Resolved
The overall position as at quarter 2 on the capital programme and the update on the capital funding and reserves position was noted.
Cabinet noted this item on Tuesday 6 November 2018. Below is the council's own wording, with the papers it was decided on.
Resolved
The overall position as at quarter 2 on the capital programme and the update on the capital funding and reserves position was noted.
Capital Schemes progress to date Appendix B
1 Hatfield Town Centre (HTC) – Original budget for 2018/19 is £7.883m plus budgets for Highview redevelopment of £0.384m. The current budget of £10.875m includes rolled forward budgets from 2017/18 of £2.608m. Phase two of the redevelopment is now being delivered including public realm costs and the development of the new multi storey car park in Hatfield and the upper level of the Lemsford Road car park. Other expenditure in year includes roof works to Culpitt House, Hatfield Town Centre 2030 and the development of 1 & 3-9 Hatfield Town Centre. The current forecast reflects the re-phasing of £7.651m of major schemes into 2019/20.
2 Strategic Property Investment – Original Budget for 2018/19 is £5.000m with rolled forward budget from 2017/18 of £4.316m giving a forecast of £9.317m. The property investment programme aims to support the council’s wider economic development regeneration, as well as generating a net income return to the general fund. The council has completed the purchase of 88 Town Centre, and a payment of £725k has been made as a deposit for the purchase of Stonehills retail units in Welwyn Garden City.
3 Hunters Bridge car park concrete waterproofing – Rolled forward budget in 2018/19 is £0.552m. Budget is to restore and preserve the appearance and water-proofing to the concrete members. The works are to refurbish the surface finishes which are delaminating or separating from the concrete below, thus preventing further water to enter the concrete and damage to the reinforcement inside. The current forecast shows a reduction of £0.372m which reflects that substantial part of the main works will be carried out in the early part of 2019/20 leaving £0.180m in the current year to fund the contract tender award.
4 Bereavement Services – Rolled forward budget in 2018/19 is £4.066m. The budget will be used for the construction of the new crematorium. An update to the forecast outturn has been made as although works have started on this project, the scheme will not complete during the financial year and will cross into 2019/20. The tender for the works will commence following receipt of a successful planning decision. It is anticipated that £2.9m will be re-phased to 2019/20.
5 Development of Splashlands Site (Stanborough) – Rolled forward budget in 2018/19 is £2.291m. This budget is to continue development of the new leisure facilities to complete the regeneration of the former Splashlands site at Stanborough Park.
6 Affordable Housing Programme - Original budget is £16.547m. Cabinet agreed on 7 August 2012 for the council to enter into an agreement to allow the council to retain receipts from the reinvigorated Right to Buy (RTB) sales and to reinvest in the delivery of new affordable
-1- homes within the district. These receipts need to be spent within three years of the receipt being received.
The council’s Affordable Housing Programme delivers new affordable housing through a range of methods including property acquisition, grant funding Registered Providers and direct new build. There are fourteen schemes in the current programme. The largest expenditure this year relates to seven new build houses at Little Mead, Hatfield and the redevelopment of sixteen flats at Northdown Road, Hatfield plus open market purchases and grants to registered providers.
7 Disabled Facilities Grant & Decent Homes Grant – Original budget for 2018/19 DFG is £0.471m. The council receives grant funding which meets the cost of Disabled Facilities Grant expenditure via the County Council from the Ministry of Housing, Communities and Local Government (MHCLG)’s Better Care Fund. The 2018/19 determination is expected to be £0.709m in year.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
12a: Appendix AAppendix | 24 KB | Download |
PDF |
12b: Capital Monitoring Appx BReport | 61 KB | DownloadRead as text |
PDF |
CAPITAL BUDGET MONITORING AS AT 30 SEPTEMBER 2018 (QUARTER 2)Report | 88 KB | Download |
Follow Cabinet at Welwyn Hatfield and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 8 Sep 2026 | MINUTESThe minutes of the meeting on 11 August 2026 were approved as an accurate record. | Approved | Open |
| 8 Sep 2026 | ApologiesNo apologies for absence were received. | Decided | Open |
| 8 Sep 2026 | Actions status reportCabinet noted the Action Status report. | Noted | Open |
| 8 Sep 2026 | Notification of urgent business to be considered under items 10 & 13One urgent item of business was considered. | Decided | Open |
| 8 Sep 2026 | Declarations of interests by membersCouncillor Quinton declared an interest in agenda item 7b, Business Improvement District Welwyn Garden City and recus... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.