Adoption of the Essex Joint Air Quality Strategy

Agreed Executive 5 papers

AI summaryThurrock Cabinet adopts the All Essex Air Quality Strategy jointly with Essex County Council and Southend, replacing the expired local plan and meeting a statutory duty.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeAgreedJoint strategy with ECC and Southend formally adopted
MoneyNo new costDelivered within existing resources
What happens nextImplementation through joint consortiumContinued participation in Essex Air Quality Consortium
Who it affectsThurrock residents, especially near 18 AQMAsAir quality across the borough

What was decided

Cabinet formally adopted the All Essex Air Quality Strategy as local policy, as originally approved in November 2024. Report 2.1, P2

The decision fulfils the council's statutory duty under the Environment Act 2021 to produce an Air Quality Action Plan, after Thurrock's previous plan expired. Report 4.2, 4.3

The decision is subject to call-in.

Why

Thurrock has 18 Air Quality Management Areas and its previous Air Quality Action Plan has expired, so a new plan is legally required. Report 4.2

Air pollution is cross-boundary; a joint strategy is expected to improve access to Defra Air Quality Fund, which Thurrock has historically struggled to secure. Report 4.6, 4.7, P1

Public consultation in early 2025 showed 82% of respondents felt improving air quality was important and 83% supported the strategy's vision. Report P16, P17, 6.2

What happens next

Officers will continue to participate in the Essex Air Quality Consortium, with regular governance meetings to keep Thurrock's needs represented. Report 9.6, P26

Any future projects needing extra funding will go through the council's usual governance process, including bids for external funds such as the Defra Air Quality Fund. Report 7.3, 7.4

The preliminary equality impact assessment prepared by ECC will be updated to assess conditions for Thurrock residents. Report P41

Options considered

  • Chosen: Adopt the joint All Essex Air Quality Strategy. Fulfils statutory duty, costs nothing, improves funding prospects and allows cross-boundary working Report 4.3, 4.6, 4.7, 5.1
  • Rejected: Recommenced work on Thurrock's own draft Air Quality Action Plan. Would miss the opportunities of joint working and external funding Report 5.1

Implications

  • Legal: Meets the statutory duty to review and assess air quality and to publish an air quality strategy under the Environment Act 1995 and 2021; reduces risk of judicial review or regulator criticism. Report 9.1, 9.3, P32, P33
  • Financial: No new spending required; future project costs would go through normal governance, with possible external funding streams opened up. Report 7.1, 7.2, 7.3, 7.4
  • Risk: Limited risk; mitigated through regular partner meetings and senior officer oversight so Thurrock is not left behind. Report 8.1, P26
  • Equalities: Expected positive impact on protected characteristics and health outcomes, with a preliminary equality impact assessment to be updated. Report P41
  • Other: Strengthens reputational position by showing a coordinated, collaborative approach across Essex. Report 9.7, P34

Who and where

  • Thurrock residents, particularly those living in or near the 18 Air Quality Management Areas Report 4.2, 6.2, P18
  • Southend and Essex County Council, as joint partners in the strategy Report P1, 4.6
  • Officers in Thurrock's Community Protection and Public Health teams Report 6.1, P45

Timeline

  • November 2024: Thurrock Cabinet approved progressing with an Essex-wide Air Quality Strategy Report P1, 2.1
  • Early 2025: Public consultation on the joint Air Quality Strategy was held Report 6.2
  • 3 February 2026: Finance implications verified by Head of Finance Business Partnering (Place and Corporate Services) Report 7.4
  • 4 February 2026: Risk implications verified by the Risk Manager Report P27, P28
  • 12 February 2026: Legal implications verified by the Principal Lawyer (Litigation) Report P39
  • 14 February 2026: Equality and diversity implications verified by the Head of Community Development Report P42, P43
  • 18 March 2026: Cabinet formally adopts the All Essex Air Quality Strategy Report 2.1

Plain English for the jargon

  • AQS: All Essex Air Quality Strategy, the joint strategy document covering air quality
  • AQAP: Air Quality Action Plan, the plan setting out actions to improve air quality within an AQMA
  • AQMA: Air Quality Management Area, a statutory designation for areas exceeding national air quality objectives
  • ECC: Essex County Council, lead authority in producing the joint strategy
  • Defra: Department for Environment, Food and Rural Affairs, which runs the main external air quality grant fund
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item335

Resolved

2.1 Cabinet agreed to formally adopt the Strategy as local policy, as originally approved at Cabinet in November 2024. Reason for the decision: as outlined in the report This decision is subject to call-in
Word for word from the decision Thurrock published for this meeting. Source: democracy.thurrock.gov.uk

Follow this further

Built from Thurrock's papers

What the report saysPro

Report to Cabinet

Executive summary

In November 2024, Cabinet was presented and approved a recommendation to progress with an ‘Essex Wide Air Quality Strategy’. The process of which has been ongoing and in-line with that Cabinet decision, Thurrock, Southend and Essex County Council’s (ECC’s) have worked together to produce the “All Essex Air Quality Strategy” (AQS), a document that contains an Air Quality Action Plan (AQAP). Adopting the joint Strategy would fulfil our statutory obligation to produce and AQAP. It would also: facilitate cross-boundary participation in managing air pollution, which is a cross-boundary issue; make it more likely that we would be successful in securing external funding (e.g. Defra Air Quality Fund), which is something we have struggled to do in the past; and streamline delivery of our statutory obligations in local air quality management. The final version of the AQS has been published.

Recommendations

For the reasons set out in this report, the Cabinet is recommended to:

2.1Formally adopts the Strategy as local policy, as originally approved at Cabinet in November 2024.

3. Commissioner’s Comments

3.1Commissioners have been consulted on the content of this report and agree with the recommendations made. 4. Proposals – the rationale and evidence for the recommendations

4.1Under Part IV of the Environment Act (2021), local authorities have a responsibility to monitor and manage local air quality. If an LA finds an area where pollution is monitored or modelled to exceed the health-based concentration thresholds (AKA. the national air quality objectives), the Act requires that they declare an Air Quality Management Area (AQMA). The AQMA is a statutory designation that gives an LA the justification for actions to improve air quality within and adjacent to the designated area. As part of the designation, an LA must produce an AQAP outlining the actions it intends to take to bring air quality within the AQMA back into compliance with the national air quality objectives. An Annual Status Report must be produced to update on progress to that end. The AQAP must be remade every five years.

4.2Thurrock currently has 18 AQMAs. Our most recent AQAP (the Air Quality and Health Strategy) has expired. Therefore, a new AQAP must be adopted, in line with the requirements of the Environment Act.

4.3Adopting the joint AQS would fulfil our statutory obligation in this regard by providing us with a high-quality Strategy that has been written by external consultants at no cost to Thurrock. Actions within the joint AQS are non- specific by necessity because they must be adaptable to the specific needs of each participating borough. This allows Thurrock the flexibility to tailor actions to meet the specific needs of our residents.

4.4The draft actions within the joint AQS are split into four overarching “proposals”:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Adoption of the Essex Joint Air Quality StrategyReport 149 KB DownloadRead as text
PDF
Essex Air Quality Strategy 2025Appendix 1 5 MB Download
PDF
Essex Air Quality Strategy (Action Plan)Appendix 2 1.3 MB Download
PDF
Essex Air Quality Strategy (Supporting Information)Appendix 3 4.7 MB Download
PDF
Completed Equalities Comprehensive Impact Assessment: Essex Air Quality StrategyReport 67 KB Download

At this meeting

Whole meeting

Who was there

7 of 21 attended
LW
Councillor Lynn WorrallChair, present
LW
Councillor Lee WatsonVice-Chair, present
VH
Councillor Vikki HartsteanCommittee Member, present
LH
Councillor Lynda HeathCommittee Member, present
VH
Councillor Victoria HollowayCommittee Member, present
MH
Councillor Mark HooperCommittee Member, present
JK
Councillor John KentCommittee Member, present
VM
Councillor Valerie Morris-CookCommittee Member, apologies
MB
Mark BradburyOfficer, in attendance
PC
Paul CrickOfficer, in attendance
CD
Claire DemmelOfficer, in attendance
DF
Daniel FenwickOfficer, in attendance

All 21 on the meeting page

On this subject at Thurrock

Search all
  1. Adoption of the Essex Joint Air Quality StrategyThis decision
  2. Adoption of the Essex Coast Recreational Disturbance Avoidance & Mitigation Strategy Supplementary Planning Document and Partnership Agreement (Decision: 110556)Approved

More from Thurrock Cabinet

All decisions
MeetingDecisionOutcome
16 Sep 2026 Corporate and Improvement Plan - 2025/26 Quarter 4 and End of Year Performance Report and Annual Report3.1 Cabinet Noted the quarterly Corporate Performance Report at Appendix 1 and consider which performance issues Cabi... Noted Open
16 Sep 2026 Thurrock Transport Strategy Adoption2.1 Cabinet approved the Thurrock Transport Strategy given in Appendix 1 to be progressed to Full Council for adoptio... Approved Open
16 Sep 2026 Proposed Changes to the Essex Coast Recreational Disturbance Avoidance and Mitigation Strategy (RAMS) and Tariff2.1 Cabinet approved the £476 RAMS tariff, as set out in section 9.1 of the Cabinet report; 2.2 Cabinet agreed to wit... Approved Open
16 Sep 2026 High Priority Housing Policies - Housing Adaptations Policy2.1 Cabinet agreed the Council’s Housing Adaptations Policy in Appendix 1 to commence with effect from 1 October 2026... Agreed Open
16 Sep 2026 Matrix Agency Worker 1 year contract extension2.1 Cabinet agreed to utilise the one-year extension option contained within the current contract and extend the exis... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies