Major Works Status Report Incorporating Warm, Dry and Safe

Noted Executive 1 paper

AI summarySouthwark Cabinet noted a March 2014 update on Warm, Dry and Safe works, which were on course to be fully committed by the end of 2015/16. Resources would be reassessed against commitments to deliver kitchens and bathrooms and finish the £383m programme. [D][P9][P2] [D][P7][P60]

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedFire safety and resource progress also noted [P3][P6][P7]
Money£383m WDS budget [P60]Additional resources needed to complete WDS [P12][P100]
What happens nextRevise resources and programme [P71]Kitchens, bathrooms and WDS resources [P7][P71][P73]
Who it affectsCouncil tenants and residents [P36]Fire safety, heating and home improvements [P16][P36]

What was decided

Cabinet noted the housing investment programme status, with WDS on course to be fully committed by the end of 2015/16. [D][P1][P2] Report P1, P2

Cabinet noted that all substantial risk high rise blocks and nearly all originally identified high moderate blocks were complete. Additional Fire Risk Assessment schemes were added, with an allowance outside WDS for substantial risk medium rise properties. Further Fire Risk Assessment work will be prioritised with the London Fire Brigade alongside long term planning for council housing assets. [D][P3][P4][P38][P41] Report P3, P4, P38, P41

Cabinet noted British Gas environmental work on roofs, windows and cavity work at a notional cost, plus the current programme resources. Resources will be assessed against the commitment to provide a quality kitchen and bathroom for every council tenant and finish WDS. [D][P5][P6][P7] Report P5, P6, P7

Why

Making every home warm, dry and safe is a council priority and part of Southwark's Fairer Future promises. [P9][P18] Report P9, P18

Fire Risk Assessment work is intended to reduce risk in high rise properties, including substantial risk blocks. [P38][P41] Report P38, P41

Scheme costs exceed original estimates because stock data was limited and budgets had insufficient allowance for scaffolding, asbestos, preliminary work and work outside WDS. Further resources are needed for WDS and kitchens and bathrooms. [P63][P71][P100] Report P63, P71, P100

What happens next

Funding assumptions for kitchens, bathrooms and the resources needed to finish WDS will go to the Housing Investment Board as a capital bid. A revised programme will be drawn up. [P71][P73] Report P71, P73

Further Fire Risk Assessment work will be prioritised with the London Fire Brigade alongside long term planning for council housing assets. The benefits of British Gas work will be reviewed and reported when the work ends. [P4][P41][P61] Report P4, P41, P61

Following cabinet approval, the report will be sent to Home Owners Council and Tenant Council. A further annual progress report will go to cabinet after the current financial year. [D][P8][P98][P120] Report P8, P98, P120

The money

  • £383m Current WDS programme budget Report P60, P114
  • £326m Original WDS provision Report P60, P117
  • £48.8m Additional backlog funding Report P57, P60
  • £8.2m Additional capital bids Report P58, P60
  • Over £180m Spent on the first three years of WDS Report P10, P26
  • £90m WDS spend target for 2014/15 Report P10, P47
  • £2.3m Work on 48 substantial risk medium rise blocks Report P39
  • Over £36m Investment in Fire Risk Assessment works Report P38

Options considered

  • Chosen: Coordinate substantial risk medium rise work with WDS. £2.3m was agreed for work at 48 blocks alongside the remaining WDS programme. Report P39
  • Chosen: Continue British Gas environmental improvements. The work covers roofs, windows and cavity work at a notional cost to Southwark. Report P5, P61
  • Chosen: Use back up contractors and competitive tendering. This continued delivery after the two Major Works partnering contracts ended by mutual agreement. Report P22
  • Chosen: Keep partnering contracts and tender individual projects. Existing contracts would remain subject to extension reviews. Elsewhere, lists of contractors would tender for individual building projects. Report P88
  • Chosen: Prioritise future fire risk work with the London Fire Brigade. Further work would be prioritised alongside long term planning for council housing assets. Report P4, P41
  • Chosen: Tackle the worst housing conditions first. Later schemes were expected to need only minor works as earlier work addressed the worst conditions. Report P68

Implications

  • Financial: Scheme costs are above original estimates, so further resources are needed to complete WDS and deliver kitchens and bathrooms. [P63][P71][P115] Report P63, P71, P115
  • Financial: The WDS budget is £383m, with around £120m uncommitted at the end of March 2014. This excludes voids capitalisation and ongoing lift and heating programmes. [P60][P69][P75] Report P60, P69, P75
  • Financial: The approved Housing Investment Programme was approximately £1.5bn up to the period 2021/22, with a significant shortfall against projected expenditure. [P118] Report P118
  • Risk: All substantial risk high rise blocks and nearly all originally identified high moderate blocks were complete. Further Fire Risk Assessment work still required prioritisation. [P38][P41] Report P38, P41
  • Climate: British Gas work, efficient windows and heating systems are intended to reduce carbon emissions. [P61][P108] Report P61, P108
  • Equalities: Better insulation and heating should benefit all communities, including people on fixed incomes and people facing fuel poverty. [P109] Report P109
  • Other: Making homes warm, dry and safe is likely to produce health benefits for tenants and residents. [P107] Report P107
  • Legal: There are no specific legal implications from the recommendations, but legal services will continue to advise when required. [P123] Report P123

Who and where

  • Council tenants Report P43
  • Residents of high rise blocks requiring fire safety work Report P38
  • Residents in sheltered accommodation and hostels Report P40, P92
  • Pensioner households Report P106, P109
  • People on fixed incomes, benefits or in fuel poverty Report P109
  • Residents with health problems in social housing Report P106
  • Home owners with major works concerns Report P83
  • Contractors bidding for Major Works projects Report P88

Timeline

  • 18 October 2011: Cabinet agreed a detailed five year housing investment programme. [P15] Report P15
  • 18 June 2012 and 15 February 2013: The Major Works Lot 2 and Lot 1 partnering contracts both ended by mutual agreement. Delivery continued through back up contractors and competitive tendering. [P22] Report P22
  • end of March 2014: The interim update recorded over £180m spent and 62.66% of the council's rented accommodation meeting the Decent Homes Standard. [P9][P17][P26][P43] Report P9, P17, P26, P43
  • 2014/15: A £90m WDS spend target was set. Most of the remaining programme was expected to be on site by the end of the year. [P47][P100] Report P47, P100
  • by March 2015: Automatic battery powered smoke and heat detection was due to start in the highest priority blocks. [P40] Report P40
  • 2015: A new contractor framework was planned. [P88] Report P88
  • by the end of 2015/16: The WDS programme was expected to be fully committed. [P2][P52] Report P2, P52
  • by September 2016: Sprinkler systems were due for sheltered and hostel accommodation. [P40] Report P40

Plain English for the jargon

  • WDS: The Warm, Dry and Safe programme, based on making homes warm, dry and safe and equated with the Government's Decent Homes Standard. [P17]
  • FRA: Fire Risk Assessment work for historic blocks, divided into substantial and moderate risk sections. [P38][P186][P187]
  • Decent Homes Standard: The Government standard to which the WDS principles equate. [P17][P103]
  • HIP: The Housing Investment Programme, which directs council investment in housing stock. [P111][P114]
  • HINE: High Investment Needs Estate funding used for additional work. [P32][P141]
  • LD2: Automatic battery powered smoke and heat detection for council homes. [P40]
  • BEMS: Building Management Systems, which monitor and control services such as heating. [P156]
  • CWI: Cavity wall insulation filled through British Gas work. [P61]
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item15

Resolved

That the status of the housing investment programme with particular reference to the warm, dry and safe (WDS) programme be noted. 2. That it be noted that the current warm, dry and safe programme is on course to be fully committed by the end of 2015/16. 3. That the progress of the strategic safety works programme be noted. All substantial risk high rise blocks have now been completed and nearly all the high moderate risk blocks originally identified have now been completed. Additional schemes have been added to the fire risk assessment (FRA) programme and an additional allowance has been made outside of w arm, dry and safe to tackle substantial risk medium rise properties. Further FRA work will be prioritised in discussion with the London Fire Brigade alongside the council’s longer term asset management planning. 4. That the ongoing work that has been delivered through British Gas to deliver environmental improvements including roofs, windows and cavity work at a notional cost to Southwark be noted. 5. That the current programme resources be noted. 6. That it be noted that the resources for the programme will be assessed in line with the commitment to deliver a quality kitchen and bathroom for every council tenant and the completion of the warm, dry and safe programme. 7. That it be noted that this report will be sent to Home Owners Council and Tenant Council following cabinet approval.
Word for word from the decision Southwark published for this meeting. Source: moderngov.southwark.gov.uk

Follow this further

Built from Southwark's papers

What the report saysPro

Report to Cabinet (decommissioned, for the Executive after, 51 pages

Recommendations

1. That cabinet notes the status of the Housing investment programme with particular reference to the Warm, Dry and Safe (WDS) programme.

2. That cabinet notes that the current WDS programme is on course to be fully committed by the end of 2015/6.

3. That cabinet notes the progress of the strategic safety works programme. All substantial risk high rise blocks have now been completed and nearly all the high moderate risk blocks originally identified have now been completed. Additional

1 schemes have been added to the Fire Risk Assessment (FRA) programme and an additional allowance has been made outside of Warm, Dry and Safe to tackle substantial risk medium rise properties. Further FRA work will be prioritised in discussion with the London Fire Brigade alongside our longer term asset management planning.

4. That cabinet notes the ongoing work that has been delivered through British Gas to deliver environmental improvements including roofs, windows and cavity work at a notional cost to Southwark.

5. That cabinet notes the current programme resources.

6. That cabinet notes that the resources for the programme will be assessed in line with the commitment to deliver a quality kitchen and bathroom for every council tenant and the completion of the WDS programme.

7. That cabinet notes that this report will be sent to Home Owners Council and Tenant Council following cabinet approval.

Summary

8. It is a key priority of the council to make every home in Southwark warm, dry and safe. This paper is to give an interim update on the WDS programme as at the end of March 2014.

9. Over £180m has been spent and the programme is on course to be fully committed by the end of March 2015/16. The annually set WDS spend target for 2013/14 of £80m was achieved and a spend target of £90m has been set for 2014/15.

10. Some of the programme has been accelerated, whilst some delays have been caused to some projects due to the mutual conclusion of two partnering contractors.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Report and appendices: Major Works Status Report incorporating Warm Dry and SafeReport 51 pages DownloadRead as text

At this meeting

Whole meeting
3Notice of Intention to conduct business in a closed meeting, and any representations receivedOn the agenda 6MinutesApproved 8Southwark Community Wardens Service (Housing, Environment and Community Safety Scrutiny Sub-Committee)Noted 9Prevalence of Psychosis and Access to Mental Health Services for the BME Community in Southwark (Health, Adult Social Care, Communities & Citizenship Scrutiny Sub-Committee)Noted 10Access to Health Services in Southwark (Health, Adult Social Care, Communities & Citizenship Scrutiny Sub-Committee)Noted 11Council Plan 2014/15 - 2017/18Agreed 12Fairer Future Annual Performance Report 2013/14Noted 13Blue Bermondsey Business Improvement District Proposal and BallotNoted 14Next Steps on Developing Long Term Plans for the Delivery of New Council HomesNoted
15Major Works Status Report Incorporating Warm, Dry and SafeThis decision
16Integrated Community Support - A New Commissioning Strategy, underpinned by an Ethical Care CharterAgreed 17School Places Strategy UpdateNoted 18Non-Domestic Rates - Discretionary Rate Relief Policy for Retail Relief, Reoccupation Relief and New Build Empty Property ReliefApproved 19Elephant and Castle Regeneration ProgressAgreed 20Gateway 1 Abbeyfield Estate HINE (Maydew House) WorksApproved 21Review of Void Disposal StrategyNoted 22Quarterly Capital Monitoring Outturn Report for 2013/14 and Capital Programme Refresh for 2013/14 - 2023/24Noted 23Revenue Outturn Report 2013/14, including Treasury ManagementNoted 24Nominations to Centre for Literacy in Primary Education and Safeguarding Adults Partnership Board 2014/15Agreed 25Motions Referred from Council AssemblyNoted 26Disposal of Site A - 5 Nunhead Green, London SE15Agreed 27Gateway 2 - Contract Award Approval: Lift Maintenance ContractApproved 28Proposal to Lease Northcott House HostelAgreed 29Gateway 1 - Procurement Strategy Approval - Appointment of Contractors for Primary Expansion ProgrammeApproved 30Gateway 1 - Procurement Strategy Approval - Heating and Water ContractsApproved 31Exclusion of Press and PublicOn the agenda

Who was there

10 of 12 attended
PJ
Councillor Peter JohnChair, present
IW
Councillor Ian WingfieldCommittee Member, present
FC
Councillor Fiona ColleyCommittee Member, present
DD
Councillor Dora Dixon-Fyle MBECommittee Member, present
BH
Councillor Barrie HargroveCommittee Member, present
RL
Councillor Richard LivingstoneCommittee Member, present
DM
Councillor Darren MerrillCommittee Member, present
VM
Councillor Victoria MillsCommittee Member, present
MS
Councillor Michael SituCommittee Member, present
MW
Councillor Mark WilliamsCommittee Member, present
EK
Eleanor KellyOfficer, expected
DF
Doreen Forrester-BrownOfficer, expected

On this subject at Southwark

Search all
  1. Major Works Status Report Incorporating Warm, Dry and SafeThis decision
  2. Response to the Report of the Housing Scrutiny Commission:The Council's work with social landlord partners; the Fair Street/Devon Mansions, Canada and Kirby Estates QHIP major works projects; the revised resident engagement strategy; and temporary accommodation in properties awaiting demolitionNoted
  3. Report of the Housing Scrutiny Commission: The Council's work with social landlord partners; the Fair Street/Devon Mansions, Canada and Kirby Estates QHIP major works projects; the revised resident engagement strategy; and temporary accommodation in properties awaiting demolitionNoted
  4. Four Squares Estate - Major Works UpdateNoted
  5. Major Works Status Report incorporating Warm, Dry and SafeNoted
  6. Report into Major Works at Draper House (Housing, Environment, Transport and Community Safety Scrutiny Sub-Committee)Noted

More from Southwark Cabinet (decommissioned, for the Executive after

All decisions
MeetingDecisionOutcome
28 May 2026 Election of Chair for the meetingThat Councillor Maisie Anderson be elected chair for this meeting. Decided Open
28 May 2026 Notification of any items of business which the chair deems urgentIt was agreed that all the deputations would be heard so that consideration of these representations could be given p... Agreed Open
28 May 2026 Disclosure of Interests and DispensationsDecision Maker (IDM) report in respect of this issue. Councillor Peter John also declared a personal, non prejudicial... Decided Open
28 May 2026 Review of Void Disposal StrategyThat the progress of disposals of void housing properties since April 2009 be noted. 2. That the importance of void d... Noted Open
28 May 2026 Housing Revenue Account - Approval of Housing Revenue Budget Account 2011/12That the savings required to deliver a balanced housing revenue account (HRA) for 2011/12 be noted. 2. That the propo... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies