Written from the decision and the officer reportPDF Pro
OutcomeAgreedProposals endorsed; ITT design delegated; contracts return to Cabinet
MoneyUp to £8.5m over four yearsAdjusted for inflation from contract start
What happens nextInvitation to Tender in May 2026Go live planned for March 2027
Who it affectsAll wards, young people 16 to 25Looked after children, care leavers, former UASC, homeless
What was decided
Cabinet endorsed the proposals to recommission supported accommodation for young people aged 16 to 25 through a new framework or dynamic market.
Cabinet delegated decisions on the design of the Invitation to Tender to the Executive Director of Children Services, in consultation with the lead member.
Officers must return to Cabinet for approval of the contract award before any arrangement is made with external providers.
Why
Spot purchasing, used since the previous framework ended in March 2025, is not sustainable and gives poor value for money.
Some care experienced young people have struggled to reach full independence despite weekly targeted support, so a wider range of provision is needed.
The procurement is high value, crosses Children, Adult and Housing services, and must be designed to remain workable after Local Government Reorganisation. Report 3.2
What happens next
Analyse and plan work continues until April 2026, with the Invitation to Tender issued in May to June 2026 and evaluation in July to August 2026. Report P14, P15, P16, P17, P18, P19, P20
Officers will return to Cabinet in September 2026 with contract award recommendations. Report P21
Ofsted registration of provision and go live are scheduled between October 2026 and March 2027. Report P22, P23, P24, P25, P26, P27
The money
£8.5m Maximum estimated council spend over four years on contracts awarded through this recommissioning, adjusted for inflation Report P9
£1.5m Current 2025/26 budget for the service
£2.1m Projected spend at Quarter 3 2025/26
£0.6m Current annual funding gap, expected to be closed by better value and wider housing options from the new contract
Options considered
Rejected: Continue with spot purchasing as the route to market. Inefficient and does not secure provision designed around the needs of Thurrock children Report P29
Chosen: Decide route to market for each home type: closed framework, open framework, dynamic market, or in-house delivery. Decisions to be taken during the design phase, informed by market understanding, provider input and partners such as Fostering Report P29
Implications
Financial: A £0.6m annual funding gap is expected to be met through better value and a wider range of housing options from the new arrangements.
Legal: The services are classed as Light Touch under the Procurement Act 2023 and must comply with the Council's Contract Procedure Rules and Finance Procedure Rules. Report P31
Legal: Statutory duties arise under section 20 of the Children Act 1989, the Care Planning, Placement and Care Review Regulations 2010, the Children and Social Work Act 2017, and the Housing Act 1996. Report P31, P32
Equalities: A Community Equality Impact Assessment will be carried out during the design phase and will treat care experience as a category for impact. Report P33
Risk: Thurrock's small demand may limit market interest; mitigation includes joint commissioning with Essex or Southend, early provider engagement, and considering in-house delivery. Report P30
Risk: Ofsted registration delays of six to 18 months could postpone new provision, requiring case by case judgement on suitable accommodation. Report P30
Other: Contracts must be drafted to allow for change of contracting authority and contract changes arising from Local Government Reorganisation. Report 3.2
Who and where
Looked after children aged 16 and 17 Report P9, P31
Care leavers aged 16 to 25, including former unaccompanied asylum seeking children Report P9, P31, P32
Homeless young people aged 16 to 25 Report P9, P32
January 2026: Analyse: consultation, co-production, needs analysis Report P14
February 2026: Analyse: develop specification and ITT Report P15
March 2026: Analyse: continue planning Report P16
April 2026: Analyse: continue planning Report P17
May 2026: Do: Invitation to Tender issued Report P18
June 2026: Do: Invitation to Tender period Report P19
July 2026: Do: evaluation of tenders Report P20
August 2026: Do: evaluation of tenders Report P20
September 2026: Do: return to Cabinet for contract award decisions Report P21
October 2026 to February 2027: Do: Ofsted registration of providers Report P22, P23, P24, P25, P26
March 2027: Go live: new contracts start Report P27
Plain English for the jargon
UASC: Unaccompanied asylum seeking children
HMO: House in Multiple Occupation, a property rented out by at least three tenants from more than one household
ITT: Invitation to Tender, the formal request for suppliers to bid for a contract
Dynamic market: A procurement route that stays open for new suppliers to join at any time; previously called a Dynamic Purchasing System
Light Touch regime: A procurement regime under the Procurement Act 2023 that applies to certain health, social and other services, with more flexible rules
KPI: Key Performance Indicator, a measurable target used to judge how well a service is performing
LGR: Local Government Reorganisation, restructuring of local authorities
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item341
Resolved
2.1 Cabinet endorsed the proposals set out in this report. 2.2 Cabinet agreed to delegate decisions concerning the design of the ITT through the arrangements described in this report, to the Executive Director of Children Services following consultation with the lead member for children services. 2.3 Cabinet agreed to require that Officers present their recommendations for the award of new contracts, to Cabinet for their decision, prior to entering into any arrangement with external providers.
Word for word from the decision Thurrock published for this meeting.Source: democracy.thurrock.gov.uk
Report to Cabinet Report Title Accommodation and Support Pathway for 16–25: Looked After Children, Care Leavers, Former UASC and Homeless Young People Date of Meeting 18 March 2026
Report Author James Purdie, Head of Commissioning for Childrens Services Corporate Director Sheila Murphy, Executive Director Childrens Services
Lead Cabinet Member(s) Councillor Vikki Hartstean
Why is this a key 1. Expenditure over £500K yes decision? 2. Significant impact on 2 or more wards yes
Wards Affected All wards could be affected by this matter
Identify exempt information and exemption category
Is report Urgent? No
Reasons for urgency (only where applicable)
Appendices (if any) None 1. Executive Summary This report describes how Children’s Services are going to recommission supported accommodation (SA) for young people aged 16 to 25. The intention is to commission a range of provision, including supported lodgings, group living with 24/7 staffing, group living with part time staffing, independent living with floating support. All types of provision for 16 / 17 year olds will be registered with OFSTED. To achieve this, we will work with Housing to ensure that this new provision compliments their existing offer to this cohort of young people. We will also work with Adult Services to ensure that this offer to young people with additional needs is consistent with the Thurrock Council Supported Housing Strategy (2025 - 2035). The Commissioning exercise will focus on securing supported accommodation that promotes young people’s development whilst also offering excellent value for money. The estimated value of Thurrock Council expenditure on these services, over four years for any contracts awarded through these arrangements, is £8.5m. Cabinet is asked to agree to the recommissioning of services as set out in this report and also to agree to spend in relation to these same services up to a maximum of £8.5m adjusted for inflation over a four year period from the start date of the contract. 2. Recommendations For the reasons set out in this report, the Cabinet is recommended to: 2.1 Endorse the proposals set out in this report. 2.2 To delegate decisions concerning the design of the ITT through the arrangements described in this report, to the Executive Director of Children Services following consultation with the lead member for children services. 2.3 To require that Officers present their recommendations for the award of new contracts, to Cabinet for their decision, prior to entering into any arrangement with external providers. 3. Commissioner’s Comments 3.1 The procurement seeks to commission accommodation and accommodation- based support for young people’s and will cut across Children’s, Adults and Housing in ensuring it support a seamless transition throughout a young person’s journey to independent living, improve provision, deliver stable homes and secure better value.
3.2The procurement will require collaboration, innovation and could be complex. It is high value, with expenditure currently outside its designated budget and a degree of risks. The decision is required to return to Cabinet for approval to ensure strategic alignment, legal and statutory compliance, impact and outcomes is fully understood, risks managed and financial accountability. This procurement will initiate contracts designed to remain effective following Local Government Reorganisation (LGR) and as such must allow for change of identity of contracting authority and changes to the contract, if the LGR arrangements necessitate.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Thurrock Transport Strategy Adoption2.1 Cabinet approved the Thurrock Transport Strategy given in Appendix 1 to be progressed to Full Council for adoptio...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.