Gateway 1 - Procurement Strategy Approval - Appointment of Contractors for Primary Expansion Programme
ApprovedExecutive1 paper
AI summaryCabinet approved the iESE procurement strategy for appointing two contractors to the primary schools expansion programme. [D] The works contracts have an estimated total value of £60.5m, plus £0.7m for each package's preconstruction services, with projects from £1.5m to £10.0m. [P2]
Written from the decision and the officer reportPDF Pro
OutcomeApprovedTwo contractors via iESE for school expansion [D] [P1]
Money£60.5m estimated contract value [P2]Plus £0.7m per package for preconstruction [P2]
What happens nextGateway 2 contractor approvals [P3]Children’s services director approves appointments [P3]
Who it affectsSchools expansion programme [D]11 additional forms of entry by September 2016 [P21]
What was decided
Cabinet approved the procurement strategy for appointing two contractors through the iESE construction and management framework for the primary schools expansion programme. Report P1
Cabinet noted that one contractor will be appointed for each of two packages for preconstruction services. Separate construction contracts will follow for projects within each package. The estimates are £0.7m per package for preconstruction, £60.5m for construction in total, and £1.5m to £10.0m per project. Report P2
Cabinet noted that individual appointments will be approved in Gateway 2 reports by the Strategic Director of Children’s and Adults Services. Report P3
Why
Procurement was required to enable the council to meet its statutory responsibility to provide sufficient primary school places. The programme targeted 11 additional forms of entry by September 2016 against forecast demand. Report P21
The iESE route was expected to save approximately six months compared with a fresh EU procurement. It offered schools experience, EU compliance, early contractor involvement, cost and time certainty, value for money and quality. The council had previously used iESE for office accommodation at Queens Road and phase 1 of directly funded housing. Report P36, P37, P38, P45, P46, P47
Two packages would spread contractor performance risk and add competitive pressure. Bidders could win only one package, and each contractor would act as the other’s reserve contractor after default. Report P48
What happens next
A further competition will be issued to seven of the eight framework firms, followed by a shortlist of four. Each shortlisted firm will submit price and quality bids for both packages, using the mandatory 70:30 quality to price weighting. Report P122, P124, P125, P128
A single Gateway 2 report will seek approval of two preconstruction appointments, one for each package, each estimated at £0.7m. The Strategic Director of Children’s and Adults Services will approve individual appointments. Report P3, P52, P53
Twelve Gateway 2 reports will seek approval of separate construction contracts for individual projects, with values from £1.5m to £10.0m. Further reports may cover enabling works, and approved additions for Phoenix Primary School and Keyworth Primary School would be added to procurement. Each award report must identify funding, and the Belham contract must not be awarded until Education Funding Agency funding is confirmed. Report P22, P54, P55, P190
The money
£60.5m Overall estimated cost of works contracts. Report P2, P160
£0.7m Estimated preconstruction value for each of two packages. Report P2, P53
£1.5m to £10.0m Estimated range for individual construction projects. Report P2, P54
29.5m Package A total estimated project value. Report P158
31m Package B total estimated project value. Report P159
£15m Threshold above which procurement strategy approval was reserved to Cabinet. Report P180
£4.3m EU procurement threshold for some individual contracts. Report P181
Options considered
Chosen: iESE framework arrangements. The route offered collaboration, cost and time certainty, value for money, quality and risk control. It complied with EU rules and was expected to save approximately six months against a fresh EU procurement. Report P36, P37, P38, P45, P47
Rejected: EU restricted procedure procurement route. A new restricted procedure would be lengthy, would constrain progress and would prevent completion by September 2016. It offered no balancing advantage over existing compliant arrangements. Report P34
Rejected: Local Education Partnership, known as 4 Futures. The route was excluded because LEP resources needed to remain focused on current projects. It also required consideration of possible legal challenges by alternative suppliers. Report P35
Rejected: LHC Schools and Community Buildings contractor framework. Only five framework contractors were available in the London region. This reduced the number of firms that could be invited and created a risk of insufficient responses. Report P39
Rejected: EFA Contractors’ Framework. The programme mixed refurbishment, remodelling and new build, which did not fit the framework. Its single stage approach prevented early engagement on phasing, access and site logistics. Report P40
Rejected: SCAPE construction framework. It was based on a single provider, so could not divide the programme into more than one package or spread risk. Report P41
Rejected: Traditional procurement route. It would remove early contractor involvement in design, specification, programming and cost planning. It would also significantly lengthen the time before site work started. Report P42, P43, P44
Implications
Financial: Existing identified resources can meet the total estimated contract cost, and the council will continue seeking funding from other sources. The contracts were expected across three consecutive financial years from 2014/15, requiring close monitoring of expenditure, receipts and progress. Schools will meet ongoing revenue effects, each Gateway 2 report must identify funding, and the Belham contract must not be awarded until Education Funding Agency funding is confirmed. Report P161, P164, P165, P189, P190
Legal: The total estimated contract values exceed £15m, so Cabinet approval of the procurement strategy was reserved. Some individual contracts exceed the £4.3m EU threshold, but the iESE framework satisfies EU procurement requirements. Report P180, P181
Equalities: Cabinet must have regard to the Public Sector Equality Duty under section 149 of the Equality Act 2010. Additional school places were expected to improve provision, community cohesion and the safeguarding and wellbeing of local children and young people. Report P133, P182, P186
Climate: New schools and expansions will meet a minimum BREEAM very good environmental standard where applicable. They will use recycled and low carbon materials where possible, plus energy efficient fittings and building management systems where appropriate. Report P147, P148
Risk: Two packages spread contractor performance risk, with each contractor acting as reserve for the other after default. Nearby residents may experience short term construction inconvenience, managed through consultation and the Considerate Contractor scheme. Report P48, P134, P135
Risk: The assessment rated five procurement risks as low: insufficient contractor interest, timetable slippage, a challenged process, bids below an acceptable standard and failure to reach school selection consensus. Report P62, P63, P64, P65, P66, P67
Staffing: The procurement will use existing staff and existing budgets. Officers considered staff resources sufficient for the proposed timetable. Report P154, P155
Other: Contractors are expected to support local supply chains, labour, training, apprenticeships and nearby trade. Successful contractors and subcontractors must meet London Living Wage requirements. Report P140, P141, P143, P145
Who and where
Package A schools: Ivydale, Cherry Garden, Crawford, Redriff, Gloucester and Keyworth Report P15, P16, P158
Package B schools: Albion, Bellenden, Grange, Charles Dickens, Robert Browning and The Belham Report P16, P159
Phoenix Primary School, if the separate recommendations are approved Report P22
Children and young people needing additional primary school places Report P21, P72, P133
Schools receiving expansions, which are responsible for ongoing revenue implications Report P164
Residents near new developments, who may experience short term construction inconvenience Report P134
Local residents, businesses and traders expected to benefit from construction Report P140, P141, P143
Contractor and subcontractor staff, subject to London Living Wage requirements Report P145
Timeline
10 July 2014: Final officer report dated. Report P198
30 Jul 14: Notification of implementation of the Gateway 1 decision. Report P82
8 Aug 14 and 11 Aug 14: Tender documentation completion and invitation to the further competition. Report P82, P85
8 Sep 14: Closing date for competition submissions. Report P86
17 Oct 14: Gateway 2 contract award report approval. Report P90
28 Oct 14 and 29 Oct 14: Contract award and contract start. Report P92, P93
March 15, Aug 16 and September 2016: Approximate preconstruction completion, construction completion and facilities ready for use. Report P19, P95, P103
Plain English for the jargon
iESE: Improvement and Efficiency South East regional construction framework for projects over £1 million in value. [D] [P36]
Gateway 1: The approval point for the procurement strategy before individual contractor appointments. [P19] [P51]
Gateway 2: The approval point for each preconstruction or construction contract appointment. [P49] [P52] [P54]
Preconstruction services: Work before construction contracts are awarded, covering design development, planning consent, detailed pricing and contractor proposals. [P58]
Forms of entry: The programme measure used for expanded primary school provision. [P6] [P21]
Open book tendering: A collaborative design and build procurement process with early contractor involvement. [P26] [P37] [P38]
PSED: Public Sector Equality Duty under section 149 of the Equality Act 2010. [P182] [P186]
BREEAM: A minimum very good environmental performance standard for applicable new schools and expansions. [P147]
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item29
Resolved
That the procurement strategy for appointment of two contractors for the primary schools expansion programme using the Improvement and Efficiency South East (iESE) construction and management framework arrangements be approved. 2. That it be noted that a contractor will be appointed for each of two packages noted in paragraph 23 of the report for pre-construction services using the iESE contractor framework (estimated value for each package: £0.7m) and a series of works contracts for the construction stage of individual projects within their respective package using the iESE contractor framework (estimated total value of £60.5m, comprising a range of project values from £1.5m to £10.0m). 3. That the individual appointments set out in paragraphs 26 and 27 of the report will be approved in gateway 2 reports by the strategic director of children’s and adults services be noted.
Word for word from the decision Southwark published for this meeting.Source: moderngov.southwark.gov.uk
Report to Cabinet (decommissioned, for the Executive after, 18 pages
Recommendations
1. That cabinet approve the procurement strategy for appointment of two contractors for the primary schools expansion programme using the Improvement and Efficiency South East (iESE) construction and management framework arrangements.
2. That the cabinet note that a contractor will be appointed for each of two packages noted in paragraph 23 for pre-construction services using the iESE contractor framework (estimated value for each package: £0.7m) and a series of works contracts for the construction stage of individual projects within their respective package using the iESE contractor framework (estimated total value of £60.5m, comprising a range of project values from £1.5m to £10.0m).
3. That the cabinet note that the individual appointments noted in paragraphs 26 and 27 will be approved in gateway 2 reports by the strategic director of children’s and adults services.
BACKGROUND INFORMATION
Context
4. The Primary Investment Strategy was agreed by cabinet in July 2013 and updated by the cabinet member for children’s services in January 2014 to address the forecast shortfall of places in the borough over the three year period to September 2016. A further update report is included elsewhere on the agenda of this meeting. Expansion of the following 12 primary schools was approved to provide 11 additional forms of entry (FE):
1 Table 1: Primary expansion programme
Primary school Expansion Nature of works ‘The Belham’ Free School 2FE Remodel Bellenden – site to be confirmed 1FE New Build Keyworth 0.5FE Remodel Gloucester 1FE Remodel Grange 0.5FE Remodel Charles Dickens 0.5FE Remodel Robert Browning 0.5FE Remodel Crawford 1FE Remodel Redriff 1FE Remodel Albion 1FE New Build Ivydale @ Bredinghurst 2FE New Build Cherry Garden N/A New Build Total 11FE
5. The procurement strategy for appointing the consultant design team using the CRCS 2012 Framework, was approved in February 2014. This comprises:
• two contracts for architect-led design teams (including building services engineer, structural engineer, civil engineer and landscape architect); and
• one contract each for project manager, quantity surveyor, BREEAM assessor, CDM co-ordinator and clerk of works to provide these services across the programme.
6. For Architectural Services, the schools were divided into the following two packages, each of roughly equal value and each with a different architect:
Table 2: Procurement Packages
PACKAGE A PACKAGE B Schools: Schools:
New Build Schemes: New Build Schemes: • Ivydale • Albion • Cherry Gardens • Bellenden
7. The consultant architect together with their associated sub-consultants will novate to the contractor following completion of RIBA Work Stage D (Employer’s Requirements/planning consent).
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Cabinet (decommissioned, for the Executive after at Southwark and we tell you when its next papers are published, before the meeting rather than after it.
Review of Void Disposal StrategyThat the progress of disposals of void housing properties since April 2009 be noted. 2. That the importance of void d...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.