AI summaryThurrock Cabinet approves £7,851,800 transport funding programme for 2026/27 across five DfT funding streams, with indicative spend of £32,700,900 through to 2030, and waives call-in to meet a 20 March 2026 deadline.
Written from the decision and the officer reportPDF Pro
OutcomeAgreedPlus delegated authority to vary the 2026/27 plan within funding parameters
Money£7,851,800 for 2026/27; £40,552,700 to 2030Capital £6,470,500 plus revenue £1,381,300 in 2026/27
What happens nextNot stated
Who it affectsAll wards in ThurrockHighways, bus services, active travel, EV charging
What was decided
Cabinet approved the proposed 2026/27 capital and revenue programmes totalling £7,851,800 across five DfT funding streams. Report P12, P13
Cabinet supported the indicative programme of £32,700,900 for 2027/28 to 2029/30 as part of the Local Transport Delivery Plan. Report P12, P13
Cabinet gave delegated authority to the Chief Operations Lead, in consultation with the Cabinet Member for Place and the Environment, to vary the 2026/27 plan within the overall funding parameters. Report P13
Why
The Department for Transport wrote to all local transport authorities on 23 December 2025 announcing consolidated funding across five workstreams covering 2026/27 to 2029/30. Report P12
Thurrock must submit a combined Local Transport Delivery Plan with Essex County Council and Southend City Council as part of the Accelerated Devolution Programme for Greater Essex, with a draft due to the DfT by 20 March 2026. Report P9
Funding cannot be released until a signed Memorandum of Understanding and the Local Transport Delivery Plan are submitted to the DfT. Report 4.6
What happens next
The Section 151 Officer will sign the Memorandum of Understanding to release funding, and officers will submit the draft Greater Essex Local Transport Delivery Plan by 20 March 2026 and the final plan by 18 September 2026. Report 4.6
The Chief Operations Lead, in consultation with the Cabinet Member for Place and the Environment, will manage in-year variations to the 2026/27 programme within the funding envelope.
The programme will be reviewed annually as part of the Local Transport Delivery Plan cycle, with funding carried forward or reallocated where schemes change.
The money
£6,470,500 Capital programme for 2026/27 Report P12, P16
£1,381,300 Revenue programme for 2026/27 Report P12, P22
£7,851,800 Total 2026/27 capital plus revenue Report P12, P92
£2,762,600 Indicative revenue programme 2027/28 to 2028/29 Report P13
£29,938,300 Indicative capital programme 2027/28 to 2029/30 Report P13
£32,700,900 Indicative total 2027/28 to 2029/30 Report P13
£36,408,800 Total capital funding across all four years Report P19
£4,143,900 Total revenue funding across three years Report P26
£40,552,700 Total DfT consolidated funding to March 2030 Report P12
£3,965,000 Highways Maintenance capital allocation 2026/27 Report P16, P40
Options considered
Chosen: Approve the proposed programme and submit to DfT as recommended. Allows the council to access £40,552,700 of DfT funding and meet the 20 March 2026 deadline Report P13
Rejected: Not approve the programme. Risks the council's reputation with the DfT, could lead to clawback of funds, and would put essential highway maintenance and bus services at risk
Rejected: Use Integrated Transport Fund flexibility to support ferry services. The paper notes this is an option available under the ITF if the council is ready to implement it, but it is not proposed in this programme
Implications
Financial: The programme is fully grant funded from the DfT and requires no council borrowing, with no ongoing revenue impact on the council.
Legal: The council has powers to deliver the programme under the Highways Act 1980, Traffic Management Act 2004, Transport Act 2000, and the Localism Act 2011, and must comply with the Procurement Act 2023.
Risk: Funding may be reclaimed by the DfT if not committed or spent within the agreed timeframes, and if schemes are removed without due process the council may be liable to repay associated funding.
Risk: Failure to deliver on time and within budget may impact future grant awards and could lead to third-party claims if the highway network is not maintained. Report P94
Equalities: Schemes benefitting particular communities or groups will be subject to individual equality assessments, and a full CEqIA is not required for this report. Report P96
Other: From 2028/29 the five funding streams will transfer to a new Mayoral Transport Fund once the Greater Essex County Combined Authority and its Mayor are established.
Who and where
All residents and road users across all Thurrock wards, including bus passengers, cyclists, and pedestrians Report P7
Care leavers in Thurrock, through extension of free bus travel
Residents of Aveley, South Ockendon, and Little Thurrock served by new active travel crossings and routes Report P44, P45, P48, P49, P50
Horndon-on-the-Hill, Stanford-le-Hope, Corringham, East Tilbury, Grays, Bulphan and West Horndon residents using supported bus services 375 and 88
Existing council staff in the Strategic Transport Team, the Highways team, and EV infrastructure delivery Report 4.33
Bus operator Ensign Bus, which may receive contributions towards up to five electric buses
Timeline
19 January 2025: Finance business partnering implications verified by Head of Finance
23 December 2025: DfT writes to all local transport authorities announcing consolidated funding across five workstreams
19/01/2026: Risk implications verified by Risk Manager and equality implications verified Report P96
20 March 2026: Draft Greater Essex Local Transport Delivery Plan must be submitted to DfT Report P9
01 April 2026: Start of the 2026/27 financial year and four-year funding period
18 September 2026: Final Greater Essex Local Transport Delivery Plan due to DfT
2026/27 to 2028/29: Three-year revenue funding period for Active Travel, EV, Local Transport Grant, and Bus Grant
2026/27 to 2029/30: Four-year capital funding period across the four capital workstreams
2028/29: First year when funding becomes the Mayoral Transport Fund after election of a Mayor for the new County Combined Authority
31 March 2030: End of the four-year funding period
Plain English for the jargon
Local Transport Delivery Plan (LTDP): Plan each local transport authority must submit to the DfT setting out proposed capital and revenue transport expenditure for the year ahead and indicative spend for subsequent years
Integrated Transport Fund (ITF): The consolidated grouping of four of the five DfT funding streams, covering Highway Maintenance, Active Travel, Electric Vehicle Infrastructure Capability, and Local Transport Grant
Bus Services Fund (BSF): The component of the consolidated settlement covering the Local Authority Bus Grant, treated separately from the ITF
Mayoral Transport Fund (MTF): The fund that will replace the current arrangements from 2028/29 once a Mayor is elected to the new Greater Essex County Combined Authority
Memorandum of Understanding (MoU): Agreement signed by the council's Section 151 Officer that the DfT requires before releasing the consolidated funding
Project Adjustment Request (PAR): Mechanism allowing councils to revise their Local Transport Delivery Plan submissions between annual cycles
CEqIA: Council Equality Impact Assessment; this report concludes one is not required at programme level because individual schemes will be assessed separately
LCWIP: Local Cycling and Walking Infrastructure Plan, adopted by Thurrock in January 2025
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item339
Resolved
2.1 Cabinet agreed to: - 2.1.1 Approve the proposed capital (£6,470,500) and revenue (£1,381,300) programmes for financial year 2026/27 totalling £7,851,800 2.1.2 Support the indicative programme for revenue expenditure for financial years 2027/28 and 2028/29 totalling £2,762,600, and the capital programme for financial years 2027/28 to 2029/30 totalling £29,938,300 as part of the Local Transport Delivery Plan requirements as set by Department for Transport, totalling £32,700,900. 2.1.3 Permit delegated authority to the Chief Operations Lead in consultation with the Cabinet Member for Place and the Environment to make programme amendments to the 2026/27 Local Transport Delivery Plan within the overall funding parameters outlines.
Word for word from the decision Thurrock published for this meeting.Source: democracy.thurrock.gov.uk
Report to Cabinet Report Title Local Transport Consolidated Funding - 2026/27
Date of Meeting Wednesday, 18 March 2026
Report Author Paul Crick - Chief Operations Lead
Corporate Director Claire Demmel - Executive Director Place
Lead Cabinet Member(s) Cabinet Member for Place and the Environment
Why is this a key 1. Expenditure over £500K yes decision? 2. Significant impact on 2 or more wards yes
Wards Affected (All Wards);
Identify exempt Choose an item. information and exemption category
Is report Urgent? This report is waived from the call in process. The cabinet meeting is 18 March 2026, and if the decision is taken, the council must report to the Department for Transport by 20 March 2026. This is the absolute deadline and no extension can be granted. As such, the decision needs to be implemented in advance of the call-in period expiring. Appendices (if any) A. The Local Transport Consolidated Funding Settlement Letter
B. Highway Maintenance Fund – Capital Programme 2026/27
C. Local Transport Grant – Capital Programme 2026/27
D. Local Authority Bus Grant Revenue and Capital Programme 2026/27 E. The Local Transport Consolidated Funding Settlement Breakdown by Local Authority within Greater Essex 1. Executive Summary Thurrock Council has been asked to submit a Local Transport Delivery Plan by the Department for Transport, outlining proposed revenue and capital expenditures for the year 2026/27 and indicative expenditure through to 2028/29 for revenue funds and 2029/30 for capital funding. The Local Transport Delivery Plan covers five funding streams – Highways Maintenance, Active Travel, Electric Vehicle, Local Transport Grant, and Local Authority Bus Grant, totalling £7,851,800 for financial year 2026/27 and £40,552,700 through until March 2030. This report seeks approval from Cabinet to submit a Local Transport Delivery Plan containing the proposed expenditure across these funds for 2026/27, and to submit an outline proposal for expenditure across the subsequent three-year period.
2. Recommendations 2.1 For the reasons set out in this report, the Cabinet is recommended to: 2.1.1 Approve the proposed capital (£6,470,500) and revenue (£1,381,300) programmes for financial year 2026/27 totalling £7,851,800 2.1.2 Support the indicative programme for revenue expenditure for financial years 2027/28 and 2028/29 totalling £2,762,600, and the capital programme for financial years 2027/28 to 2029/30 totalling £29,938,300 as part of the Local Transport Delivery Plan requirements as set by Department for Transport, totalling £32,700,900. 2.1.3 Permit delegated authority to the Chief Operations Lead in consultation with the Cabinet Member for Place and the Environment to make programme amendments to the 2026/27 Local Transport Delivery Plan within the overall funding parameters outlined. 3. Commissioner’s Comments 3.1 Commissioners note the content of this report and that delivering projects on time and within budget will require a multi-year strategy focused on prioritisation, robust project management, and active stakeholder engagement. Notably, full receipt of Highways Maintenance and Active Travel incentive funding is contingent on the Council demonstrating compliance with best practice and meeting DfT transparency and performance standards. 3.2 Commissioners note the need for this decision to be exempt from call in due to time constraints in complying with the requirement to submit draft Transport Delivery Plans by 20 March 2026. This should be used rarely and in exceptional circumstances only.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Thurrock Transport Strategy Adoption2.1 Cabinet approved the Thurrock Transport Strategy given in Appendix 1 to be progressed to Full Council for adoptio...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.