That the award of the five (5) year contract for Repairs and Maintenance to Mears Ltd be approved, as the Mears bid submission based on a combined price and quality assessment obtained the highest overall scores, resulting in them being the preferred supplier following a fully compliant OJEU procurement. 2. That it be noted the contract term will be for an initial duration of five (5) years subject to satisfactory performance. 3. That it be noted the contract term is extendable at the sole discretion of the Council for a further period or periods up to and including five (5) years either as a single extension or by any number of individual extensions for a period of one year or more making a total possible Term of ten (10) years. Reason for Decision - as stated in the report This decision is not subject to call-in (Chapter 4, Part 3, paragraph 10.14 (d)).
Word for word from the decision Thurrock published for this meeting.Source: democracy.thurrock.gov.uk
This report sets out the procurement analysis and recommendation for the award of the Councils Repairs & Maintenance contract. The current contract for Repairs and Maintenance will end in January 15. At present the housing repairs and maintenance service is provided under an interim contract with Mears.
This report, and associated appendices, provides an overview of the process the Council has undertaken to ensure that it is able to deliver an enhanced responsive repair service that offers long term benefits to residents along with value for money. The service will be delivered through a partnering arrangement with recommended bidder, Mears Ltd, who submitted the most competitive bid. The bid includes substantial, local, deliverable commitments along with some key enhancements that are a direct result of listening to residents throughout the tendering process.
1. Recommendation(s)
It is recommended that cabinet:
1.1Approve the award of the five (5) year contract for Repairs and Maintenance to Mears Ltd as the Mears bid submission based on a combined price and quality assessment obtained the highest overall scores, resulting in them being the preferred supplier following a fully compliant OJEU procurement.
1.2Note the contract term will be for an initial duration of five (5) years subject to satisfactory performance. 1.3 Note the contract term is extendable at the sole discretion of the Council for a further period or periods up to and including five (5) years either as a single extension or by any number of individual extensions for a period of one year or more making a total possible Term of ten (10) years.
2. Introduction and Background
2.1Background to procurement
The Council first outsourced its responsive repairs service in 2010 in a contract with Morrison’s. Following a period of two years of service provision, it had become apparent that performance of the contractor was poor, and their approach to rectifying performance was unacceptable. Due to substantial failings on the part of the service provider, the Council terminated the Morrison’s contract in December 2012. Negotiation of termination was made in such a way as to proceed without legal dispute or settlement claim.
Since January 2013, the council has been in an interim arrangement with Mears Ltd. The interim contract was established, with improved client contract management, in a way that enforced a robust contract performance management framework. Through the introduction of robust contract, governance measurements, the Council working with Mears Ltd has seen substantial increase in resident satisfaction and increased value for the services delivered.
At the end of the 13/14 financial year, 14 months into the interim contract, a number of indicators showed significant improvements, including:
• In April 2013, emergency & urgent repairs accounted for 55% of demand, this had fallen to 48% by March 2014. • In April 2013, all performance targets for repairs completed in time were failed (emergency 91%, urgent 60%, routine 68%), by March 2014 these had improved to 99%, 96% and 98% respectively. • In April 2013, there were 7.7 complaints per thousand repairs, in comparison by March 2014 there were just 2.9 complaints per thousand repairs issued
The procurement for a new Repairs & Maintenance contract follows this period of interim provision, the associated improvements in performance, learning gained through improvements in client contract management and the implementation of a robust performance management framework.
The contract award for the Councils Repairs and Maintenance contract addresses:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Thurrock Transport Strategy Adoption2.1 Cabinet approved the Thurrock Transport Strategy given in Appendix 1 to be progressed to Full Council for adoptio...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.