London Borough of Southwark
Cabinet (decommissioned, for the Executive after, Thursday 28 May 2026 at 4.00pm

Elephant and Castle Regeneration Progress

Agreed Executive 6 papers

AI summarySouthwark Council's Cabinet agreed to amend the Elephant and Castle regeneration agreement, delay the Crossways Church site transfer, revise sustainable energy provisions and approve changing the purpose of two council land areas to planning purposes. No new costs or receipts arise from the decision. [D] [P32]

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeAgreedChurch delayed; energy provisions revised [D] [P3] [P4]
MoneyNot stated
What happens nextChurch site transfer delayed [P3]Earlier of replacement completion or 30 September 2016 [P3]
Who it affectsElephant and Castle regeneration [D] [P8]

What was decided

Southwark Cabinet agreed to amend the Regeneration Agreement dated 23 July 2010 with Lend Lease (Elephant & Castle) Limited. The Crossways Church site transfer is delayed until the earlier of completion of the replacement church at Hampton Street or 30 September 2016. The agreement's provisions for MUSCO, a multi utility service company, are revised using the sustainable energy provisions approved on 15 January 2013. Report P2, P3, P4

The Council confirmed that the land edged black at Appendix B, held for housing and leisure purposes, is no longer required for those purposes. It approved the land's appropriation to planning purposes under section 226 of the Town and Country Planning Act 1990 and section 122(1) of the Local Government Act 1972. The appropriation will facilitate the development proposals for the area. Report P5

The Council confirmed that the land edged black at Appendix D, held for housing purposes, is no longer required for that purpose. It approved the land's appropriation to planning purposes under section 226 of the Town and Country Planning Act 1990 and section 122(1) of the Local Government Act 1972. The appropriation will facilitate the development proposals for the area. Report P6

Why

The Council could not provide vacant possession of Crossways Church until the replacement church was completed. Temporary exclusion allowed the main site transfer and redevelopment to proceed without waiting for the replacement. Report P17

The alternative energy and utility solution met the Council's and C40 Cities Climate Leadership Group's sustainability aspirations and was already being implemented. Report P19

The housing on the Heygate site was beyond economic repair and was being demolished, while the Castle Day Centre site was no longer needed and was required for the replacement church. Appropriation gives developers certainty by overriding affected third party rights, with compensation available instead of an injunction to stop or delay development. Report P22, P41, P44, P45

What happens next

Complete the main former Heygate Estate transfer, scheduled for September, with Crossways Church excluded, and begin redevelopment from Wansey Street. Include the church site in the lease once vacant possession is obtained, either when the replacement church is complete or on 30 September 2016, whichever is sooner. Report P3, P17, P36

Continue implementing the alternative energy and utility provisions. Further provisions will be addressed through planning applications for individual phases. Report P19

A planning application has been made for the replacement Crossways Church on the former Castle Day Centre site in Hampton Street. The land appropriation is intended to enable construction of the new church. Report P26, P27

Options considered

  • Rejected: Transfer Crossways Church with the main site now. The Council could not provide vacant possession until the replacement church was completed, and waiting would delay the overall regeneration. Report P17
  • Chosen: Transfer the main site with Crossways Church temporarily excluded. This lets the main site transfer proceed before the replacement church is complete. Report P17
  • Rejected: Keep the original MUSCO provisions. An alternative approved on 15 January 2013 was already being implemented. Report P19
  • Chosen: Revise the MUSCO provisions around the sustainable energy solution. The alternative met the Council's and C40 Cities Climate Leadership Group's sustainability aspirations. Report P19
  • Chosen: Appropriate Appendix B land for planning purposes. The land was no longer required for housing and leisure, and appropriation would facilitate the area's development proposals. Report P5, P24
  • Chosen: Appropriate Appendix D land for planning purposes. The land was no longer required for housing and was needed for the replacement church. Report P6, P26, P44

Implications

  • Legal: After appropriation, construction or use in accordance with planning permission can override certain private rights over the land. Claimants may seek compensation for loss of value but cannot obtain an injunction to stop or delay development. Report P22, P45
  • Financial: If appropriation causes compensation claims, Lend Lease will reimburse the Council's costs for handling the claims and paying compensation. Report P23
  • Risk: The lease mechanism lets construction start earlier than it otherwise would. Appropriating the replacement church site reduces the risk that private rights could frustrate or delay construction. Report P27, P37
  • Financial: Temporary exclusion of Crossways Church reduces the risk of delayed transfer penalties and prevents delays in land receipts paid to the Council. Report P31
  • Financial: The Council will receive payment from Lend Lease under the existing Regeneration Agreement when the main site transfers. There are no new costs or receipts, and the alternative energy and utility provisions are expected at or below the original forecast cost. Report P18, P32, P48
  • Climate: The alternative energy and utility solution meets the Council's and C40 Cities Climate Leadership Group's sustainability aspirations. Report P19
  • Equalities: The regeneration had extensive consultation, and a full Equalities Impact Assessment was submitted as part of the outline planning application determined on 15 January 2013. Report P30
  • Risk: Developers can insure against compensation claims or quantify them. The report warns that the grant or risk of an injunction may be fatal to development or cause significant unquantifiable costs. Report P22

