Gateway 1 Abbeyfield Estate HINE (Maydew House) Works
ApprovedExecutive1 paper
AI summarySouthwark Cabinet approved an EU restricted procurement strategy for an Abbeyfield Estate HINE works contract estimated at £22m over 208 weeks. [D] The Leader delegated award to the housing cabinet member; the total estimated scheme cost is £24.2m. [D]
Written from the decision and the officer reportPDF Pro
OutcomeApprovedRestricted tender for the works contract only [P21] [P31]
MoneyTotal scheme cost £24.2m [D]Estimated total £24.2m, including £22m works and £2.2m fees [D]
What happens nextAward and progress update [P5]Housing cabinet member to award; Cabinet update December 2014 [P5]
Who it affectsMaydew House residents [P101]New homes, housing waiting list and Bede centre [P67] [P68]
What was decided
Cabinet approved the procurement strategy for the Abbeyfield Estate HINE works contract, with an estimated value of £22m over 208 weeks.
Cabinet noted estimated internal and external fees of £2.2m, making the total estimated scheme cost £24.2m.
The Leader delegated authority to the cabinet member for housing to award the contract, subject to a procurement progress update to Cabinet in December 2014.
Why
Maydew House needed extensive investment because of asbestos, communal heating and hot water infrastructure requiring full replacement, and a declining building fabric. Report P8
The previous Major Works Lot 2 contract ended by mutual agreement, so a competitive procurement route was needed. Report P24
Delegating award was recommended to allow a prompt contract award and start on site while the block was empty, avoiding continuing security costs. Report P22
What happens next
The housing cabinet member will award the contract, and Cabinet will receive a procurement update in December 2014. Report P5
Outline planning approval will be sought before the invitation to tender is issued, with council building control approval sought at relevant stages. Report P44, P45
Calfordseaden will prepare the full specification, outline design and bill of quantities. The project board will sign off the tender documents before they are issued, and the contract will be advertised through the Official Journal of the European Union and on the council website. Report P53, P55, P57, P58
The money
£22m Estimated value of the works contract
£2.2m Estimated internal and external fees
£24.2m Total estimated scheme cost
£ 13,850,000 Maydew refurbishment Report P95
£ 2,950,000 Additional floors and units at Maydew Report P95
£ 5,200,000 Re-provision Bede and new build Report P95
£11,000,000 Warm, Dry and Safe funding Report P97
£4,197,767 High Investment Needs Estate funding Report P97
Options considered
Chosen: EU restricted tender process. The other routes were not viable, and the market had sufficient contractors and was very competitive. Report P26, P31
Rejected: The council does nothing. Works were required because of asbestos, the need to replace communal heating and hot water infrastructure, and declining building fabric. Report P8, P30
Rejected: Use the Major Works Partnering contract. The Lot 2 contract ended on 18 June 2012, leaving no provision for work in Bermondsey and Rotherhithe. Report P24, P30
Rejected: Provide the works in house. The council has no resource or expertise for this type of works. Report P30
Implications
Financial: The allocated Abbeyfield Estate budget covers the main works, sales of additional units fund the extension, and the regeneration budget funds the new council homes on the Bede site. The report says the new build resources are yet to be identified. Expenditure, receipts and progress need close monitoring across four consecutive financial years from 2014/15. Report P93, P99, P122, P123
Legal: The restricted two stage procedure must comply with Public Contracts Regulations 2006 and the council's Contract Standing Orders, including taking reasonable steps to obtain at least 5 tenders. Report P115, P116, P117
Legal: Tender evaluation will use 70% price and 30% quality. The JCT Design and Build 2011 form will be amended by council legal services and executed under seal. Report P54, P61, P62
Legal: Planning approval is required before the invitation to tender. Council building control approval is required at relevant stages, and the contractor cannot use another building control authority. Report P44, P45
Risk: Controls cover procurement compliance, financial soundness, delays and contractor performance. The contract has a 12 month defects liability period. A Performance Bond is required, retention is held as work progresses, and a Parent Company Guarantee is required if the contractor has a parent company. Report P36, P37, P39, P40
Equalities: The proposed environmental works are not expected to adversely affect any one particular group, and Bede management can help shape the relocated centre. Contractors must demonstrate an Equal Opportunities Policy, meet London Living Wage requirements and provide apprenticeships and school placements. Report P68, P75, P77, P79
Climate: New homes will connect to the council's communal heating and hot water infrastructure. The waste disposal design must incorporate environmentally friendly factors. Report P15, P82
Staffing: Letting the contract has no staffing implications. A dedicated fixed term contract manager is already in place within the major works team. Report P90
Who and where
Maydew House tenants and leaseholders Report P101, P102
New home occupiers and people on the council housing waiting list Report P67
Bede centre management and the local Bede community Report P68
Neighbouring block residents and the resident project team Report P88
EU and local companies bidding for the contract Report P71, P72
Contractor staff, apprentices and the local labour market Report P69, P77, P79
Council major works, procurement, legal and building control teams Report P45, P86, P112
Garage team and future garage tenants Report P127
Timeline
4 Aug 2014: Contract advertised Report P47
4 Sept 2014: Closing date for expressions of interest Report P47
6 Oct 2014: Invitation to tender Report P47
19 Nov 2014: Closing date for tender returns Report P47
31 Dec 2014: Gateway 2 contract award approval Report P47
20 Feb 2015: Contract award Report P49
2 Mar 2015: Contract start Report P49
25 Feb 2019: Contract completion Report P49
Plain English for the jargon
HINE: High Investment Needs Estate funding identified for the scheme [P97].
EU restricted procedure: A two stage tender where companies express interest, complete a PQQ, and shortlisted firms are invited to tender [P33] [P47].
PQQ: Pre Qualification Questionnaire used to assess applicants before tender invitation [P33] [P60].
ITT: Invitation to tender sent after shortlisting [P44] [P47].
OJEU: Official Journal of the European Union, where the contract notice is published [P57].
JCT Design and Build 2011: The proposed contract form, subject to council legal amendments and execution under seal [P54].
LLW: London Living Wage. The successful contractor is expected to meet the pay requirement [P76] [P77].
TUPE: Staff transfer rules that should not apply here, but would need review if the contractor changes [P51].
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item20
Resolved
Decisions of the Cabinet 1. That the procurement strategy outlined in the report for the Abbeyfield Estate HINE ( Maydew House) works contract at an estimated value of £22m for an estimated period of 208 weeks be approved. 2. That the estimated internal and external fees of £2.2m making a total estimated scheme cost of £24.2m be noted. Decision of the Leader 3. That authority be delegated to the cabinet member for housing to award the contract for the reasons set out in paragraph 17 of the report, subject to an update being provided to cabinet on progress with this procurement in December 2014.
Word for word from the decision Southwark published for this meeting.Source: moderngov.southwark.gov.uk
Report to Cabinet (decommissioned, for the Executive after, 14 pages
Recommendations
Recommendations for the Cabinet
1. That cabinet approves the procurement strategy outlined in this report for the Abbeyfield Estate HINE (Maydew House) works contract at an estimated value of £22m for an estimated period of 208 weeks.
2. That cabinet notes that there are estimated internal and external fees of £2.2m making a total estimated scheme cost of £24.2m.
Recommendation for the Leader
3. That the leader of the council delegates authority to the cabinet member for housing to award the contract for the reasons set out in paragraph 17 below, subject to an update being provided to cabinet on progress with this procurement in December 2014.
BACKGROUND INFORMATION
4. Cabinet approved the enhanced refurbishment works to Abbeyfield Estate on 20 March 2012 following an extensive options appraisal consultation process managed by regeneration on the future of the estate with key stakeholders and a deputation from residents on the Estate to cabinet. The options appraisal process included a desktop review of officer held information on the blocks, external and internal surveys by MACE, production of relevant options for the blocks and the subsequent pricing of these options by Potter Raper Partnership and regeneration conducting a series of events and open days to obtain and gauge feedback from residents.
5. The options appraisal followed on from previously shelved contracts for asbestos removal which identified the need for Maydew House to be decanted due to the levels of asbestos contained within the block and for the fact that the communal heating and hot water infrastructure needed full replacement. As such Maydew House has required a large amount of investment for a number of years and the building fabric has been in decline whilst the council decided the future of the block.
6. Abbeyfield Estate falls within Area 2 for major works and it was intended that all major refurbishment works in the Bermondsey and Rotherhithe areas be allocated to the council’s Major Works partnering contract for Lot 2 - Wates Construction Ltd (WCL) during the anticipated initial 5 year duration of that contract running to 2015.
7. Unfortunately, the Major Works partnering contract for Lot 2 with WCL was ended by mutual agreement on 18 June 2012. Temporary arrangements (approved on 11 May 2012) were put in place with the reserve contractor, Keepmoat Regeneration (Apollo) Ltd, to deliver urgent works pending the tendering of future projects in Area 2. The refurbishment of Damory and Thaxted Houses will be delivered by Keepmoat Regeneration (Apollo) Ltd in order to mitigate delays for the residents in these 2 blocks.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Cabinet (decommissioned, for the Executive after at Southwark and we tell you when its next papers are published, before the meeting rather than after it.
Review of Void Disposal StrategyThat the progress of disposals of void housing properties since April 2009 be noted. 2. That the importance of void d...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.