Water Remedial Actions Progress Report

Noted Executive 1 paper

AI summaryWaverley's Landlord Services Advisory Board noted a water safety progress report, which shows contractor SMS Environmental continuing remedial works on council housing while new contractor Urban Environment prepares to take over planned maintenance on 1 July 2026.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedWater remedial actions progress report
MoneyNot stated
What happens nextHandover to Urban EnvironmentPlanned maintenance from 1 July 2026
Who it affectsCouncil housing tenants and leaseholdersAcross Waverley housing stock

What was decided

The Board noted the water remedial actions progress report.

Why

SMS Environmental Services has been carrying out water safety remedial works since 18 December 2025 under a 36 month contract with Waverley. Report P1

Urban Environment signed a new 36 month contract with the council on 28 April 2026 to take over the work from SMS. Report P2

SMS will continue delivering the planned preventative maintenance programme until 1 July 2026 to allow time for mobilisation of the new contractor and confirmation that risks have been identified or mitigated. Report P11

What happens next

Urban Environment will begin water risk assessments from the start of June 2026 and take over planned preventative maintenance on 1 July 2026. Report P3

A mobilisation plan with Urban Environment is to be agreed on 13 May 2026. Report P19

SMS is targeting a July 8 deadline to have reviewed all overdue and pending remedial works, with 50 inspections or surveys planned for May. Report P7

Implications

  • Risk: Faulkner Court poses the highest level of risk to residents because the loft cannot be accessed to inspect water tanks; works to install thermal stores in each flat started on 28 April 2026. Report P6
  • Risk: Of 730 overdue water safety actions identified overall, 389 remained outstanding at the end of April 2026, with 32 actions completed during the month. Report P9
  • Risk: In April, SMS completed 35 of 42 scheduled planned preventative maintenance tasks, 83 per cent, with the remaining seven requiring follow on works. Report P11
  • Staffing: SMS has employed one trainee apprentice in March and two plumbers in April to increase capacity for completing remedial works. Report P7
  • Equalities: Several blocks requiring water hygiene works are predominantly occupied by leaseholders, who have been informed of the process including details of potential costs. Report P19
  • Other: A standardised questionnaire template is to be introduced for use by the Bracknell Forest Out of Hours Call Centre to improve data collection and access arrangements. Report P15
  • Other: A new Gantt chart is being developed to track the progress of each action identified or assigned to SMS by other contractors. Report P19

Who and where

  • Residents at Faulkner Court, an independent senior living scheme Report P6
  • Wider council housing tenants living in properties with water safety actions outstanding Report P9
  • Leaseholders in blocks requiring water hygiene works Report P19
  • SMS Environmental Services Ltd, the current water safety contractor Report P1
  • Urban Environment, the incoming water safety contractor Report P2

Timeline

  • 18 December 2025: SMS Environmental Services contract with Waverley began Report P1
  • April 2026: SMS employed two plumbers, having taken on one trainee apprentice in March Report P7
  • 28 April 2026: Urban Environment signed the contract with WBC; works at Faulkner Court started Report P2, P6
  • 1 May 2026: WBC met with SMS to address targets to completion for historic remedial actions Report P19
  • 13 May 2026: Urban Environment mobilisation meeting scheduled Report P2, P19
  • Beginning of June 2026: Urban Environment to commence water risk assessments Report P3
  • 1 July 2026: Urban Environment to assume responsibility for maintaining the planned preventative maintenance Report P3
  • 8 July: SMS target to have reviewed all overdue and pending remedial works Report P7

Plain English for the jargon

  • PPM / PPMS: Planned Preventative Maintenance, the scheduled checks and servicing programme for water systems
  • SMS: SMS Environmental Services Ltd, the current water safety contractor
  • UE: Urban Environment, the incoming water safety contractor
  • WBC: Waverley Borough Council
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item13

Resolved

Resolved that: The water remedial actions progress report be noted.
Word for word from the decision Waverley published for this meeting. Source: modgov.waverley.gov.uk

Follow this further

Built from Waverley's papers

What the report saysPro

Report to Landlord Services Advisory Board (Executive Working Group)

Background

SMS Environmental Services Ltd (SMS) entered into a contract with Waverley on 18 December 2025 to address and resolve all water safety remedial actions. The contract has a duration of 36 months, with an option to extend for a further 24 months.

Urban Environment (UE) has now signed the agreed contract with WBC on 28 April 2026 and a contract mobilisation meeting has now been scheduled for Wednesday 13 May. This contract is a 36-month contract, with a possible extension for a further 24 months.

It is planned - that UE will commence completion of water risk Assessment from the beginning of June. Once all the relevant information has been handed over to from SMS, UE will assume responsibility for maintaining the PPMS from 1 July 2026. Further confirmation of resources allocated to WBC along with detailed implementation and mobilisation plans, will be agreed at the fourth coming mobilisation meeting.

3. Remedial Progression Overview

SMS have confirmed in April that they would be on site at three locations and will be inspecting as many additional sites as possible to agree and progress further required works.

One of these sites is Faulkner Court (Independent Senior Living Scheme). While we continue to sample the water to confirm it is safe to drink, we are unable to access the loft to inspect the tanks. Due to this, this scheme poses the highest level of risk to our customers and works to resolve this started on Tuesday 28 April. We have confirmed with the residents that due to no gas supply to this site, we are installing Thermal Stores to each flat along with main water supply to each flat. The existing loft water tanks will be isolated, and each flat will benefit from an instantaneous hot water supply.

Page 1 of 4 Once the conversion from a tank to store per flat at Faulkner Court has taken place, this will resolve 9 high risk actions and 2 medium risks. SMS have confirmed that they will be completing 50 inspections/surveys in May, to stay on target for the July 8 deadline. By July, we expect SMS to have reviewed all overdue and pending remedial works. To achieve this target and the works that will follow, SMS have also employed extra staff. In March, one trainee apprentice was employed, followed by the employment of two plumbers in April.

Achievements for April 2026 are as follows:

Count of Risk Rating for Overdue Actions Actions Update Completed April 26 April 26 (New Actioned / Outstanding Grand actions Category (A) High Medium Low completed Category Total identified) Category (A+B-C) Category (B) (C) Backflow 11 11 0 - 11 CWST 167 199 4 370 0 7 370 CWST - Access 73 134 207 0 1 207 issue Dead leg / Dead 31 9 40 0 1 40 end Expansion vessels 2 1 3 0 2 3 Flexible pipework 3 17 20 0 6 20 Flushing 3 3 0 - 3 HWS 34 6 40 0 4 40 Insulation 19 19 0 2 19 Outlets 9 4 13 0 1 13 PPM 1 1 0 - 1 Quick fill 2 2 0 8 2 TMV - Access 1 1 0 - 1 Grand Total 320 389 21 730 0 32 730

4. Planned Preventative Maintenance Progression Overview

SMS will continue to deliver WBC’s PPM programme until 1 July 2026. This extension allows the Council sufficient time to mobilise the new contractor, UE, and to confirm that all risks have been identified, mitigated, or resolved, or appropriately prioritised for handover from SMS to UE. In April, SMS attended all scheduled tasks; however, only 35 (83%) were completed within the required timescales. The remaining seven tasks required follow-on works, five of which have now been completed and are awaiting invoicing.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Water Remedial Actions Progress ReportReport 786 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

14 of 18 attended
PR
Councillor Paul RiversChair, present
TD
Terry DaubneyVice Chair, present
JC
Councillor Janet CroweCommittee Member, present
AL
Councillor Andrew LaughtonCommittee Member, apologies
JK
Councillor Jacquie KeenCommittee Member, apologies
AM
Councillor Alan MorrisonCommittee Member, present
RB
Rod BlackmoreCommittee Member, present
RS
Robert StratfordCommittee Member, present
DW
Dave WilliamsObserver, expected
DM
Dave MaddamsObserver, expected
AF
Alex FosterOfficer, present
AH
Annalisa HowsonOfficer, present

All 18 on the meeting page

On this subject at Waverley

Search all
  1. Water Remedial Actions Progress ReportThis decision
  2. Water Remedial Actions Progress ReportNoted
  3. Water Remedial Actions Progress ReportNoted
  4. Water Remedial Actions Progress ReportNoted
  5. New Contract for Water Hygiene Remedial WorksApproved

More from Waverley Landlord Services Advisory Board (Executive Working Group)

All decisions
MeetingDecisionOutcome
30 Jul 2026 Capital Programme updateRESOLVED that the Capital Programme update be noted. Noted Open
30 Jul 2026 Council Response to Tenant Panel Proposal on Repairs, Maintenance and Service AppointmentsRESOLVED that: · the tenant panel proposal be noted, · the principles of a standardized appointments and communicatio... Noted Open
30 Jul 2026 Low Carbon Heating SolutionsRESOLVED that the Low Carbon Heating Solutions report be noted. Noted Open
30 Jul 2026 Water Hygiene ReportRESOLVED that the monthly Water Hygiene Report be noted. Noted Open
30 Jul 2026 Landlord Services Improvement Plan Update [2025-26]RESOLVED that the Landlord Services Improvement Plan update was noted. Noted Open