Grays Town Centre Transport Study (Decision: 01104346)

Approved Executive 2 papers

Cabinet approved this item on Wednesday 17 December 2014. Below is the council's own wording, with the papers it was decided on.

Item85

Resolved

That the package of measures which have been developed through the Grays Town Centre Transport Study and additional supporting documents – as set out in Appendix 1, be endorsed. 2. That the development and implementation of the focused package of experimental measures (as set out in Paragraph 3.4) that will address key access issues in Grays while enabling the Council to test proposals and discuss them with relevant users and stakeholders, be approved. 3. That authority be delegated to the Director for Planning & Transportation in consultation with the Leader of the Council, to initiate a consultation and review process that will be reported to Planning & Regeneration Overview & Scrutiny and make local changes to the proposed measures taking into account local views and priorities. Reason for Decision - as stated in the report This decision is subject to call-in
Word for word from the decision Thurrock published for this meeting. Source: democracy.thurrock.gov.uk

Follow this further

Built from Thurrock's papers

What the report saysPro

Report to Cabinet

Executive summary

In 2013 the Council developed an integrated multi-modal transport strategy for Grays town centre. This piece of work looked at existing and future transport issues which need to be addressed to support forecast growth and planned regeneration, including new development such as the South Essex College Thurrock Campus, Grays Magistrates Court, Hogg Lane South and the proposed rail station/underpass development in Grays South.

This work was developed around the regeneration vision for Grays and subsequent supporting work relating to the delivery of an underpass and public squares which is the subject of a separate report to this meeting.

The 2013 strategy identified the need for a more focused approach to be undertaken. This resulted in the development of the Grays Town Centre Access Study (August 2014) which identified a comprehensive package of measures to be considered for implementation which will deliver step-change improvements in terms of access and amenity, supporting Grays asa key destination for learning, business and investment.

The report sets out how the Planning and Transportation Directorate will utilise available funding to develop and deliver the initial phase of works , and how additional future funding allocations might be used to support the longer term vision for the town centre. 1. Recommendation(s)

That Cabinet:

1.1Endorse and support the package of measures which have been developed through the Grays Town Centre Transport Study and additional supporting documents – as set out in Appendix 1.

1.2Approve the development and implementation of the focused package of experimental measures (as set out in Paragraph 3.4) that will address key access issues in Grays while enabling the Council to test proposals and discuss them with relevant users and stakeholders.

1.3Agree to delegate authority to the Director for Planning & Transportation in consultation with the Leader of the Council, to initiate a consultation and review process that will be reported to Planning & Regeneration Overview & Scrutiny and make local changes to the proposed measures taking into account local views and priorities.

2. Introduction and Background

2.1In July 2013 Cabinet received a report outlining an exciting vision for the future of Grays; (at the time) one of five Growth Hubs identified within the Council’s Community Regeneration Strategy and Local Development Framework. The vision, which was created following significant public and stakeholder engagement, was approved by Cabinet.

2.2The report took the opportunity to outline the scale of ambition for Grays and update on progress in securing the delivery of the first of the projects which will generate this growth. With the South Essex College Thurrock Campus having opened in September 2014 and work started on the refurbishment of Grays Magistrates Court, there is a clear momentum building behind the regeneration of Grays. Further projects, include proposals to redevelop Hogg Lane South and potential future redevelopment of the rail station. A separate report to this meeting sets out progress on work required for provision of an underpass at the level crossing and surrounding public squares.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Grays Town Centre Transport StudyAppendix 1 2.4 MB Download
PDF
Grays Town Centre Transport Study (Decision: 01104346)Decisions 49 KB DownloadRead as text

