Resolved
That the Planning Transport Regeneration Overview and Scrutiny Committee noted and commented on the information provided relating to the Stanford le Hope Interchange project.
Planning, Transport, Regeneration Overview and Scrutiny Committee noted this item on Tuesday 8 December 2020. Below is the council's own wording, with the papers it was decided on.
Resolved
That the Planning Transport Regeneration Overview and Scrutiny Committee noted and commented on the information provided relating to the Stanford le Hope Interchange project.
This report is provided at the Chair’s request in order to inform Members of an update on the SLH scheme.
1. Recommendation(s)
1.1That the Planning Transport Regeneration Overview and Scrutiny Committee notes and comments on the information provided relating to the Stanford le Hope Interchange project.
2. Introduction and Background
2.1This scheme involves the construction of new station buildings with footbridge and lifts, passenger information system, bus turnaround facility, passenger drop-off points and cycle parking.
2.2There are a number of stakeholders involved in the scheme including UK Power Networks, C2C, Network Rail and the Port of London Authority and it will be delivered under a Development Agreement with C2C, who are the principal land owner.
2.3Since the last update to the PTR Overview & Scrutiny Committee in July 2020, significant progress has been made to move the project forward. Most of this work has been behind the scenes getting the project ready for physical delivery on site. The exception is that there have been works undertaken to clear vegetation and invasive species from both banks of the River Hope.
2.4A report was considered by Standards and Audit Committee on 24 November 2020 in relation to this project.
3. Issues, Options and Analysis of Options
Progress:
3.1The Concept Design for the station has been completed and passed Inter Disciplinary Review with very positive feedback. The Design will be ready to go to Planning by publication of this report.
3.2The concept design for the Phase 2 Transport Hub is in development and a workshop is planned for November to share some suggested configurations with the key Stakeholders including London Gateway DPW and c2c.
3.3Invitations to tender have been sent out to 11 potential Principal Contractors within an existing Thurrock Council Framework Agreement. We expect some Companies will decline to participate, as they will fail to meet Network Rail criteria. However, we fully expect to get sufficient Letters of Interest to carry out a meaningful tender.
3.4The project steering group is continuing to meet on a monthly basis, to share information and ideas and obtain feedback on progress to ensure this infrastructure is coming forward with the agreement of stakeholders and local residents. So far, all the feedback has been very positive.
Budget
3.5It has been agreed with the designers that a high level “estimated project” cost evaluation exercise be carried out at two “checkpoints” through the design process, once when the full concept is agreed and a further check at final design approval, to give further certainty and to give some indicative numbers in support of the tender evaluation process
Programme
3.6An updated programme is currently being worked up to reflect the time required to prepare a full OJEU compliant tender process. This will include the preparation of tender documentation, prequalification of bidders, the tender process, through to tender evaluation and award.
3.7Subject to the procurement process, it is anticipated that Phase 1 of the works will be delivered within the current programmed completion date of Summer 2021 with the Phase 2 works following in quick succession.
3.8At the moment, there are no impacts from Covid 19 affecting the progress of this project but Covid remains a live issue and impacts may arise once works begin again on site. This will be monitored and kept under review.
4.1To respond to the Chair’s request for information on Stanford-le-Hope Interchange project.
5. Consultation (including Overview and Scrutiny, if applicable)
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Stanford-le-Hope Interchange ReportReport | 142 KB | DownloadRead as text |
Follow Planning, Transport, Regeneration Overview and Scrutiny Committee at Thurrock and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 21 Feb 2024 | ITB Capital Programme 2024/251.1 That the Committee provide comments on the 2024/25 Integrated Transport Block capital programme allocations and p... | Agreed | Open |
| 21 Feb 2024 | Tilbury and Grays Towns Fund Update - to follow1.1 That the Committee notes the proposed changes to the original programmes and the progress on delivering the Tilbu... | Decided | Open |
| 21 Feb 2024 | Regeneration Projects Update - to follow1.1 That the committee notes the proposed changes to the original programmes and the progress on delivering the Regen... | Decided | Open |
| 17 Oct 2023 | Thurrock Scheduled Ancient Monuments: Assessment of Settings - April 2023That the Planning, Transportation and Regeneration Overview and Scrutiny Committee note and provide comment on the Th... | Decided | Open |
| 17 Oct 2023 | East Tilbury (Bata Village) & Corringham Conservation Areas Character Appraisal and Management Plans - April 2023That the Planning, Transport and Regeneration Overview and Scrutiny Committee notes and comments on the East Tilbury ... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.