The Surrey Hills National Landscape Management Plan 2025 to 2030

Approved Executive 4 papers

AI summaryWaverley Executive adopts Surrey Hills National Landscape Management Plan 2025-2030, with minor edits delegated to the Assistant Director for Planning.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedSurrey Hills National Landscape Management Plan 2025-2030
Money£5,709 per annumWaverley's existing core funding contribution to the Surrey Hills Board
What happens nextLaunch in November 2025At the Surrey Hills Symposium, with publication shortly after
Who it affects60% of Waverley countrysideCould rise to 70% under Natural England boundary review

What was decided

The Executive adopted the Surrey Hills National Landscape Management Plan 2025-2030, meeting the council's statutory duty to review the plan every five years. Report P5, 3.1, 6.2

Authority was delegated to the Assistant Director for Planning, in consultation with the Portfolio Holder for Planning and Economic Development, to make minor factual, typographical and formatting edits before publication. Report P6, 3.2, 6.11

Why

Adoption is needed to comply with the statutory duty under the Countryside and Rights of Way Act 2000, which requires management plans to be reviewed every five years. Report 6.2, P67

The Levelling Up and Regeneration Act 2023 places a new legal duty on relevant authorities to seek to further the purpose of National Landscapes, strengthening the previous duty of regard. Report 6.8, P25

The plan will be a material consideration in planning decisions and supports the implementation of the Local Plan, though it is not part of the development plan. Report 1.2, P20

What happens next

The plan is to be launched in November 2025 at the Surrey Hills Symposium and published shortly afterwards, subject to adoption by all relevant local authorities. Report 4.1, P10

The Surrey Hills Board approved the final plan on 11 July 2025 after consultation between March and June 2025, which received 40 responses. Report 9.1, P47, P48

The money

  • £5,709 per annum Waverley's existing core funding contribution to the Surrey Hills Board Report P63

Options considered

  • Chosen: Adopt the 2025-2030 Management Plan. Meets statutory duties under the CRoW Act in a cost-effective way and maintains a consistent approach with partner authorities. Report P52
  • Rejected: Recommend changes prior to adoption. Would require agreement of other constituent authorities, further consultation, and risk missing the statutory deadline. Report P53, P54
  • Rejected: Do not adopt the Management Plan. Would still require a separate plan under the CRoW Act, risking inconsistent management, legal challenge, and missing the statutory deadline. Report P55, P56
  • Chosen: Delegate minor edits to Assistant Director for Planning. Avoids delays and ensures adoption within the statutory deadline. Report P58, P59
  • Rejected: Do not delegate minor edits. Would require further Executive approval and delay publication for non-substantive reasons. Report P60, P61

Implications

  • Legal: Adoption enables the council to comply with its statutory duty under the CRoW Act 2000 to prepare and review a management plan every five years. Report P67
  • Legal: The plan supports the new statutory duty under the Levelling Up and Regeneration Act 2023 to seek to further the purposes of National Landscapes. Report 6.8, P25
  • Financial: No additional financial resources are required beyond the existing annual contribution; any future funding needs would be sought case by case. Report P63, P64
  • Financial: Waverley's funding share may increase if the Natural England boundary review expands the SHNL area, but the amount is unknown. Report P65, P66
  • Equalities: An Equalities Impact Screening Assessment concluded the plan has a positive impact on two target groups and neutral impact on others; a full assessment is not required. Report P72, P73
  • Climate: The plan sets strategic targets on climate, nature and engagement, and promotes small-scale renewable energy installations on farms where they do not harm landscape beauty. Report P75
  • Risk: Risks of non-adoption include legal challenge, inconsistent management, and missing the statutory deadline. Report P54, P56, 10.1

Who and where

  • Planning applicants and planning authorities within or near the Surrey Hills National Landscape Report 1.2, P20
  • Residents and visitors to the 60% of Waverley countryside within the SHNL Report 6.1
  • Partner authorities across the Surrey Hills, including Guildford, Mole Valley, Tandridge and Reigate and Banstead Report 1.1, P52
  • The Surrey Hills Board and Surrey Hills Unit, who prepared the plan Report 6.5, 9.1

Timeline

  • October 2019: Previous Management Plan (2020-2025) adopted by Waverley Borough Council Report 1.1, 3.1
  • March to June 2025: Public consultation on the draft Management Plan, receiving 40 responses Report 9.1, P47
  • 11 July 2025: Surrey Hills Board approved the final Management Plan Report P48
  • 15 September 2025: Overview and Scrutiny (Services) Committee reviewed the plan and made no amendment recommendations Report 13.1, P76
  • 14 October 2025: Waverley Executive adopted the Management Plan 2025-2030
  • November 2025: Planned launch at the Surrey Hills Symposium, with publication shortly after Report 4.1, P10

Plain English for the jargon

  • Surrey Hills National Landscape (SHNL): Formerly known as an Area of Outstanding Natural Beauty, a protected landscape stretching from Farnham to Oxted across Surrey.
  • Management Plan: A document required under the CRoW Act 2000 setting out the vision, strategy and policies for conserving and enhancing a National Landscape, reviewed at least every five years.
  • CRoW Act: The Countryside and Rights of Way Act 2000, which requires local authorities to produce and review Management Plans for National Landscapes.
  • LURA: The Levelling Up and Regeneration Act 2023, which imposed a new legal duty on relevant authorities to seek to further the purpose of National Landscapes.
  • Material consideration: A factor that must be taken into account when determining planning applications, though the plan does not form part of the development plan.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemEXE 81/25

Resolved

RESOLVED that: 1. The Surrey Hills National Landscape Management Plan 2025-2030 be adopted 2. Authority be delegated to the Assistant Director for Planning, in consultation with the Portfolio Holder for Planning and Economic Development, to make any minor edits.
Word for word from the decision Waverley published for this meeting. Source: modgov.waverley.gov.uk

Follow this further

Built from Waverley's papers

What the report saysPro

Report to Executive

Executive summary

1.1The Surrey Hills covers a large area across Surrey and parts sits within Waverley, Guildford, Mole Valley, Tandridge and Reigate and Banstead. The Management Plan for the Surrey Hills National Landscape (SHNL), prepared by the Surrey Hills Board was adopted by Waverley Borough Council in October 2019. It has been reviewed as required under legislation, and a revised Management Plan for the next five-year period (2025-2030) has been prepared and consulted on by the Surrey Hills Board, with the input of other local authorities within the Surrey Hills. The Management Plan is included as Appendix 1 to this report.

1.2The Management Plan will be a material consideration in the determination of relevant planning applications and supports the implementation of the Local Plan. Each relevant local authority is required to adopt it separately through an Executive meeting.

1.3The review is more extensive than previous iterations to account for revised legislation including the Environment Act and the Levelling Up and Regeneration Act. The main changes are summarised in the report.

Recommendations

2.1That the Executive resolves to:

2.2.1 Adopt the Surrey Hills National Landscape Management Plan 2025-2030

2.2.2 Delegate any minor editing to the Assistant Director for Planning in consultation with the Portfolio Holder for Planning and Economic Development

Reasons for recommendation

3.1It is recommended that the Surrey Hills National Landscape Management Plan 2025-2030 is adopted to meet Waverley Borough Council’s statutory obligations. The current iteration covers the period 2020-2025 and was adopted by the Council in October 2019.

2 Adoption of Surrey Hills National Landscape Management Plan 2025-2030

3.2Delegation of any minor editing will allow for minor factual, typographical and formatting amendments to be agreed without delay prior to publication of the final document, in conjunction with the Surrey Hills Board.

4 Next steps

4.1Subject to the adoption of the document by the relevant Local Authorities, it is intended that the Surrey Hills Management Plan 2025-2030 will be launched in November 2025 at the Surrey Hills Symposium and published shortly after.

5 Exemption from publication

5.1This report is not exempt from publication.

6 Background and Proposal

Introduction

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
SHNL Management Plan 81/25Appendix 1 3.9 MB Download
PDF
250606 Letter WBC response to Draft Management Plan 2025: 2030 81/25Appendix 2a 229 KB Download
PDF
250606 Waverley BC comments and track changes on consultation on Draft NLMP 2025 to 2030 81/25Appendix 2b 155 KB Download
PDF
The Surrey Hills National Landscape Management Plan 2025 to 2030Report 253 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 10 attended
PF
Councillor Paul FollowsChair, present
TF
Councillor Tony FaircloughVice Chair, present
JC
Councillor Janet CroweCommittee Member, present
VK
Councillor Victoria KiehlCommittee Member, present
GL
Councillor Gemma LongCommittee Member, present
MM
Councillor Mark MerryweatherCommittee Member, present
KM
Councillor Kika MiryleesCommittee Member, present
PR
Councillor Paul RiversCommittee Member, apologies
LT
Councillor Liz Townsend BEMCommittee Member, present
SW
Councillor Steve WilliamsCommittee Member, present

On this subject at Waverley

Search all
  1. The Surrey Hills National Landscape Management Plan 2025 to 2030This decision
  2. The Surrey Hills National Landscape Management Plan 2025 to 2030Agreed

More from Waverley Executive

All decisions
MeetingDecisionOutcome
1 Sep 2026 Lease Renewal on Unit 3, Enterprise Centre, Farnhamthat 1) Delegated authority be given to the Director of Assets and Property for the granting of the lease of Unit 3, ... Agreed Open
1 Sep 2026 New Contract for Communal Block Cleaning Servicesthat 1) Delegated authority be given to the Director of Housing Service to enter into the Block Cleaning Services con... Decided Open
1 Sep 2026 Acquisition of Land off Hale Road, Adjacent to Farnham Park, Farnhamthat 1) The Executive request consent from West Surrey Shadow Authority to enter into a Conditional Purchase Agreemen... Agreed Open
1 Sep 2026 Waverley Fire Loss - Underinsurance at 13 & 14 Springwood, Station Lane, MilfordRECOMMENDED that Council RESOLVE to: 1) Approve a supplementary estimate increase of £106,269.98 for FY26/27 to be fu... Approved Open
1 Sep 2026 Recycling and Waste Collection and Street Cleansing Services Contracts Arrangements from 1 November 2027that 1) An 8-year extension to the current Waste Collection and Street Cleansing Contract with an option of a contrac... Approved Open