Thurrock Council
Cabinet, Wednesday 17 December 2014 at 7.00pm

2014/15 Capital Monitoring Report, (Decision: 01104337)

Noted Executive 5 papers

Cabinet noted this item on Wednesday 17 December 2014. Below is the council's own wording, with the papers it was decided on.

Item76

Resolved

That it be noted the General Fund Capital Programme is projected to have unused resources of £3.693m as at 31 March 2015 although this is likely to be carried forward to 2015/16 to fund schemes currently being developed or work in progress. 2. That the virements within the Children’s service, totalling £1.616m, which will realign project budgets with projected costs, be approved. 3. That it be noted the Housing Revenue Account Capital Programme is projected to have no unused resources in 2014/15. Reason for Decision - as stated in the report This decision is subject to call-in
Word for word from the decision Thurrock published for this meeting. Source: democracy.thurrock.gov.uk

Follow this further

Built from Thurrock's papers

What the report saysPro

Report to Cabinet

Executive summary

At its meeting on 12 February 2014, Cabinet agreed the 2014/15 capital programme.

Since the 1st April 2014, additional funding has been added to the programme, funded from various sources (i.e. environmental trusts and section 106). In addition the budget carry forwards from 2013/14, have also been added to the programme.

This report pulls all of the changes together and sets out the latest forecasted outturn position.

Capital budgets cannot contribute to the General Fund revenue position although officers ensure that all appropriate capitalisations occur.

1. Recommendation(s)

That Cabinet agrees:

1.1To note that the General Fund Capital Programme is projected to have unused resources of £3.693m as at 31 March 2015 although this is likely to be carried forward to 2015/16 to fund schemes currently being developed or work in progress;

1.2To approve the virements within the Children’s service, totalling £1.616m, which will realign project budgets with projected costs; 1.3 To note that the Housing Revenue Account Capital Programme is projected to have no unused resources in 2014/15.

2. Introduction and Background

2.1This report provides an update to Cabinet on the financial position of the Capital programme and highlights significant variances. It is the first monitoring report for 2014/15 and is based on expenditure at month 7 (April to October) and projected expenditure for the remainder of the year.

2.2Capital schemes and resources are distinguished over two specific categories:

• Mainstream Schemes – Capital expenditure that is funded by supported or unsupported (prudential) borrowing, by capital receipts, from the Revenue Budget or from earmarked reserves.

• Specific Schemes – Capital expenditure that is funded by external funding sources, for example, Government Grants and Section 106 monies that can only be spent on specific projects.

3. General Fund Schemes

3.1Appendix 1 sets out the Capital Programme at Month 7 showing the movement since the start of the financial year and the resources that are available to finance the programme.

3.2The current position for General Fund Schemes for 2014/15 is summarised in Table 1 and analysed in further detail within Appendix 2.

Table 1: Capital Programme – Projected Outturn Current Projected Variance Agreed Outturn As Against Budget At Budget As At Month 7 Month 7 Expenditure: £000’s £000’s £000’s Children’s Service (Note: the schools capital budget is designed around academic years 21,672 18,020 (3,652) and officers are confident that this will be defrayed in full within the current academic year). Adult Social Care 150 137 (13) Environment 2,220 2,250 30 Planning and Transportation 5,797 5,759 (38) Housing General Fund 2,033 2,244 211 Current Projected Variance Agreed Outturn As Against Budget At Budget As At Month 7 Month 7 Commercial Services 476 459 (17) Transformation 4,772 4,786 14 Chief Executive Delivery Unit 11,112 10,884 (228)

Total Expenditure (see appendix 2) 48,232 44,539 (3,693)

Resources: Mainstream (22,193) (22,283) (90) Specific (26,039) (22,256) 3,783

Total Resources (48,232) (44,539) 3,693

Forecast Deficit in Resources 0 0 0

3.3Table 1 is showing that the projected outturn for the year is £44.539m which is £3.693m less than the latest agreed budget for the year. 3.4 The forecast variance is further analysis in Table 2

Table 2: – Analysis of forecast variance Forecast Re-profiling Capital Completed variance of schemes Projects against expenditure requiring budget at at additional Month 7 Month 7 funding

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
2014/15 Capital Monitoring Report, (Decision: 01104337)Decisions 71 KB DownloadRead as text
PDF
2014-15 Capital Monitoring ReportAppendix 1 50 KB Download
PDF
2014-15 Capital Monitoring ReportAppendix 2 259 KB Download
PDF
2014-15 Capital Monitoring ReportAppendix 3 26 KB Download
PDF
2014-15 Capital Monitoring ReportAppendix 4 20 KB Download

At this meeting

Whole meeting
64MinutesOn the agenda 68Mid Year Corporate Progress and Performance Report 2014-15Noted 69Review of the Council's Senior Management StructureOn the agenda 73Community Transport Review (Decision: 01104334)Agreed 74Borrowing and Investment Performance and Policy Review 2013/14 and 2014/15 Mid Year Report (Decision: 01104335)Approved 75Revenue Monitoring Report 2014/15, (Decision: 01104336)Noted
762014/15 Capital Monitoring Report, (Decision: 01104337)This decision
77Local Council Tax Support Scheme, (Decision: 01104338)Decided 78Budget 2015/16 - Proposed Fees And Charges, (Decision: 01104339)Decided 79Shaping the Council and Budget Progress Update, (Decision: 01104340)On the agenda 80School Capital Programme Update (Decision: 01104341)Noted 81Thames Gateway South Essex Partnership update (Decision: 01104342)Noted 82Highways Maintenance Efficiency Programme -Strategic Review and Recommendations for Improvement (Decision: 01104343)Noted 83Depot Relocation and Procurement of Buildings (Decision: 01104344)Approved 84Grays South and Rail Station Regeneration (Decision: 01104345)Approved 85Grays Town Centre Transport Study (Decision: 01104346)Approved 86Thames Estuary Festival (Decision: 01104347)Agreed 87Purfleet Centre Regeneration Programme (Decision: 01104348)Noted 88Responsive Repairs and Maintenance Policy (Decision: 01104349Approved 89Repairs and Maintenance Contract Award (Decision: 01104350)Approved 90Progress Report on Housing Estate Regeneration and Local Growth Fund Bids (Decision: 01104351)Approved 91Progress on Gloriana - Proposed Development of St. Chad's Site, Tilbury and Belmont Road Site, Grays (Decision: 01104352)Approved

Who was there

5 of 13 attended
JK
Councillor John KentChair, present
BR
Councillor Barbara RiceVice-Chair, present
TF
Councillor Tony FishCommittee Member, present
VH
Councillor Victoria HollowayCommittee Member, present
BO
Councillor Bukky OkunadeCommittee Member, absent
PS
Councillor Philip SmithCommittee Member, apologies
LW
Councillor Lynn WorrallCommittee Member, present as substitute
GF
Graham FarrantOfficer, in attendance
SC
Steve CoxOfficer, in attendance
BB
Barbara BrownleeOfficer, in attendance
DB
David BullOfficer, in attendance
CL
Carmel LittletonOfficer, in attendance

All 13 on the meeting page

On this subject at Thurrock

Search all
  1. 2014/15 Capital Monitoring Report, (Decision: 01104337)This decision
  2. Revenue Capital Budget Monitoring Report Q2 2024-25Noted
  3. Q3 Monitoring Forecast Revenue and Capital Outturn 23/24Noted
  4. 2018/19 Capital Monitoring Report - Quarter 3Noted
  5. 2018/19 Capital Monitoring ReportNoted
  6. 2017/18 Capital Monitoring Report - Quarter 3 (Decision 0110466)Noted

More from Thurrock Cabinet

All decisions
MeetingDecisionOutcome
16 Sep 2026 Corporate and Improvement Plan - 2025/26 Quarter 4 and End of Year Performance Report and Annual Report3.1 Cabinet Noted the quarterly Corporate Performance Report at Appendix 1 and consider which performance issues Cabi... Noted Open
16 Sep 2026 Thurrock Transport Strategy Adoption2.1 Cabinet approved the Thurrock Transport Strategy given in Appendix 1 to be progressed to Full Council for adoptio... Approved Open
16 Sep 2026 Proposed Changes to the Essex Coast Recreational Disturbance Avoidance and Mitigation Strategy (RAMS) and Tariff2.1 Cabinet approved the £476 RAMS tariff, as set out in section 9.1 of the Cabinet report; 2.2 Cabinet agreed to wit... Approved Open
16 Sep 2026 High Priority Housing Policies - Housing Adaptations Policy2.1 Cabinet agreed the Council’s Housing Adaptations Policy in Appendix 1 to commence with effect from 1 October 2026... Agreed Open
16 Sep 2026 Matrix Agency Worker 1 year contract extension2.1 Cabinet agreed to utilise the one-year extension option contained within the current contract and extend the exis... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies