Noted Executive 1 paper

AI summaryWaverley Borough Council's Landlord Services Advisory Board noted Q4 2025/26 damp and mould performance, endorsed improvement actions and accepted risk assurance. Quarter saw 263 new cases, 292 completions and £144,063 total damp-related spend.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedPerformance data noted, improvement actions endorsed, risk assurance accepted
Money£144,063Total damp-related spend for Q4 2025/26
What happens nextQ1 2026/27Stock survey, budget review and timescale recovery expected
Who it affectsWBC housing tenantsIncluding 168 of 263 Q4 cases flagged as vulnerable

What was decided

The Board noted the Q4 2025/26 performance data showing 263 new cases, 292 completed cases and full resolution of all four Category 1 Hazards within statutory timescales. Report P7, P8, P82

The Board noted the updated Decent Homes Standard published 28 January 2026 and the updated Part F Regulations published 25 March 2026. Report P9, P83

The Board endorsed the improvement actions and accepted assurance that residual risks, including contractor transition and regulatory compliance deadlines, are being managed. Report P68, P84, P85

Why

New case volumes rose from 153 in Q4 2024/25 to 263 in Q4 2025/26, reflecting better resident awareness and more proactive case identification, while completed cases rose from 107 to 292. Report P8, P13, P14, P18

All 263 new cases were assessed under the HHSRS and all four Category 1 Hazards were resolved within Awaab's Law timescales, with no Cat.1 Hazards outstanding at quarter end. Report P5, P30, P31, P57

Significant mitigation and prevention work timescales declined because the main contractor's subcontractor lacked the expertise for domestic ventilation installations, prompting a temporary specialist contractor. Report P23, P24, P25

What happens next

A new long-term specialist DMC contractor is expected to commence in July 2026, with timescale recovery to target expected by end of Q1 2026/27. Report P25, P56, P68, P75

A budget review and revised annual DMC allocation for 2026/27 will be undertaken in Q1 2026/27, alongside a Part F compliance stock assessment planned for Q2 2026/27. Report P76, P81

The DMC Policy is being reviewed in Q1 2026/27 to incorporate the updated Decent Homes Standard and Part F requirements, and a dedicated DMC work order code is in progress. Report P9, P57, P72, P73

The money

  • £92,064 Total DMC operational spend (DP damp and mould contract) in Q4 2025/26 Report P47
  • £52,004 Total other damp-related spend via reactive repairs in Q4 2025/26 Report P53
  • £144,063 Total operational damp, mould and other damp-related spend for Q4 2025/26 Report P54
  • £47,976 Prevention works: 78 ventilation installations (11 PIV, fan overhauls), avg £615 per property Report P44
  • £36,076 Gutter repairs (193 orders), cold bridge contributor to damp and mould Report P38, P52
  • £34,700 Mould treatment and minor repair works, single-visit model (263 properties, avg £162) Report P43
  • £8,900 Plumbing leak repairs (66 orders, reactive) Report P35, P50
  • £6,588 Temporary measures: dehumidifier rental and delivery (6 properties) Report P45

Options considered

  • Chosen: Use temporary specialist contractor for prevention works while mobilising a new long-term contractor. Main contractor's subcontractor lacked expertise to install domestic ventilation systems, delaying prevention works Report P25, P56
  • Chosen: Continue raising related damp works (loft insulation, structural damp, leaks) as standard reactive repairs. Limited DMC budget and absence of a dedicated work order code, though establishing a dedicated code is an agreed improvement action Report P19, P68, P72

Implications

  • Legal: WBC operates in full compliance with Awaab's Law (in force 27 October 2025), the Housing Regulation Act 2023, the updated Decent Homes Standard (28 January 2026) and forthcoming Part F Regulations (effective March 2027). Report P5, P9, P57
  • Financial: Indicative Q4 spend of £144,063 across DMC contract and reactive damp works, with a budget review and revised annual allocation for 2026/27 planned in Q1 2026/27. Report P54, P81
  • Equalities: 168 of 263 new Q4 cases (64%) involved a resident flagged as vulnerable, including respiratory conditions, disabilities, elderly residents and families with under-fives; all received an inspection within 10 calendar days. Report P58
  • Staffing: Specialist staff shortages in the main contractor's subcontractor delayed prevention works; a temporary specialist contractor is in place until the new long-term contractor commences in July 2026. Report P25, P56, P68
  • Risk: Key risks for Q1 2026/27 include timescale recovery, contractor transition mobilisation, low PIV unit orders, and Part F compliance assessment. Report P68
  • Climate: 22 properties received ventilation and insulation upgrades in Q4 2025/26 under SHDF Wave 2.2 and Wave 3, funded separately from a capital budget and not included in DMC spend. Report P40, P56

Who and where

  • Waverley Borough Council tenants in affected properties, including 168 of 263 Q4 cases flagged as vulnerable Report P58
  • Residents with respiratory conditions, disabilities, elderly residents living alone, and families with children under five Report P58
  • Households with historically elevated DMC risk profiles who received 340 advice leaflets in the winter readiness programme Report P56
  • WBC Housing Services team and the DMC Officer (Loredana Hobbs), supported by a temporary specialist contractor and a new long-term contractor from July 2026 Report P2, P56, P68

Timeline

  • 27 October 2025: Awaab's Law (Housing Act 2004 as amended) came into force with binding investigation and repair timescales Report P5, P9
  • 28 January 2026: Updated Decent Homes Standard published, with strengthened focus on energy efficiency and damp and mould Report P9, P83
  • February 2026: Highest monthly new case volume at 139, consistent with seasonal mid-winter peak Report P8, P18
  • Q4 2025/26 (January to March 2026): Reporting period: 263 new cases, 292 completions, 68 open at end of March 2026 Report P7, P13, P14
  • 25 March 2026: Updated Part F Regulations (Ventilation) published Report P9, P83
  • May 2026: DMC quarterly performance summary presented to LSAB Report P80
  • July 2026: New long-term specialist DMC contractor expected to commence; PCA training for surveyors and CIH Level 4 enrolment also planned Report P68, P75, P77, P78
  • Q1 2026/27: Stock survey (deck-access and Godalming North properties), Aico sensor expansion to 20 further properties, budget review and DMC policy review due Report P57, P71, P74, P81
  • March 2027: Updated Part F Regulations come into force Report P9, P68, P83

Plain English for the jargon

  • DMC: Damp, Mould and Condensation
  • HHSRS: Housing Health and Safety Rating System
  • Awaab's Law: Housing Act 2004 as amended, in force 27 October 2025, imposing legally binding investigation and repair timescales
  • Decent Homes Standard: Government standard for housing quality, updated 28 January 2026 with stronger focus on energy efficiency and damp and mould
  • Part F Regulations: Building Regulations covering ventilation, updated 25 March 2026 and effective March 2027
  • PIV: Positive Input Ventilation, a whole-house ventilation system
  • SHDF: Social Housing Decarbonisation Fund, funding energy efficiency upgrades (Wave 2.2 and Wave 3)
  • LSAB: Landlord Services Advisory Board (Executive Working Group)
  • CIH: Chartered Institute of Housing
  • Cat.1 Hazard: Category 1 Hazard under the HHSRS, the most serious damp and mould hazard rating requiring urgent action
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item12

Resolved

RESOLVED that: · The Q4 2025/26 performance data be noted. · The updated decent homes standard and forthcoming Part F regulations be noted. · The improvement actions be endorsed. · The assurance that the residual risks are being managed be accepted.
Word for word from the decision Waverley published for this meeting. Source: modgov.waverley.gov.uk

Follow this further

Built from Waverley's papers

What the report saysPro

Report to Landlord Services Advisory Board (Executive Working Group)

Damp, Mould and Condensation Quarterly Performance Report Q4 2025/26 (January–March 2026)

Waverley Borough Council Information note to: Landlord Services Advisory Board Date: 6 May 2026 Author: Loredana Hobbs, Damp and Mould Officer Email: [email protected]

Information for Scrutiny and Comment

1.0Purpose

This report provides Waverley Borough Council’s (WBC) performance data for damp, mould and condensation (DMC) cases for Q4 2025/26 (January–March 2026). It benchmarks against the two preceding comparison periods Q3 2025/26 (Oct–Dec 2025) and Q4 2024/25 (Jan–Mar 2025), enabling the Landlord Services Advisory Board to assess trends and evaluate the impact of improvement actions. All quarter references in this report follow the WBC financial year, which runs from 1 April to 31 March. The health, safety and wellbeing of residents is the overriding priority. WBC operates in full compliance with the Housing Health and Safety Rating System (HHSRS), the Housing Regulation Act 2023 and the Awaab’s Law provisions which came into force on 27 October 2025. All responses are risk-stratified to ensure the most vulnerable residents receive timely intervention.

Key Performance Indicators at a Glance

263 292 68 4 New Cases Completed Cases Open at End of Q Cat.1 Hazards Q4 2025/26 total Q4 2025/26 — all End of March 2026 Q4 2025/26 — all resolutions resolved

New case volumes have risen substantially year-on-year (153 in Q4 2024/25 to 263 in Q4 2025/26), reflecting improved resident awareness of reporting routes and more systematic proactive case identification. Completed cases represent all resolutions during the quarter, including cases opened in prior periods. February 2026 recorded the highest monthly new case volume at 139, consistent with the seasonal mid-winter peak. All four Category 1 Hazards identified in Q4 2025/26 were resolved within statutory timescales. 2.0 Background This section sets out the legislative and regulatory context within which WBC delivers its damp, mould and condensation service, the case volume and demand data for Q4 2025/26, and the response timescale performance for the reporting period.

Legislative and Policy Context The health and safety of tenants is a key priority for WBC. The policy environment continues to evolve, with several significant developments during and immediately after the current reporting quarter. • Awaab’s Law (Housing Act 2004 as amended, in force 27 October 2025) imposes legally binding investigation and repair timescales. WBC’s response protocols, triage scripts and case management workflows are fully aligned to these statutory requirements. • The Decent Homes Standard was updated and published on 28 January 2026, with a strengthened focus on energy efficiency and the direct connection between thermal performance and the prevention of damp and mould. Officers are reviewing the updated standard to identify stock-level investment implications for the housing programme. • Updated Part F of the Regulations (Ventilation) were published on 25 March 2026 and will come into force in March 2027. The revised requirements raise minimum ventilation standards for dwellings and are directly relevant to WBC’s ventilation upgrade programme. Officers are assessing current stock compliance and planning proactive upgrades and associated budget accordingly. • The Housing Ombudsman’s Spotlight on Damp and Mould continues to inform approaches across the sector, from which WBC actively seeks to learn and benchmark practice. • The Social Housing (Regulation) Act 2023 Consumer Standards remain in force and are embedded in WBC’s performance monitoring framework. • WBC’s Damp, Mould and Condensation Policy (adopted September 2025) is being reviewed in Q1 2026/27 to incorporate the updated Decent Homes Standard and Part F requirements.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Damp and Mould Quarterly Update ReportReport 637 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

14 of 18 attended
PR
Councillor Paul RiversChair, present
TD
Terry DaubneyVice Chair, present
JC
Councillor Janet CroweCommittee Member, present
AL
Councillor Andrew LaughtonCommittee Member, apologies
JK
Councillor Jacquie KeenCommittee Member, apologies
AM
Councillor Alan MorrisonCommittee Member, present
RB
Rod BlackmoreCommittee Member, present
RS
Robert StratfordCommittee Member, present
DW
Dave WilliamsObserver, expected
DM
Dave MaddamsObserver, expected
AF
Alex FosterOfficer, present
AH
Annalisa HowsonOfficer, present

All 18 on the meeting page

On this subject at Waverley

Search all
  1. Damp and Mould Quarterly Update ReportThis decision
  2. New contract for Damp, Mould and Condensation Prevention and Remediation ServicesDecided
  3. Damp and Mould UpdateNoted
  4. Damp and Mould Quarterly UpdateNoted
  5. Damp and Mould Quarterly Update (20 mins)Agreed
  6. Approval to commence tendering for Damp and Mould Specialist Services contractDecided

More from Waverley Landlord Services Advisory Board (Executive Working Group)

All decisions
MeetingDecisionOutcome
30 Jul 2026 Capital Programme updateRESOLVED that the Capital Programme update be noted. Noted Open
30 Jul 2026 Council Response to Tenant Panel Proposal on Repairs, Maintenance and Service AppointmentsRESOLVED that: · the tenant panel proposal be noted, · the principles of a standardized appointments and communicatio... Noted Open
30 Jul 2026 Low Carbon Heating SolutionsRESOLVED that the Low Carbon Heating Solutions report be noted. Noted Open
30 Jul 2026 Water Hygiene ReportRESOLVED that the monthly Water Hygiene Report be noted. Noted Open
30 Jul 2026 Landlord Services Improvement Plan Update [2025-26]RESOLVED that the Landlord Services Improvement Plan update was noted. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies