Planning, Transport, Regeneration Overview and Scrutiny Committee decided this item on Tuesday 7 March 2017. Below is the council's own wording, with the papers it was decided on.
RESOLVED That the Planning Transport and Regeneration Overview and Scrutiny Committee are asked to comment on the approach to managing the delivery of the Grays South Project including; a) The division of roles which proposes that Network Rail lead technical design and construction of the underpass, access ramps and steps (elements which are on sensitive operational land) while the Council lead land assembly and design ... view the full minutes text for item 38.
Word for word from the decision Thurrock published for this meeting.Source: democracy.thurrock.gov.uk
Report to Planning, Transport, Regeneration Overview and Scrutiny Committee
Executive summary
The Grays South Project aims to transform Grays town centre, creating public squares and an underpass to replace the pedestrian level crossing in Grays High Street together with the development of modern retail and residential units.
The Council has been working with Network Rail to develop the proposals over the past four years. Network Rail continues to support the project through design and their approvals processes however it has become apparent that they are unable to offer significant funding towards delivery of the scheme.
In order to progress the project the Council will have to meet most of the costs of the project. A funding strategy has been developed drawing upon the existing commitments within the capital programme, available s106 funds and anticipated receipts from future developments of other sites owned by the Council around the town centre.
In addition, on the 2nd February 2017 the Council received notification that its bid for £10.8 million from the Local Growth Fund had been successful and that the Council would receive the full amount requested to complete the funding package to deliver the Grays South Project.
Given the ongoing discussion with Network Rail and the recent announcement of funding to support the project the Council is reviewing how we deliver the scheme and seeks the views of the Committee about the approach that is proposed. 1. Recommendation(s)
1.1Planning Transport and Regeneration Overview and Scrutiny Committee are asked to comment on the approach to managing the delivery of the Grays South Project including;
a) The division of roles which proposes that Network Rail lead technical design and construction of the underpass, access ramps and steps (elements which are on sensitive operational land) while the Council lead land assembly and design of the public realm;
b) The terms on which the Council will agree to this division of roles as set out in paragraph 3.6 of this report;
c) The funding strategy which is based on current commitments in the capital programme, S106 funds, use of development receipts from Council land, and the grant from the Local Growth Fund;
d) Land assembly based on an approach that keeps land acquisition to the minimum necessary and is based on negotiated settlement with Compulsory Purchase used as a last resort.
2. Introduction and Background
2.1The Grays South Project aims to transform Grays town centre, creating public squares and an underpass to replace the pedestrian level crossing in Grays High Street together with the development of modern retail and residential units.
2.2The recent announcement that the Council will receive c£10.8 million from the Local Growth Fund in 2019/20 and 2020/21 completes the funding package required to deliver the Grays South Project.
2.3The Grays South Project is a key part of delivering the Council’s strategy for the long term regeneration of Grays.
2.4In September 2016 Overview and Scrutiny Committee received a report which outlined an approach to delivering the scheme. Subsequent discussions with Network Rail have led to a revision of the approach which is explained in this report.
3. Issues, Options and Analysis of Options
3.1This section considers delivery of the underpass under the following headings;
a) Scope of the scheme and approach to delivery b) Funding Strategy c) Land Assembly d) Delivery Programme
Scope of the scheme and approach to delivery
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Planning, Transport, Regeneration Overview and Scrutiny Committee at Thurrock and we tell you when its next papers are published, before the meeting rather than after it.
Regeneration Projects Update - to follow1.1 That the committee notes the proposed changes to the original programmes and the progress on delivering the Regen...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.