This report is provided at the Committee’s request to have a quarterly update on the SLH project. This report and future reports will focus on the latest progress in delivery of the scheme, any changes in the agreed programme and any changes in the out turn forecast
1. Recommendation(s)
1.1That the Standards and Audit Committee notes and comments on the report content.
2. Introduction and Background
2.1This scheme involves the construction of new station buildings with footbridge and lifts, passenger information system, bus turnaround facility, passenger drop-off points and cycle parking.
2.2There are a number of stakeholders involved in the scheme including UK Power Networks, C2C, Network Rail and the Port of London Authority and it will be delivered under a Development Agreement with C2C, who are the principal land owner.
2.3There have been a number of issues with the project which culminated in a pause and review of the scheme. The reasons for that have been discussed and considered in previous reports to both this committee and PTR O&S.
2.4Since that review, many positive changes have been made to the scheme which have created a greater level of certainty on its deliverability and a much improved, high quality scheme.
3. Issues, Options and Analysis of Options
Progress
3.1A single Option concept design has been developed and reviewed by all key stakeholders. A consolidated list of comments has been compiled and the designers will now progress the design adding Architectural details.
3.2Changes to the design have meant that there is a need to resubmit a planning application for the station site as soon as possible. Each phase of the design development is shared with Thurrock Council Planners and a Full Planning Application will be submitted as soon as Architectural Details are agreed. Working in parallel, a team of designers is working on the development of the scheme for the Transport Hub Phase 2 which is well advanced.
3.3A report is due to be considered at Cabinet on16 September 2020 to obtain authority to procure a main works contractor as soon as possible. Specialist legal procurement and contract advice has been sought to build in to a strategy going forward to address members concerns raised about cost control on major projects.
3.4The project steering group is continuing to meet on a monthly basis, to share information and ideas and obtain feedback on progress to ensure this infrastructure is coming forward with the agreement of stakeholders and local residents. So far, all the feedback has been very positive.
Programme
3.5An updated programme is currently being worked up to reflect the time required to prepare a full OJEU compliant tender process. This will include the preparation of tender documentation, prequalification of bidders, the tender process, through to tender evaluation and award.
3.6Subject to the procurement process, it is anticipated that Phase 1 of the works will be delivered within the current programmed completion date of Summer 2021 with the Phase 2 works following in quick succession.
3.7At the moment, there are no impacts from Covid 19 affecting the progress of this project but Covid remains a live issue and impacts may arise once works begin again on site. This will be monitored and kept under review.
Budget
3.8The table below shows the funding sources for the project:
Source £ SELEP 7,500,000 London Gateway (DPW) 550,000 NSIP (Network Rail) 3,050,000 C2C 737,000 Other S106 contributions 1,533,000 Council 5,720,000 TOTAL 19,090,000
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Stanford Le Hope Transport ProjectReport | 144 KB | DownloadRead as text |
Follow Standards and Audit Committee at Thurrock and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 21 Mar 2024 | Internal Audit Charter 20241.1 That the Standards and Audit Committee approve the (Appendix 1) and the Chair of the Standards and Audit Committe... | Approved | Open |
| 21 Mar 2024 | Internal Audit Protocol- Item to follow1.1 That the Standards and Audit Committee agree that the Internal Audit Protocol provides the Council and the Intern... | Agreed | Open |
| 21 Mar 2024 | Committee on Standards in Public Life Update1.1 Note the content of report of the Committee on Public Life’s report Leading in Practice (Appendix 1), and conside... | Noted | Open |
| 29 Feb 2024 | Internal Audit Progress Report1.1 Note the progress to 11 January 2024 against the Audit Plan 2023/24 as documented in Appendix 1. 1.2 Consider the... | Noted | Open |
| 29 Feb 2024 | Future Arrangements for the Standards and Audit Committee1.1 To consider the options set out in this report and recommend a preferred option for inclusion in the Annual Counc... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.