At this meeting

Whole meeting
64MinutesOn the agenda 68Mid Year Corporate Progress and Performance Report 2014-15Noted 69Review of the Council's Senior Management StructureOn the agenda 73Community Transport Review (Decision: 01104334)Agreed 74Borrowing and Investment Performance and Policy Review 2013/14 and 2014/15 Mid Year Report (Decision: 01104335)Approved 75Revenue Monitoring Report 2014/15, (Decision: 01104336)Noted 762014/15 Capital Monitoring Report, (Decision: 01104337)Noted 77Local Council Tax Support Scheme, (Decision: 01104338)Decided 78Budget 2015/16 - Proposed Fees And Charges, (Decision: 01104339)Decided 79Shaping the Council and Budget Progress Update, (Decision: 01104340)On the agenda 80School Capital Programme Update (Decision: 01104341)Noted 81Thames Gateway South Essex Partnership update (Decision: 01104342)Noted 82Highways Maintenance Efficiency Programme -Strategic Review and Recommendations for Improvement (Decision: 01104343)Noted 83Depot Relocation and Procurement of Buildings (Decision: 01104344)Approved 84Grays South and Rail Station Regeneration (Decision: 01104345)Approved
85Grays Town Centre Transport Study (Decision: 01104346)This decision
86Thames Estuary Festival (Decision: 01104347)Agreed 87Purfleet Centre Regeneration Programme (Decision: 01104348)Noted 88Responsive Repairs and Maintenance Policy (Decision: 01104349Approved 89Repairs and Maintenance Contract Award (Decision: 01104350)Approved 90Progress Report on Housing Estate Regeneration and Local Growth Fund Bids (Decision: 01104351)Approved 91Progress on Gloriana - Proposed Development of St. Chad's Site, Tilbury and Belmont Road Site, Grays (Decision: 01104352)Approved

Who was there

5 of 13 attended
JK
Councillor John KentChair, present
BR
Councillor Barbara RiceVice-Chair, present
TF
Councillor Tony FishCommittee Member, present
VH
Councillor Victoria HollowayCommittee Member, present
BO
Councillor Bukky OkunadeCommittee Member, absent
PS
Councillor Philip SmithCommittee Member, apologies
LW
Councillor Lynn WorrallCommittee Member, present as substitute
GF
Graham FarrantOfficer, in attendance
SC
Steve CoxOfficer, in attendance
BB
Barbara BrownleeOfficer, in attendance
DB
David BullOfficer, in attendance
CL
Carmel LittletonOfficer, in attendance

All 13 on the meeting page

On this subject at Thurrock

Search all
  1. Grays Town Centre Transport Study (Decision: 01104346)This decision
  2. Grays Town Fund - Grays Riverfront Public Realm & Flood Defence: Design & Build Contract Award, and External FundingApproved
  3. Update on Grays/Tilbury Towns Board (deferred from 3 December 2024)Decided
  4. Tilbury and Grays Towns Fund Update - to followDecided
  5. Grays Town Fund Programme (Decision: 110623)Approved
  6. Grays Town Centre: Civic Offices Project (Decision 0110442)Decided

More from Thurrock Cabinet

All decisions
MeetingDecisionOutcome
16 Sep 2026 Corporate and Improvement Plan - 2025/26 Quarter 4 and End of Year Performance Report and Annual Report3.1 Cabinet Noted the quarterly Corporate Performance Report at Appendix 1 and consider which performance issues Cabi... Noted Open
16 Sep 2026 Thurrock Transport Strategy Adoption2.1 Cabinet approved the Thurrock Transport Strategy given in Appendix 1 to be progressed to Full Council for adoptio... Approved Open
16 Sep 2026 Proposed Changes to the Essex Coast Recreational Disturbance Avoidance and Mitigation Strategy (RAMS) and Tariff2.1 Cabinet approved the £476 RAMS tariff, as set out in section 9.1 of the Cabinet report; 2.2 Cabinet agreed to wit... Approved Open
16 Sep 2026 High Priority Housing Policies - Housing Adaptations Policy2.1 Cabinet agreed the Council’s Housing Adaptations Policy in Appendix 1 to commence with effect from 1 October 2026... Agreed Open
16 Sep 2026 Matrix Agency Worker 1 year contract extension2.1 Cabinet agreed to utilise the one-year extension option contained within the current contract and extend the exis... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies