Community Infrastructure Levy which have been incurred by the council Will be recouped in the sale receipt. Report P40

Options considered

  • Chosen: Sell to the recommended purchaser. The head of property confirmed that the sale gives the best consideration reasonably obtainable and supports delivery of the consented scheme. Report P19, P21
  • Chosen: Use an alternative bidder if the recommended purchaser does not contract. The fallback is authorised within a reasonable period only if the transaction continues to represent the best consideration reasonably obtainable. Report P3
  • Chosen: Proceed with the consented private housing redevelopment on Site A. The consent includes eight houses and six flats on Site A, and the private housing site was intended for sale. Report P15, P16
  • Rejected: Retain Site A for the Direct Housing Delivery Programme. As a general fund site, it was considered less suitable than sites in the Housing Revenue Account such as Site B. Report P26, P27
  • Rejected: Develop a health facility on the site. The Primary Care Trust had no need or future use for the site. Report P9

Implications

  • Financial: A substantial capital receipt will support the general fund capital programme in 2014/15 and the council's key priorities. Report P25, P29, P37, P48
  • Legal: Legal advice confirmed adequate powers to dispose by agreement, provided the sale meets Section 123 of the Local Government Act 1972. The head of property confirmed that the recommended price was the best reasonably obtainable at this time. Report P21, P43, P44, P45
  • Other: The Site A property extends to approximately 2,727m2 (0.67 acres). The consent provides for eight houses and six flats, and the sale is intended to bring the vacant property back into beneficial use. It has frontages to Nunhead Green, Nunhead Lane (A2214) and Scylla Road. Report P5, P15, P23
  • Financial: Buyers will contribute towards administration costs, there will be no loss of income, and planning consent, s.106 and Mayoral Community Infrastructure Levy costs will be recouped in the sale receipt. Report P38, P39, P40
  • Climate: New dwellings are designed to meet level 4 of the sustainable homes code, 20% of the site's energy requirements will come from renewable sources, and the community centre targets BREEAM Excellent. Report P30
  • Equalities: The council found no adverse effect on protected characteristics and considered its Equality Act 2010 duties satisfied. The new community centre will be fully accessible and open to all. Report P33
  • Legal: The contract will trigger further council payments if sales thresholds are exceeded or the property is sold within a ten year period for more than the original consideration. Report P22
  • Risk: The recommended transaction includes safeguards requiring the developer to build the consented scheme. The council owns no interest in any bidding company. Report P19, P24

Who and where

  • Local residents Report P23, P33, P35
  • Occupiers of new homes on Site A Report P15, P23
  • Users of the replacement community centre Report P33
  • People who used the former community centre at 56 Nunhead Lane Report P12, P33
  • Nunhead's Voice, identified as a potential lessee Report P15
  • The council's general fund and capital programme Report P6, P25, P29, P48
  • The recommended purchaser and any alternative bidder Report P2, P3, P24

Timeline

  • 6 March 2007: The executive approved relocation of childcare services to Rye Oak Primary School and noted that the two properties might become surplus. Report P8
  • June 2013: Planning consent was granted for eight affordable homes on Site B, a new community centre, eight houses and six flats on Site A. Report P15
  • 25 April 2014: Best bids were received after a period of two months marketing by informal tender, with 124 enquiries and 14 bids from 12 separate bidders. Report P18
  • 10 July 2014: The final report was dated. Report P53
  • 2014/15: A capital receipt from the sale was expected. Report P37, P48
  • within a ten year period: Further payments to the council may be triggered if the property is sold for more than the original consideration. Report P22
  • 2026-05-28: Cabinet authorised the disposal.

Plain English for the jargon

  • freehold interest: The council is the freeholder of the property. [P5]
  • general fund: The fund holding the property and receiving the sale receipt. [P6] [P25] [P29]
  • best consideration: The best price for the land that could reasonably be obtained. [P21] [P44]
  • capital receipt: Money received from the sale, expected in 2014/15. [P25] [P37]
  • vacant possession: The property is sold with no occupier in place. [P24]
  • overage clauses: Contract clauses requiring further council payments if later sales exceed thresholds or the original price. [P22]
  • planning consent: Permission for the wider development, including eight houses and six flats on Site A. [P15]
  • BREEAM Excellent: The sustainability status targeted by the new community centre. [P30]
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item26

Resolved

That the disposal of the council’s freehold interest in Site A - 5 Nunhead Green, SE15 3QQ (“the property”), as shown edged black on the plan in Appendix 1 of the report be authorised, to the party on the terms outlined in the closed version of the report. That authority be delegated to the head of property to agree the detailed terms of the transaction and negotiate any other items considered necessary. 2. That the disposal of the property to an alternative bidder be authorised should the recommended purchaser not enter into contracts within a reasonable period as long as the transaction continues to represent the best consideration reasonably obtainable.
Word for word from the decision Southwark published for this meeting. Source: moderngov.southwark.gov.uk

Follow this further

Built from Southwark's papers

What the report saysPro

Report to Cabinet (decommissioned, for the Executive after, 5 pages

Recommendations

That the cabinet authorises

1. The disposal of the council’s freehold interest in Site A - 5 Nunhead Green, SE15 3QQ (“the property”), as shown edged black on the plan in Appendix 1, to the party on the terms outlined in the closed version of this report. Delegating authority to the head of property to agree the detailed terms of the transaction and negotiate any other items considered necessary.

2. The disposal of the property to an alternative bidder should the recommended purchaser not enter into contracts within a reasonable period as long as the transaction continues to represent the best consideration reasonably obtainable.