Who and where

  • Lend Lease (Elephant & Castle) Limited Report P2, P17, P19
  • London Borough of Southwark Report P5, P6, P23
  • Crossways Church Report P3, P26
  • Claimants with third party rights over the appropriated land Report P22, P45
  • Developers carrying out the area's development proposals Report P22, P43
  • Local people benefiting from jobs created by the projects Report P9

Timeline

  • 23 July 2010: The Regeneration Agreement was signed between the Council and Lend Lease. Report P2, P8
  • 15 January 2013: The Planning Committee approved the alternative energy and utility solution. Report P19
  • 5 July 2014: The final officer report was dated. Report P55
  • September: Transfer of the main former Heygate Estate was scheduled, with redevelopment due to start in Wansey Street. Report P17
  • 30 September 2016: The Crossways Church site was to transfer by this date unless the replacement church was completed sooner. Report P3, P17

Plain English for the jargon

  • MUSCO: A multi utility service company envisaged to provide energy and other utilities to the regeneration area. [P19]
  • Appropriation: Changing the purpose for which a council holds land or buildings. [P22]
  • Section 237: A power allowing construction in accordance with planning permission to override certain private rights over appropriated land. [P45]
  • TCPA 1990: Town and Country Planning Act 1990. [P42]
  • 1972 Act: Local Government Act 1972. [P39]
  • Easement: One of the private rights that may be overridden after land is appropriated for planning purposes. [P45]
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item19

Resolved

That the regeneration agreement dated 23 July 2010 between the London Borough of Southwark and Lend Lease (Elephant & Castle) Limited be amended as follows: (a) the transfer of the Crossways Church site is delayed until the earlier of the completion of the replacement Crossways Church at Hampton Street or 30 September 2016. (b) to revise MUSCO provisions with the sustainable energy provisions provided within the Planning Committee approval (minute 6) on 15 January 2013. 2. That it be confirmed that the land edged black on the plan at Appendix B of the report that is currently held for housing and leisure purposes is no longer required for those purposes and the appropriation of the land to planning purposes be confirmed to facilitate the carrying out of the development proposals for the area in accordance with section 226 of the Town and Country Planning Act 1990 and section 122(1) of the Local Government Act 1972 3. That it be confirmed that the land edged black on the plan at Appendix D of the report that is currently held for housing purposes is no longer required for those purposes and that the appropriation of the land to planning purposes to facilitate the carrying out of the development proposals for the area in accordance with section 226 of the Town and Country Planning Act 1990 and section 122(1) of the Local Government Act 1972 be approved.
Word for word from the decision Southwark published for this meeting. Source: moderngov.southwark.gov.uk

Follow this further

Built from Southwark's papers

What the report saysPro

Report to Cabinet (decommissioned, for the Executive after, 7 pages

Recommendations

That Cabinet:

1. agrees to amend the Regeneration Agreement dated 23 July 2010 between the London Borough of Southwark and Lend Lease (Elephant & Castle) Limited as follows:

1 (a) the transfer of the Crossways Church site is delayed until the earlier of the completion of the replacement Crossways Church at Hampton Street or 30 September 2016.

(b) to revise MUSCO provisions with the sustainable energy provisions provided within the Planning Committee approval (minute 6) on 15 January 2013.

2. confirms that the land edged black on the plan at Appendix B that is currently held for housing and leisure purposes is no longer required for those purposes and approves the appropriation of the land to planning purposes to facilitate the carrying out of the development proposals for the area in accordance with section 226 of the Town and Country Planning Act 1990 and section 122(1) of the Local Government Act 1972

3. confirms that the land edged black on the plan at Appendix D that is currently held for housing purposes is no longer required for those purposes and approves the appropriation of the land to planning purposes to facilitate the carrying out of the development proposals for the area in accordance with section 226 of the Town and Country Planning Act 1990 and section 122(1) of the Local Government Act 1972

BACKGROUND INFORMATION

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Plan of land to transfer to Lend Lease imminentlyAppendix A 1 pages Download
PDF
Plan of Heygate land to be appropriatedAppendix B 1 pages Download
PDF
Rationale for appropriation of Heygate LandAppendix C 2 pages Download
PDF
Plan of land for replacement Crossways ChurchAppendix D 1 pages Download
PDF
Rationale for appropriation of land for replacement Crossways ChurchAppendix E 2 pages Download
PDF
Report: Elephant and CastleReport 7 pages DownloadRead as text

At this meeting

Whole meeting
3Notice of Intention to conduct business in a closed meeting, and any representations receivedOn the agenda 6MinutesApproved 8Southwark Community Wardens Service (Housing, Environment and Community Safety Scrutiny Sub-Committee)Noted 9Prevalence of Psychosis and Access to Mental Health Services for the BME Community in Southwark (Health, Adult Social Care, Communities & Citizenship Scrutiny Sub-Committee)Noted 10Access to Health Services in Southwark (Health, Adult Social Care, Communities & Citizenship Scrutiny Sub-Committee)Noted 11Council Plan 2014/15 - 2017/18Agreed 12Fairer Future Annual Performance Report 2013/14Noted 13Blue Bermondsey Business Improvement District Proposal and BallotNoted 14Next Steps on Developing Long Term Plans for the Delivery of New Council HomesNoted 15Major Works Status Report Incorporating Warm, Dry and SafeNoted 16Integrated Community Support - A New Commissioning Strategy, underpinned by an Ethical Care CharterAgreed 17School Places Strategy UpdateNoted 18Non-Domestic Rates - Discretionary Rate Relief Policy for Retail Relief, Reoccupation Relief and New Build Empty Property ReliefApproved
19Elephant and Castle Regeneration ProgressThis decision
20Gateway 1 Abbeyfield Estate HINE (Maydew House) WorksApproved 21Review of Void Disposal StrategyNoted 22Quarterly Capital Monitoring Outturn Report for 2013/14 and Capital Programme Refresh for 2013/14 - 2023/24Noted 23Revenue Outturn Report 2013/14, including Treasury ManagementNoted 24Nominations to Centre for Literacy in Primary Education and Safeguarding Adults Partnership Board 2014/15Agreed 25Motions Referred from Council AssemblyNoted 26Disposal of Site A - 5 Nunhead Green, London SE15Agreed 27Gateway 2 - Contract Award Approval: Lift Maintenance ContractApproved 28Proposal to Lease Northcott House HostelAgreed 29Gateway 1 - Procurement Strategy Approval - Appointment of Contractors for Primary Expansion ProgrammeApproved 30Gateway 1 - Procurement Strategy Approval - Heating and Water ContractsApproved 31Exclusion of Press and PublicOn the agenda

Who was there

10 of 12 attended
PJ
Councillor Peter JohnChair, present
IW
Councillor Ian WingfieldCommittee Member, present
FC
Councillor Fiona ColleyCommittee Member, present
DD
Councillor Dora Dixon-Fyle MBECommittee Member, present
BH
Councillor Barrie HargroveCommittee Member, present
RL
Councillor Richard LivingstoneCommittee Member, present
DM
Councillor Darren MerrillCommittee Member, present
VM
Councillor Victoria MillsCommittee Member, present
MS
Councillor Michael SituCommittee Member, present
MW
Councillor Mark WilliamsCommittee Member, present
EK
Eleanor KellyOfficer, expected
DF
Doreen Forrester-BrownOfficer, expected

On this subject at Southwark

Search all
  1. Elephant and Castle Regeneration ProgressThis decision
  2. Elephant and Castle - Provision of a New Leisure FacilityApproved
  3. Elephant and Castle - Regeneration Agreement and Disposal of Associated LandAgreed
  4. Elephant and Castle – Provision of a new leisure facilityNoted
  5. Elephant and Castle Regeneration - Shopping CentreAgreed
  6. Disposal of Site 19 Elephant and CastleAgreed

More from Southwark Cabinet (decommissioned, for the Executive after

All decisions
MeetingDecisionOutcome
28 May 2026 Election of Chair for the meetingThat Councillor Maisie Anderson be elected chair for this meeting. Decided Open
28 May 2026 Notification of any items of business which the chair deems urgentIt was agreed that all the deputations would be heard so that consideration of these representations could be given p... Agreed Open
28 May 2026 Disclosure of Interests and DispensationsDecision Maker (IDM) report in respect of this issue. Councillor Peter John also declared a personal, non prejudicial... Decided Open
28 May 2026 Review of Void Disposal StrategyThat the progress of disposals of void housing properties since April 2009 be noted. 2. That the importance of void d... Noted Open