Gateway 1 - Procurement Strategy Approval Proposed expansion of Rotherhithe Primary School

Approved Executive 1 paper

AI summarySouthwark Cabinet approved a £2,200,000 design services contract and an £18,000,000 main works contract, including contingency, for Rotherhithe Primary School, and delegated Gateway 2 decisions. [D]

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedPagabo design services and EU restricted main works [P52][P74][P80][P85]
Money£2,200,000, £18,000,000, £20,200,000 [D][P5][P11]Design services, construction with contingency, and secured budget [P2][P3][P11]
What happens nextGateway 2 decisions delegated [D]Strategic director of children’s and adults’ services [D]
Who it affectsRotherhithe Primary School [P10]Expansion from two form entry to four form entry [P10]

What was decided

The professional services and design team contract was approved at an estimated value of £2,200,000 for 52 months.

The main works contract for construction was approved at an estimated value of £18,000,000, including contingency, for 22 months.

Gateway 2 decisions for the project were delegated to the strategic director of children’s and adults’ services.

Why

Pupil projections show a strong need for more places. The scheme would expand the school from two form entry to four form entry. Report P10, P18

The existing building is past its lifespan, leaks, and has poor insulation. Refurbishment was ruled out because it would not offer value for money, and the report proposes a new building before demolishing the original. Report P20, P24, P25

Pagabo scored highest for professional services, while the EU restricted procedure scored highest for main works. The restricted procedure was expected to widen competition and balance cost certainty, programme certainty and design quality. Report P52, P74, P75, P76, P77

What happens next

Procure the design team through Pagabo Lot 1 and run a mini competition for architectural practices. The preference was to invite up to six practices with relevant educational design experience. Report P44, P45, P83, P84

Procure the main works contractor through a full OJEU restricted tender. The council would publish notices in OJEU and Contracts Finder, assess expressions of interest and invite selected contractors to tender. Report P86, P89, P124

The appointed design team is expected to lead detailed design under a JCT traditional contract with council amendments, subject to Gateway 2. Report P87

The money

  • £2,200,000 Professional services and design team contract over 52 months, including ancillary costs Report P2, P162
  • £18,000,000 Main works construction contract over 22 months, including contingency Report P3, P16, P166
  • £20,200,000 Secured budget for redevelopment and expansion Report P5, P11
  • £77m 2018/19 general fund capital financing yet to be identified Report P184
  • £0.2m Scheme budget phase for 2016/17 Report P181
  • £3m Scheme budget phase for 2017/18 Report P181
  • £8.5m Scheme budget phase for 2018/19 Report P181
  • £8.5m Scheme budget phase for 2019/20 Report P181

Options considered

  • Chosen: Pagabo Lot 1 for professional services. It scored highest, provides one point of supply and allows a mini competition for the design team. Report P44, P45, P52, P80
  • Chosen: EU restricted procedure for main works. It scored highest and was expected to widen competition while balancing cost, programme and design quality. Report P65, P66, P74, P75, P76, P77, P85
  • Rejected: Greater London Authority and Transport for London design panel. Only two of its 12 architect practices had substantial experience designing primary schools. Report P39, P40, P41
  • Rejected: OJEU for professional services. It had the highest design quality score but low programme and administration scores, and would take longer and use more resources. Report P46, P47, P48, P51
  • Rejected: Southern Construction Framework Lot 3 for main works. Council experience found budget and programme difficult to manage, with risk transferred to the council and design quality reduced. Report P57, P58, P59
  • Rejected: Pagabo construction framework. It favours a partnership, design and build approach and has similar drawbacks to the Southern Construction Framework. Report P60, P62
  • Rejected: Scape Major Works framework. It has a sole supplier, so the council is unlikely to achieve best value for money because competition is limited. Report P63, P64
  • Rejected: Education Funding Agency Regional Framework. The council considered it unlikely to deliver the required building quality when the main contractor leads design. Report P68, P69, P70, P71

Implications

  • Financial: The council is forward funding the scheme while awaiting a 2019/20 basic need capital grant allocation. If the grant does not become available in 2019/20, council resources would need to be identified. Report P182
  • Financial: The capital programme is significantly over committed, with over £144m of financing still to be identified and £77m for 2018/19. Accurate forecasting and monitoring are therefore paramount. Report P184
  • Risk: The construction phase has a medium risk of exceeding the council budget. A quantity surveyor, clear design briefing and a fully measured bill of quantities are planned controls. Report P101, P102
  • Risk: The construction phase has a medium risk of delay in obtaining planning consent. Early informal consultation and time for local consultation, planning advice and design review are planned. Report P103, P104
  • Legal: The professional team appointment would use an existing EU compliant Pagabo framework, avoiding a separate tender. The main works contract would be advertised through OJEU, and the Public Contract Regulations 2015 would apply. Report P79, P191, P192
  • Equalities: The new facilities are intended to be accessible regardless of age, disability, faith or religion, gender, race or ethnicity and sexual orientation. The council must have due regard to the Public Sector Equality Duty at each stage. Report P132, P194, P195, P197
  • Climate: The council aspires to BREEAM Very Good. Whole life costs, robust materials, sound insulation and environmentally considerate heating and cooling are to be built into the brief. Report P148, P150
  • Staffing: The works contractor is expected to provide at least 18 apprentices, and the professional services provider at least two. Both must ensure staff are paid the London Living Wage. Report P139, P142, P143

Who and where

  • Current and future pupils at Rotherhithe Primary School Report P8, P10, P18
  • Local residents in the school catchment Report P18, P174
  • People needing accessible school and community facilities Report P24, P132
  • Local businesses Report P140
  • Apprentices and trainees Report P139, P146
  • Professional services and construction staff Report P142, P143
  • School staff involved in developing the design brief Report P173
  • Users of the planned multi use games area Report P145

Timeline

  • 21/03/2017: Gateway 1 procurement strategy approval Report P113, P118
  • 30/03/2017: Invitation to tender for professional services Report P113
  • 10/07/2017 and 12/07/2017: Professional services contract award and start Report P114, P115
  • 25/07/2018: Invitation to tender for the main works contract Report P118
  • 25/10/2018: Gateway 2 contract award report approval Report P118
  • 07/11/2018 and 07/12/2018: Main works contract award and start Report P118, P119
  • 07/8/2020: Main works contract completion Report P119
  • 01/12/2021: Professional services contract completion Report P115

Plain English for the jargon

  • Gateway 1: The Cabinet decision approving the procurement strategy for the two school contracts. [P1][P2][P3]
  • Gateway 2: The later contract award decision, delegated to the strategic director. [D][P4][P114][P118]
  • 2FE and 4FE: The school’s stated intake measure, changing from two form entry to four form entry. [P8][P10]
  • Pagabo: A public sector procurement framework for construction related services and works. [P43][P62]
  • OJEU: The Official Journal of the European Union, where the main works contract notice would be published. [P124]
  • EU restricted procedure: A tender process that assesses expressions of interest before inviting selected firms to tender. [P89][P128]
  • JCT traditional contract: A construction contract under which the appointed design team leads the detailed design. [P67][P87]
  • BREEAM: The environmental rating used for the new building, with a council aspiration of at least Very Good. [P148]
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item14

Resolved

That professional services and the design team contract for Rotherhithe Primary School at an estimated value of £2,200,000 for a period of 52 months be approved . 2. That the main works contractor for the construction of Rotherhithe Primary School at an estimated value of £18,000,000 including contingency for a period of 22 months be approved. 3. That gateway 2 decisions for this project be delegated to the strategic director of children’s and adults’ services.
Word for word from the decision Southwark published for this meeting. Source: moderngov.southwark.gov.uk

Follow this further

Built from Southwark's papers

What the report saysPro

Report to Cabinet (decommissioned, for the Executive after, 21 pages

Recommendations

That Cabinet approve the strategies outlined in this report for the procurement of:

1. Professional services and the design team contract for Rotherhithe Primary School at an estimated value of £2,200,000 for a period of 52 months.

2. The main works contractor for the construction of Rotherhithe Primary School at an estimated value of £18,000,000 including contingency for a period of 22 months.

3. That the cabinet agrees to delegate gateway 2 decisions for this project to the strategic director of children’s and adult’s services. BACKGROUND INFORMATION

4. At the meeting on 1 November 2016, Cabinet agreed to secure a budget of £20,200,000 for the redevelopment and expansion of Rotherhithe Primary School on the existing site.

5. Rotherhithe School was rated “Good” in a 2014 Ofsted inspection.

6. The current school building at Rotherhithe was constructed over 40 years ago. The existing building occupies a large footprint on the site, comprising a single storey prefabricated building.

7. The school is currently a 2 form entrance (FE) primary school, with a nursery. There is a separate provision of a day nursery and children’s centre on site.

8. The school is keen to expand and has currently taken on several bulge classes to help alleviate the current lack of available school places in the area.

9. The proposed works will enable the school to expand from a 2FE to 4 FE in a modern building.

10. The secured budget for the scheme is £20,200,000.

11. The professional services, design team fees and ancillary costs for the scheme are estimated to be in the region of £2,200,000.

12. The required design team includes:

 Architect  Structural engineer  Civil engineer  Mechanical engineer  Electrical engineer  Project manager / contract administrator / employer’s agent  Quantity Surveyors  Principal Designer  BREEAM advisor  * Planning Consultant  * Approved building inspector

* denotes in-house appointment by the council

13. The estimated construction costs of this scheme will be approximately £18,000,000 including contingency over a period of 22 months.

Summary of the business case/justification for the procurement

14. Pupil placement projections indicate a strong need to provide additional school places in this catchment area. The school is a popular community school on a generous site, which make this school ideal for expansion.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Report: Gateway 1: Procurement Strategy Approval Proposed expansion of Rotherhithe Primary SchoolReport 21 pages DownloadRead as text

At this meeting

Whole meeting
3Notice of Intention to conduct business in a closed meeting, and any representations receivedOn the agenda 6MinutesApproved 7Deputation RequestsDecided 8Cultural Strategy Refresh 'Creative Southwark 2017 to 2022'Agreed 9Approval to go out to Public Consultation for the Introduction of Public Space Protection Orders (PSPOs) to Tackle Dog Related Anti-Social Behaviour (ASB)Approved 10Customer Access Strategy RefreshNoted 11Gateway 1- Procurement Strategy Approval: Door Entry and Warden Call ContractApproved 12Response to Central London Area Based Review of Skills 2016Noted 13Passmore Centre Investment PlanNoted
14Gateway 1 - Procurement Strategy Approval Proposed expansion of Rotherhithe Primary SchoolThis decision
15Gateway 2 - Contract Award Approval - The Charter School East Dulwich (TCSED) - Phase 1 works contractApproved 16Gateway 1 - Procurement Strategy Approval Southwark Regeneration in Partnership Programme Procurement Approval - Lot AApproved 17Southwark Regeneration in Partnership Programme Lot B Sites AppropriationApproved 1857 Elliotts Row, SE11, 9 Faunce Street, SE17, 24 Woodwarde Road SE22 - Disposal of Freehold interestsDecided 19Agreement of the Heads of Terms for the grant of a long leasehold interest in refurbished space to be provided at Maydew House and surrender of premises at Abbeyfield Road, SE16Approved 20Commercial Property Portfolio: Addition of Income Generating AssetsNoted 21Authorisation of Debt Write-off over £50,000 for Chief Executives Department, Commercial RentApproved 22Exclusion of the Press and PublicDecided 25Commercial Property Portfolio: Addition of Income Generating AssetsOn the agenda

Who was there

11 of 12 attended
PJ
Councillor Peter John OBEChair, present
SC
Councillor Stephanie CryanCommittee Member, present
FC
Councillor Fiona ColleyCommittee Member, present
BH
Councillor Barrie HargroveCommittee Member, present
RL
Councillor Richard LivingstoneCommittee Member, present
VM
Councillor Victoria MillsCommittee Member, present
JS
Councillor Johnson SituCommittee Member, present
MW
Councillor Mark WilliamsCommittee Member, present
IW
Councillor Ian WingfieldCommittee Member, present
MA
Councillor Maisie AndersonCommittee Member, apologies
EK
Eleanor KellyOfficer, present
DF
Doreen Forrester-BrownOfficer, present

On this subject at Southwark

Search all
  1. Gateway 1 - Procurement Strategy Approval Proposed expansion of Rotherhithe Primary SchoolThis decision
  2. Gateway 1 – Procurement Strategy Approval -The NestApproved
  3. Gateway 1 - Procurement Strategy Approval - Southwark and Lambeth Barristers FrameworkApproved
  4. Gateway 1 - Procurement Strategy Approval - Framework contracts to provide bailiff services to the Revenues & Benefits and Parking ServicesApproved
  5. Gateway 2: Contract Award Approval - Corporate Insurance Procurement (excluding Property Insurance)Approved
  6. Gateway 1 - Initial Procurement Strategy, Parking and Traffic Enforcement Services ContractAgreed

More from Southwark Cabinet (decommissioned, for the Executive after

All decisions
MeetingDecisionOutcome
28 May 2026 Election of Chair for the meetingThat Councillor Maisie Anderson be elected chair for this meeting. Decided Open
28 May 2026 Notification of any items of business which the chair deems urgentIt was agreed that all the deputations would be heard so that consideration of these representations could be given p... Agreed Open
28 May 2026 Disclosure of Interests and DispensationsDecision Maker (IDM) report in respect of this issue. Councillor Peter John also declared a personal, non prejudicial... Decided Open
28 May 2026 Review of Void Disposal StrategyThat the progress of disposals of void housing properties since April 2009 be noted. 2. That the importance of void d... Noted Open
28 May 2026 Housing Revenue Account - Approval of Housing Revenue Budget Account 2011/12That the savings required to deliver a balanced housing revenue account (HRA) for 2011/12 be noted. 2. That the propo... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies