Cabinet, Wednesday 18 March 2026 at 7.00pm

Procurement of Waste Treatment and Haulage Contracts

Approved Executive 1 paper

AI summaryThurrock Cabinet approves procurement of waste treatment and haulage services as a single contract, with a three year initial term from 13 December 2026 and an option to extend by up to two more years.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedSingle contract for waste treatment and haulage
MoneyNot stated
What happens nextProcurement process to beginContract start date 13 December 2026
Who it affectsWaste services and residentsStatutory collection and disposal duties

What was decided

Cabinet approved procurement of Waste Treatment and Haulage Services as a single contract, for an initial three year term from 13 December 2026, with an option to extend for up to two additional years.

Cabinet delegated authority to the Executive Director of Place, in consultation with the Chief Finance Officer, Head of Legal and the Cabinet Member for Place and Environment, to set the price and quality split and to approve the start of procurement.

The decision is subject to call-in.

Why

As a unitary authority, the council must carry out waste collection and disposal duties under sections 45, 46 and 51 of the Environmental Protection Act 1990, and the procured services will enable the council to meet these statutory functions. Report P6

Officers set the contract length to allow for local government reform: an initial three year term with up to two years extension, and a right to novate the contract to any successor authority or terminate for convenience. Report P6

What happens next

Procurement will be run in line with the Procurement Act 2023, with the contract, award notice and performance key performance indicators published as required. Report P6

A Communities and Equality Impact Assessment will be completed before the contract is awarded to identify and mitigate any impacts on protected groups. Report P9

The new contract is due to commence on 13 December 2026 and will initially run until 12 December 2029. Report P6

Implications

  • Legal: The contract is above threshold under the Procurement Act 2023 and must comply with the full legislative regime, including publication of notices, the awarded contract and performance key performance indicators. Report P6
  • Legal: Depending on the final scope, TUPE may operate by law to transfer incumbent provider staff to any successful bidder, and bidders will be advised on pricing this risk. Report P6
  • Risk: Risk that there is no adequate resource to keep procurement to time, leading to delays, increased costs and compliance risks, mitigated by a recruited contract manager and identified project support (residual status: Amber). Report P1
  • Risk: Risk of weak market interest in the three service types, which could force reliance on a single supplier; mitigated by ongoing market engagement (residual status: Amber). Report P2
  • Risk: Risk that bid costs exceed allocated budgets, potentially requiring extra funding or reallocation; mitigated by opening the opportunity to the market to ensure price competition (residual status: Amber). Report P3
  • Risk: Failure to procure within agreed budgets could breach internal financial controls and risk delivery of the council's statutory duty to dispose of waste. Report P4
  • Equalities: A Communities and Equality Impact Assessment will be completed before the contract is awarded, with measures put in place to mitigate any negative impacts on protected groups. Report P9
  • Other: The specification will need to reflect upcoming changes including the Emissions Trading Scheme, the Deposit Return Scheme, Extended Producer Responsibility, Simpler Recycling, local government reform and devolution. Report P6

Who and where

  • Thurrock Council as unitary authority, carrying out waste collection and disposal duties Report P6
  • Residents receiving waste collection and disposal services Report P6
  • Staff of the incumbent service provider, who may transfer under TUPE Report P6
  • Any successor authority created by local government reform Report P6
  • Potential bidders in the procurement process Report P2, P3

Timeline

  • 14/01/2026: Risk implications verified by the Risk Manager Report P5
  • 19/01/2026: Equality implications verified by the Team Manager Report P10
  • 03/02/2026: Legal implications verified Report P8
  • 18/03/2026: Cabinet decision to approve procurement
  • 13/12/2026: New contract due to commence Report P6
  • 12/12/2029: End of initial three year contract term Report P6

Plain English for the jargon

  • TUPE: Transfer of Undertakings (Protection of Employment) regulations, which can transfer staff to a new employer when a service changes provider.
  • CEIA: Communities and Equality Impact Assessment, used to identify and mitigate impacts on protected groups.
  • S151 officer: The council's statutory Chief Finance Officer, designated under section 151 of the Local Government Act 1972.
  • Novate: To transfer the rights and duties of a contract from one party to another, for example to a successor authority.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item338

Resolved

2.1 Cabinet approved the procurement of Waste Treatment and Haulage Services, as a single contract, for an initial term of three years to run from 13 th December 2026 with an option for the council to extend for one or more periods, up to a maximum of two additional years in total. [MW1] [MW2] 2.2 Cabinet delegated authority to the Executive Director of Place, in consultation with the Chief Finance Officer S151, Head of Legal and the Cabinet Member for Place & Environment, to: 2.2.1 determine the appropriate price/quality split to be used for evaluation purposes to identify the most advantageous tender; and 2.2.2 approve the commencement of the procurement process Reason for the decision: as outlined in the report This decision is subject to call-in [MW1] So total contract term would be 5 years, 3 year initial term plus option to extend for a further two years? [MW2] Agreed.
Word for word from the decision Thurrock published for this meeting. Source: democracy.thurrock.gov.uk

