Gateway 1 - Procurement Strategy Approval Proposed expansion of Rotherhithe Primary School
ApprovedExecutive1 paper
AI summarySouthwark Cabinet approved a £2,200,000 design services contract and an £18,000,000 main works contract, including contingency, for Rotherhithe Primary School, and delegated Gateway 2 decisions. [D]
Written from the decision and the officer reportPDF Pro
OutcomeApprovedPagabo design services and EU restricted main works [P52][P74][P80][P85]
Money£2,200,000, £18,000,000, £20,200,000 [D][P5][P11]Design services, construction with contingency, and secured budget [P2][P3][P11]
What happens nextGateway 2 decisions delegated [D]Strategic director of children’s and adults’ services [D]
Who it affectsRotherhithe Primary School [P10]Expansion from two form entry to four form entry [P10]
What was decided
The professional services and design team contract was approved at an estimated value of £2,200,000 for 52 months.
The main works contract for construction was approved at an estimated value of £18,000,000, including contingency, for 22 months.
Gateway 2 decisions for the project were delegated to the strategic director of children’s and adults’ services.
Why
Pupil projections show a strong need for more places. The scheme would expand the school from two form entry to four form entry. Report P10, P18
The existing building is past its lifespan, leaks, and has poor insulation. Refurbishment was ruled out because it would not offer value for money, and the report proposes a new building before demolishing the original. Report P20, P24, P25
Pagabo scored highest for professional services, while the EU restricted procedure scored highest for main works. The restricted procedure was expected to widen competition and balance cost certainty, programme certainty and design quality. Report P52, P74, P75, P76, P77
What happens next
Procure the design team through Pagabo Lot 1 and run a mini competition for architectural practices. The preference was to invite up to six practices with relevant educational design experience. Report P44, P45, P83, P84
Procure the main works contractor through a full OJEU restricted tender. The council would publish notices in OJEU and Contracts Finder, assess expressions of interest and invite selected contractors to tender. Report P86, P89, P124
The appointed design team is expected to lead detailed design under a JCT traditional contract with council amendments, subject to Gateway 2. Report P87
The money
£2,200,000 Professional services and design team contract over 52 months, including ancillary costs Report P2, P162
£18,000,000 Main works construction contract over 22 months, including contingency Report P3, P16, P166
£20,200,000 Secured budget for redevelopment and expansion Report P5, P11
£77m 2018/19 general fund capital financing yet to be identified Report P184
£0.2m Scheme budget phase for 2016/17 Report P181
£3m Scheme budget phase for 2017/18 Report P181
£8.5m Scheme budget phase for 2018/19 Report P181
£8.5m Scheme budget phase for 2019/20 Report P181
Options considered
Chosen: Pagabo Lot 1 for professional services. It scored highest, provides one point of supply and allows a mini competition for the design team. Report P44, P45, P52, P80
Chosen: EU restricted procedure for main works. It scored highest and was expected to widen competition while balancing cost, programme and design quality. Report P65, P66, P74, P75, P76, P77, P85
Rejected: Greater London Authority and Transport for London design panel. Only two of its 12 architect practices had substantial experience designing primary schools. Report P39, P40, P41
Rejected: OJEU for professional services. It had the highest design quality score but low programme and administration scores, and would take longer and use more resources. Report P46, P47, P48, P51
Rejected: Southern Construction Framework Lot 3 for main works. Council experience found budget and programme difficult to manage, with risk transferred to the council and design quality reduced. Report P57, P58, P59
Rejected: Pagabo construction framework. It favours a partnership, design and build approach and has similar drawbacks to the Southern Construction Framework. Report P60, P62
Rejected: Scape Major Works framework. It has a sole supplier, so the council is unlikely to achieve best value for money because competition is limited. Report P63, P64
Rejected: Education Funding Agency Regional Framework. The council considered it unlikely to deliver the required building quality when the main contractor leads design. Report P68, P69, P70, P71
Implications
Financial: The council is forward funding the scheme while awaiting a 2019/20 basic need capital grant allocation. If the grant does not become available in 2019/20, council resources would need to be identified. Report P182
Financial: The capital programme is significantly over committed, with over £144m of financing still to be identified and £77m for 2018/19. Accurate forecasting and monitoring are therefore paramount. Report P184
Risk: The construction phase has a medium risk of exceeding the council budget. A quantity surveyor, clear design briefing and a fully measured bill of quantities are planned controls. Report P101, P102
Risk: The construction phase has a medium risk of delay in obtaining planning consent. Early informal consultation and time for local consultation, planning advice and design review are planned. Report P103, P104
Legal: The professional team appointment would use an existing EU compliant Pagabo framework, avoiding a separate tender. The main works contract would be advertised through OJEU, and the Public Contract Regulations 2015 would apply. Report P79, P191, P192
Equalities: The new facilities are intended to be accessible regardless of age, disability, faith or religion, gender, race or ethnicity and sexual orientation. The council must have due regard to the Public Sector Equality Duty at each stage. Report P132, P194, P195, P197
Climate: The council aspires to BREEAM Very Good. Whole life costs, robust materials, sound insulation and environmentally considerate heating and cooling are to be built into the brief. Report P148, P150
Staffing: The works contractor is expected to provide at least 18 apprentices, and the professional services provider at least two. Both must ensure staff are paid the London Living Wage. Report P139, P142, P143
Who and where
Current and future pupils at Rotherhithe Primary School Report P8, P10, P18
Local residents in the school catchment Report P18, P174
People needing accessible school and community facilities Report P24, P132
Local businesses Report P140
Apprentices and trainees Report P139, P146
Professional services and construction staff Report P142, P143
School staff involved in developing the design brief Report P173
Users of the planned multi use games area Report P145
30/03/2017: Invitation to tender for professional services Report P113
10/07/2017 and 12/07/2017: Professional services contract award and start Report P114, P115
25/07/2018: Invitation to tender for the main works contract Report P118
25/10/2018: Gateway 2 contract award report approval Report P118
07/11/2018 and 07/12/2018: Main works contract award and start Report P118, P119
07/8/2020: Main works contract completion Report P119
01/12/2021: Professional services contract completion Report P115
Plain English for the jargon
Gateway 1: The Cabinet decision approving the procurement strategy for the two school contracts. [P1][P2][P3]
Gateway 2: The later contract award decision, delegated to the strategic director. [D][P4][P114][P118]
2FE and 4FE: The school’s stated intake measure, changing from two form entry to four form entry. [P8][P10]
Pagabo: A public sector procurement framework for construction related services and works. [P43][P62]
OJEU: The Official Journal of the European Union, where the main works contract notice would be published. [P124]
EU restricted procedure: A tender process that assesses expressions of interest before inviting selected firms to tender. [P89][P128]
JCT traditional contract: A construction contract under which the appointed design team leads the detailed design. [P67][P87]
BREEAM: The environmental rating used for the new building, with a council aspiration of at least Very Good. [P148]
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item14
Resolved
That professional services and the design team contract for Rotherhithe Primary School at an estimated value of £2,200,000 for a period of 52 months be approved . 2. That the main works contractor for the construction of Rotherhithe Primary School at an estimated value of £18,000,000 including contingency for a period of 22 months be approved. 3. That gateway 2 decisions for this project be delegated to the strategic director of children’s and adults’ services.
Word for word from the decision Southwark published for this meeting.Source: moderngov.southwark.gov.uk
Report to Cabinet (decommissioned, for the Executive after, 21 pages
Recommendations
That Cabinet approve the strategies outlined in this report for the procurement of:
1. Professional services and the design team contract for Rotherhithe Primary School at an estimated value of £2,200,000 for a period of 52 months.
2. The main works contractor for the construction of Rotherhithe Primary School at an estimated value of £18,000,000 including contingency for a period of 22 months.
3. That the cabinet agrees to delegate gateway 2 decisions for this project to the strategic director of children’s and adult’s services. BACKGROUND INFORMATION
4. At the meeting on 1 November 2016, Cabinet agreed to secure a budget of £20,200,000 for the redevelopment and expansion of Rotherhithe Primary School on the existing site.
5. Rotherhithe School was rated “Good” in a 2014 Ofsted inspection.
6. The current school building at Rotherhithe was constructed over 40 years ago. The existing building occupies a large footprint on the site, comprising a single storey prefabricated building.
7. The school is currently a 2 form entrance (FE) primary school, with a nursery. There is a separate provision of a day nursery and children’s centre on site.
8. The school is keen to expand and has currently taken on several bulge classes to help alleviate the current lack of available school places in the area.
9. The proposed works will enable the school to expand from a 2FE to 4 FE in a modern building.
10. The secured budget for the scheme is £20,200,000.
11. The professional services, design team fees and ancillary costs for the scheme are estimated to be in the region of £2,200,000.
13. The estimated construction costs of this scheme will be approximately £18,000,000 including contingency over a period of 22 months.
Summary of the business case/justification for the procurement
14. Pupil placement projections indicate a strong need to provide additional school places in this catchment area. The school is a popular community school on a generous site, which make this school ideal for expansion.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Cabinet (decommissioned, for the Executive after at Southwark and we tell you when its next papers are published, before the meeting rather than after it.
Review of Void Disposal StrategyThat the progress of disposals of void housing properties since April 2009 be noted. 2. That the importance of void d...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.