Gateway 1- Procurement Strategy Approval: Door Entry and Warden Call Contract
ApprovedExecutive1 paper
AI summarySouthwark Cabinet approved a four year door entry and warden call procurement strategy [D]. It starts on 1 June 2018, with up to two years of extensions, at an estimated £1,210,000 a year and a total estimated value of £7,260,000 [D].
Written from the decision and the officer reportPDF Pro
OutcomeApprovedDoor entry and warden call contract [D]
Money£1,210,000 estimated annually [D]Total estimated contract value £7,260,000 [D]
What happens nextNot stated
Who it affectsNot stated
What was decided
Cabinet approved the procurement strategy for a door entry and warden call contract [D].
The initial term is four years from 1 June 2018, with one or more extensions up to two years [D].
The estimated annual cost is £1,210,000 and the total estimated contract value is £7,260,000 [D].
Why
The services support safe homes and risk management across council housing and other premises [P13] [P14]. Report P13, P14
A 2016 market review found that responsive repairs and specialist fire work should use separate contracts because the services need different delivery structures [P8] [P9]. Report P8, P9
The term allows review after two years and time to reprocure if needed, while the maximum six years is intended to attract competition [P19] [P20]. Report P19, P20
What happens next
Develop, publish and evaluate the tender, then seek Gateway 2 contract award approval [P43] [P48] [P53]. Report P43, P48, P53
Complete staff transfer and pension due diligence under TUPE before tendering and include the findings in the tender pack [P46]. Report P46
Consult leaseholders under the Commonhold and Leasehold Reform Act 2002, serving a Notice of Intention before tenders and a Notice of Proposal after analysis [P91] [P106] [P107]. Report P91, P106, P107
£7,260,000 Total estimated contract value Report P98
£7.2m Total estimated value stated in the business case Report P17
£4.8m Estimated cost for the four year term Report P18
£2.4m Estimated cost of the additional two year term Report P18
£250 Cost level above which further leaseholder notice is required Report P107
Options considered
Chosen: EU restricted tender. The other routes were not viable and the estimated service value is above the EU threshold [P29]. Report P29
Chosen: Separate contract for entry systems and warden call. Responsive repairs and specialist fire work need different delivery structures and reflect market specialisation [P8] [P9]. Report P8, P9
Rejected: Retain one combined service contract. The review concluded that two contracts would provide an improved service and support better competition [P15]. Report P15
Rejected: Do nothing. This was not available because the council must ensure the systems are functional as a landlord and employer [P26]. Report P26
Rejected: Council provides the works in house. Traded services does not currently have the required capability, although it could tender if it establishes a team [P27]. Report P27
Rejected: Shared Services with neighbouring boroughs. Neighbouring borough contracts are not open for other boroughs to use [P28]. Report P28
Rejected: Internal or external frameworks. No existing framework meets the service requirements [P28]. Report P28
Implications
Legal: The procurement must follow Public Contract Regulations 2015 and council contract standing order requirements. Cabinet approval is reserved under CSO 4.5.2 a) after corporate contracts review board consideration. The contract also supports statutory landlord obligations under the Building Regulations 2010 and the Housing Act 2004 [P40] [P104] [P105]. Report P40, P104, P105
Legal: TUPE is likely to apply between the incumbent and new contractor. The council says there should be no council employer or pension implications unless staff originally employed by the council transfer, and due diligence is needed before tendering [P46]. Report P46
Financial: The estimated cost can be met from the current Door Entry maintenance and refurbishment budget. Maintenance must remain separately identifiable and is recovered through service charges from tenants and leaseholders, subject to lease conditions. Refurbishment savings have not yet been agreed and will be considered at Gateway 2. There are no investment implications [P85] [P86] [P87] [P89]. Report P85, P86, P87, P89
Staffing: There is no impact on council staff because the existing engineering and compliance management team already performs contract management. The successful contractor must provide apprenticeship opportunities to Southwark residents, with progress monitored by the contract manager. The contractor is also expected to meet London Living Wage requirements [P65] [P69] [P83]. Report P65, P69, P83
Equalities: The successful contractor must operate an Equal Opportunities Policy and comply with equality legislation [P68]. Report P68
Climate: The contract encourages low emission vehicles and fewer journeys. Replacement electrical equipment must be disposed of under WEEE rules and new equipment must be low energy rated, recyclable packaging must be recycled, and no hazardous materials will be used [P72] [P73] [P74] [P75]. Report P72, P73, P74, P75
Risk: Procurement risks include challenges, poor submissions, delay and contractor default. Controls include robust compliant procurement, high quality tender documents, project management and contractual service mechanisms, with possible use of the council’s approved contractor list. A parent company guarantee will be required if the successful contractor has a parent company, and retention on interim payments means no performance bond is required [P36] [P37]. Report P36, P37
Other: The contract is borough wide and supports safe homes in communal and sheltered housing. The council must consider wider social, economic and environmental benefits before procurement [P60] [P62]. Report P60, P62
Tenderers and the successful contractor Report P64, P65
Timeline
21 March 2017: Gateway 1 procurement strategy approval Report P43
30 March 2017: Notice of Intention for leaseholder consultation Report P43
22 May 2017: OJEU notice publication Report P43
26 June 2017: Closing date for expressions of interest Report P43
24 July 2017: Invitation to tender Report P43
06 Feb 2018: Gateway 2 contract award approval Report P43
01 Mar 2018: Contract award Report P44
01 June 2018: Contract start. Initial contract completion is 31 May 2022 and completion with extensions is 31 May 2024 Report P44
Plain English for the jargon
Gateway 1 and Gateway 2: Gateway 1 approves the procurement strategy; Gateway 2 seeks contract award approval [P39] [P43].
OJEU: Official Journal of the European Union, where the contract notice will be published [P50].
PQQ and PAS91: The pre qualification questionnaire sent after a formal expression of interest [P31].
EU restricted procedure: A tender process that invites expressions of interest before selecting up to five organisations [P29] [P31] [P32].
M.E.A.T: Most economically advantageous tender, assessed at 70:30 for price and quality [P54].
TUPE: Transfer of Undertakings (Protection of Employment) Regulations 2006, likely to apply when service providers change [P46].
LLW: London Living Wage, which the successful contractor is expected to meet [P69].
CSO: Contract standing order, under which this approval is reserved to Cabinet after review board consideration [P104] [P105].
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item11
Resolved
That the procurement strategy outlined in the report for a door entry and warden call contract at an estimated annual cost of £1,210,000 for a period of four years from 1 June 2018 with the option of one or more extensions for a maximum of two years, making a total estimated contract value of £7,260,000 be approved.
Word for word from the decision Southwark published for this meeting.Source: moderngov.southwark.gov.uk
Report to Cabinet (decommissioned, for the Executive after, 12 pages
Recommendation
1. That cabinet approves the procurement strategy outlined in this report for a door entry and warden call contract at an estimated annual cost of £1,210,000 for a period of four years from 1 June 2018 with the option of one or more extensions for a maximum of two years, making a total estimated contract value of £7,260,000.
BACKGROUND INFORMATION
2. Currently, there is a Fire Fighting Equipment, Fire Alarms, Emergency Lighting, Warden Call and Door Entry contract in place which delivers the following services:
(a) periodic testing of fire alarm systems to meet statutory obligations; (b) responsive repairs and maintenance to door entry systems; (c) responsive repairs and testing of warden call systems; (d) testing and repairs to fire fighting equipment; (e) periodic testing of emergency lighting installations; (f) automatic opening ventilation systems; (g) some passive fire protection works; and (h) builders work in connection with services.
3. The current contract commenced on 1 June 2013 for an initial term of three years with the option to extend for two 12-month extensions. 4. A Gateway 3 report seeking the first 12-month extension was approved on 19 June 2015. This report identified the need to review the existing service packaging in relation to managing corporate risks and obtaining best value.
5. A Gateway 3 report seeking the final 12-month extension will be approved shortly. This contract will therefore expire on 31 May 2018 and there is a requirement to ensure that arrangements are in place for these services.
6. The current contract scope was based upon market evaluation carried out by consultants in 2010 that recommended that bringing the services together in single contract would deliver benefits, and was in accordance with the engineering contracts strategy.
7. In 2016 asset management engineering reviewed the market in the London area and engaged with the current contractor to consider how future services should be delivered. They concluded it would be beneficial to procure two separate contracts that group entry systems and warden call into one contract and fire safety systems and equipment into another, as this reflects market specialisation.
8. The door entry and warden call services are weighted heavily towards responsive repairs, whereas fire systems and equipment services are weighted to planned cyclical maintenance and inspection. These differences require different organisational structures to deliver services efficiently and effectively.
9. The responsive door entry and warden call services can be delivered by general electrical contractors that have the appropriate call centre facilities. The fire systems and equipment sector is a niche market, where skilled maintenance engineers are scarce. General electrical contractors struggle to recruit and retain competent fire systems and equipment staff.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Cabinet (decommissioned, for the Executive after at Southwark and we tell you when its next papers are published, before the meeting rather than after it.
Review of Void Disposal StrategyThat the progress of disposals of void housing properties since April 2009 be noted. 2. That the importance of void d...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.