Follow this further

Built from Thurrock's papers

What the report saysPro

Report to Cabinet

Report to Cabinet Report Title Procurement of Waste Treatment and Haulage Contracts Date of Meeting Wednesday, 18 March 2026

Report Author Paul Crick Chief Operations Lead - Place

Corporate Director Executive Director Place

Lead Cabinet Member(s) Cabinet Member for Place and the Environment

Why is this a key 1. Expenditure over £500K yes decision? 2. Significant impact on 2 or more wards yes

Wards Affected All wards

Is report Urgent? No

Reasons for urgency N/A (only where applicable)

Appendices (if any) N/A

1. Executive Summary 1.1 This report seeks Cabinet approval to procure an external provider for the provision of Handling, Haulage and Disposal of waste streams, replacing three existing contracts that are currently due to expire on 12th December 2026. The proposal is to integrate the existing three contracts into one contract, and for this contract to be procured by running an open procurement exercise to compete it on the market. 2. Recommendations For the reasons set out in this report, the Cabinet is recommended to: 2.1 Approve the procurement of Waste Treatment and Haulage Services, as a single contract, for an initial term of three years to run from 13th December 2026 with an option for the council to extend for one or more periods, up to a maximum of two additional years in total. 2.2 Delegate authority to the Executive Director of Place, in consultation with the Chief Finance Officer S151, Head of Legal and the Cabinet Member for Place & Environment, to: 2.2.1 determine the appropriate price/quality split to be used for evaluation purposes to identify the most advantageous tender; and 2.2.2 approve the commencement of the procurement process. 3. Commissioner’s Comments 3.1 This procurement will initiate contracts designed to remain effective following Local Government Reorganisation (LGR) and as such must allow for change of identity of contracting authority and changes to the contract, if the LGR arrangements necessitate.

3.2Contract modifications must be authorised in accordance with standing orders and public procurement law and as far as possible should be pre-empted within this process. It will be necessary to ensure that the new procurement both drives value and effective service delivery for its duration and is designed for consolidation with simple LGR clauses that requires the contractor to provide support, information requested and enter into any documents required to give effect to LGR at no additional cost and terms for novation or termination.

3.3The commissioners are content for this report to be considered.

4. Proposals – the rationale and evidence for the recommendations

4.1In November 2020 Cabinet gave delegated authority to the then Corporate Director of Finance, Governance and Property and the Director of Environment, Highways and Counter Fraud in consultation with the Portfolio Holder for Environment, Sports and Leisure for the procurement of the following three contracts:

o Household Waste & Recycling Centre (HWRC) Haulage & Disposal Service; o Haulage of Green, Food and Mixed Dry Recyclables Waste Service; and o Disposal of Waste Collected from the Public Realm.

4.2These three contracts were awarded to the same contractor for an initial term of three years with the option to extend for up to a further two years in total – this option to extend was exercised in all three cases and all three contracts are due to expire on 12th December 2026.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Procurement of Waste Treatment and Haulage ContractsReport 158 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 21 attended
LW
Councillor Lynn WorrallChair, present
LW
Councillor Lee WatsonVice-Chair, present
VH
Councillor Vikki HartsteanCommittee Member, present
LH
Councillor Lynda HeathCommittee Member, present
VH
Councillor Victoria HollowayCommittee Member, present
MH
Councillor Mark HooperCommittee Member, present
JK
Councillor John KentCommittee Member, present
VM
Councillor Valerie Morris-CookCommittee Member, apologies
MB
Mark BradburyOfficer, in attendance
PC
Paul CrickOfficer, in attendance
CD
Claire DemmelOfficer, in attendance
DF
Daniel FenwickOfficer, in attendance

All 21 on the meeting page

On this subject at Thurrock

Search all
  1. Procurement of Waste Treatment and Haulage ContractsThis decision
  2. Procurement of Future Waste Disposal Contracts (Decision 01104412)Decided

More from Thurrock Cabinet

All decisions
MeetingDecisionOutcome
16 Sep 2026 Corporate and Improvement Plan - 2025/26 Quarter 4 and End of Year Performance Report and Annual Report3.1 Cabinet Noted the quarterly Corporate Performance Report at Appendix 1 and consider which performance issues Cabi... Noted Open
16 Sep 2026 Thurrock Transport Strategy Adoption2.1 Cabinet approved the Thurrock Transport Strategy given in Appendix 1 to be progressed to Full Council for adoptio... Approved Open
16 Sep 2026 Proposed Changes to the Essex Coast Recreational Disturbance Avoidance and Mitigation Strategy (RAMS) and Tariff2.1 Cabinet approved the £476 RAMS tariff, as set out in section 9.1 of the Cabinet report; 2.2 Cabinet agreed to wit... Approved Open
16 Sep 2026 High Priority Housing Policies - Housing Adaptations Policy2.1 Cabinet agreed the Council’s Housing Adaptations Policy in Appendix 1 to commence with effect from 1 October 2026... Agreed Open
16 Sep 2026 Matrix Agency Worker 1 year contract extension2.1 Cabinet agreed to utilise the one-year extension option contained within the current contract and extend the exis... Agreed Open