1 BACKGROUND INFORMATION

3. The council is the freeholder of the property edged in black on the attached plan at Appendix 1. The property extends to approximately 2,727m2 (0.67 acres) and is split into two sections with frontages to Nunhead Green and Nunhead Lane (A2214) and Scylla Road.

4. The property is held in the council’s general fund.

5. The property comprised a single storey 1970’s built day nursery and associated grounds. The building was in poor condition and was nearing the end of its economic life.

6. On 6 March 2007, the council’s executive approved the relocation of the childcare services from Nunhead Green Early Years Centre (EYC) to Rye Oak Primary School creating a comprehensive Children’s Centre. The Executive noted that “upon conclusion of the relocation of childcare services into the proposed development at Rye Oak Primary School, property assets at Rye Oak Primary School and Nunhead Green EYC may be declared surplus to the children’s services department’s needs.”

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
MapAppendix 1 1 pages Download
PDF
Report: Disposal of Nunhead Site AReport 5 pages DownloadRead as text

At this meeting

Whole meeting
3Notice of Intention to conduct business in a closed meeting, and any representations receivedOn the agenda 6MinutesApproved 8Southwark Community Wardens Service (Housing, Environment and Community Safety Scrutiny Sub-Committee)Noted 9Prevalence of Psychosis and Access to Mental Health Services for the BME Community in Southwark (Health, Adult Social Care, Communities & Citizenship Scrutiny Sub-Committee)Noted 10Access to Health Services in Southwark (Health, Adult Social Care, Communities & Citizenship Scrutiny Sub-Committee)Noted 11Council Plan 2014/15 - 2017/18Agreed 12Fairer Future Annual Performance Report 2013/14Noted 13Blue Bermondsey Business Improvement District Proposal and BallotNoted 14Next Steps on Developing Long Term Plans for the Delivery of New Council HomesNoted 15Major Works Status Report Incorporating Warm, Dry and SafeNoted 16Integrated Community Support - A New Commissioning Strategy, underpinned by an Ethical Care CharterAgreed 17School Places Strategy UpdateNoted 18Non-Domestic Rates - Discretionary Rate Relief Policy for Retail Relief, Reoccupation Relief and New Build Empty Property ReliefApproved 19Elephant and Castle Regeneration ProgressAgreed 20Gateway 1 Abbeyfield Estate HINE (Maydew House) WorksApproved 21Review of Void Disposal StrategyNoted 22Quarterly Capital Monitoring Outturn Report for 2013/14 and Capital Programme Refresh for 2013/14 - 2023/24Noted 23Revenue Outturn Report 2013/14, including Treasury ManagementNoted 24Nominations to Centre for Literacy in Primary Education and Safeguarding Adults Partnership Board 2014/15Agreed 25Motions Referred from Council AssemblyNoted
26Disposal of Site A - 5 Nunhead Green, London SE15This decision
27Gateway 2 - Contract Award Approval: Lift Maintenance ContractApproved 28Proposal to Lease Northcott House HostelAgreed 29Gateway 1 - Procurement Strategy Approval - Appointment of Contractors for Primary Expansion ProgrammeApproved 30Gateway 1 - Procurement Strategy Approval - Heating and Water ContractsApproved 31Exclusion of Press and PublicOn the agenda

Who was there

10 of 12 attended
PJ
Councillor Peter JohnChair, present
IW
Councillor Ian WingfieldCommittee Member, present
FC
Councillor Fiona ColleyCommittee Member, present
DD
Councillor Dora Dixon-Fyle MBECommittee Member, present
BH
Councillor Barrie HargroveCommittee Member, present
RL
Councillor Richard LivingstoneCommittee Member, present
DM
Councillor Darren MerrillCommittee Member, present
VM
Councillor Victoria MillsCommittee Member, present
MS
Councillor Michael SituCommittee Member, present
MW
Councillor Mark WilliamsCommittee Member, present
EK
Eleanor KellyOfficer, expected
DF
Doreen Forrester-BrownOfficer, expected

On this subject at Southwark

Search all
  1. Disposal of Site A - 5 Nunhead Green, London SE15This decision
  2. Disposal of Site at 117-119 Ivydale Road, London, SE15Agreed
  3. Disposal of Site 19 Elephant and CastleAgreed
  4. Disposal of the Council's freehold interest in Elmington Estate sites C, D, E and G, Camberwell, SE5Approved
  5. Disposal of the Site Comprising 184-188 Southampton Way, 5a Havil Street and Part of the Beacon Estate, London SE5Approved
  6. Disposal of The Grange (Sites C2 and C4) Bermondsey Spa, London SE1Agreed

More from Southwark Cabinet (decommissioned, for the Executive after

All decisions
MeetingDecisionOutcome
28 May 2026 Election of Chair for the meetingThat Councillor Maisie Anderson be elected chair for this meeting. Decided Open
28 May 2026 Notification of any items of business which the chair deems urgentIt was agreed that all the deputations would be heard so that consideration of these representations could be given p... Agreed Open
28 May 2026 Disclosure of Interests and DispensationsDecision Maker (IDM) report in respect of this issue. Councillor Peter John also declared a personal, non prejudicial... Decided Open
28 May 2026 Review of Void Disposal StrategyThat the progress of disposals of void housing properties since April 2009 be noted. 2. That the importance of void d... Noted Open
28 May 2026 Housing Revenue Account - Approval of Housing Revenue Budget Account 2011/12That the savings required to deliver a balanced housing revenue account (HRA) for 2011/12 be noted. 2. That the propo... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies