Resolved
That the Planning Transport Regeneration Overview and Scrutiny Committee noted and comments on the information provided relating to the Stanford le Hope Interchange project.
Planning, Transport, Regeneration Overview and Scrutiny Committee noted this item on Monday 6 July 2020. Below is the council's own wording, with the papers it was decided on.
Resolved
That the Planning Transport Regeneration Overview and Scrutiny Committee noted and comments on the information provided relating to the Stanford le Hope Interchange project.
This report is provided at the Chair’s request in order to inform Members on the following specific matters relating to the SLH scheme and in particular:
A review of the original scheme design, costs incurred, overspend figures and any delays Consideration of the revised proposal for the station and the car park
The recent pause and reflect exercise has meant that the revised scheme has been developed in consultation with key stakeholders, local residents and ward councillors resulting in a much improved scheme for the local community, incorporating all of the key benefits identified whilst providing much needed additional parking for commuters and local residents since the loss of the King Street car park.
1.1That the Planning Transport Regeneration Overview and Scrutiny Committee notes and comments on the information provided relating to the Stanford le Hope Interchange project.
2. Introduction and Background
2.1This scheme involves the construction of new station buildings with footbridge and lifts, passenger information system, bus turnaround facility, passenger drop-off points and cycle parking.
2.2There are a number of stakeholders involved in the scheme including UK Power Networks, C2C, Network Rail and the Port of London Authority and it will be delivered under a Development Agreement with C2C, who are the principal land owner.
2.3Since the last update to the PTR Overview & Scrutiny Committee in January 2020, a pause and reflect exercise has been undertaken to identify a deliverable and cost effective replacement station which can deliver the criteria set out in the approved business case.
2.4Some works have been undertaken on site including the demolition of the existing station building (March 2019), the provision of a temporary ticket office on the station car park site, platform gate lines have been installed and some changes to the car park layout to improve pedestrian safety.
2.5A report on this project is due to be considered at the Standards and Audit Committee on 9th July 2020 to respond to questions asked by the Chair.
3. Issues, Options and Analysis of Options
Original design, costs, over spend and any delays
Original design:
3.1The original preliminary design of the scheme with a cantilevered deck and podium proved to be a complex and expensive design to deliver. The original design was being driven by a list of requirements which had been committed to as part of the business case to secure funding and in particular included a bus turnaround facility in the station forecourt area.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Stanford-le-Hope Interchange ReportReport | 152 KB | DownloadRead as text |
Follow Planning, Transport, Regeneration Overview and Scrutiny Committee at Thurrock and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 21 Feb 2024 | ITB Capital Programme 2024/251.1 That the Committee provide comments on the 2024/25 Integrated Transport Block capital programme allocations and p... | Agreed | Open |
| 21 Feb 2024 | Tilbury and Grays Towns Fund Update - to follow1.1 That the Committee notes the proposed changes to the original programmes and the progress on delivering the Tilbu... | Decided | Open |
| 21 Feb 2024 | Regeneration Projects Update - to follow1.1 That the committee notes the proposed changes to the original programmes and the progress on delivering the Regen... | Decided | Open |
| 17 Oct 2023 | Thurrock Scheduled Ancient Monuments: Assessment of Settings - April 2023That the Planning, Transportation and Regeneration Overview and Scrutiny Committee note and provide comment on the Th... | Decided | Open |
| 17 Oct 2023 | East Tilbury (Bata Village) & Corringham Conservation Areas Character Appraisal and Management Plans - April 2023That the Planning, Transport and Regeneration Overview and Scrutiny Committee notes and comments on the East Tilbury ... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.