The report presented the capital expenditure and associated capital funding as at the end of Quarter 1 (June 2023). The report and appendices detailed the changes to the original capital programme and funding plans, as a result of programme commitments and project delivery. The current approved capital budget is £95.304m (which includes the approved re-phasing of budgets from 2022/23) and the forecast outturn is £78.922m. A summary of forecast variances and re-phasing was shown in Table 1 and detailed explanations for key variances in Section 3.4. A summary of progress against key projects for which no variances had been identified was detailed within Section 3.5. A forecast of the resources available to fund the capital programme and variances of the current forecast against the available resources budgeted were set out in Section 4 of the report. DECISION TAKEN: Cabinet noted the capital forecast outturn position as shown in Table 1. Cabinet approved the virements set out in Section 3.4.2. Cabinet noted the forecast position as at 30 June 2023 for funding of the capital programme and reserve balances as reflected in Table 2.
Word for word from the decision Welwyn Hatfield published for this meeting.Source: democracy.welhat.gov.uk
Part I Item No: 9 Main Author: Helen O’Keeffe Executive Member: Cllr Duncan Jones All Wards
WELWYN HATFIELD BOROUGH COUNCIL CABINET – 8 AUGUST 2023 REPORT OF THE EXECUTIVE DIRECTOR (FINANCE AND TRANSFORMATION)
QUARTER 1 CAPITAL BUDGET MONITORING REPORT 2023-24
1 Executive Summary 1.1 This report presents the capital expenditure and associated capital funding as at the end of Quarter 1 (June 2023). The report and appendices detail the changes to the original capital programme and funding plans, as a result of programme commitments and project delivery. 1.2 The current approved capital budget is £95.304m (which includes the approved re-phasing of budgets from 2022/23) and the forecast outturn is £78.922m. A summary of forecast variances and re-phasing are shown in Table 1 and detailed explanations for key variances in Section 3.4. 1.3 A summary of progress against key projects for which no variances have been identified is detailed within Section 3.5. 1.4 A forecast of the resources available to fund the capital programme and variances of the current forecast against the available resources budgeted are set out in Section 4 of this report.
2 Recommendations 2.1 That Cabinet note the capital forecast outturn position as shown in Table 1. 2.2 That Cabinet approve the virements set out in Section 3.4.2. 2.3 That Cabinet note the forecast position as at 30 June 2023 for funding of the capital programme and reserve balances as reflected in Table 2.
3 Capital Programme – Expenditure Forecasts Capital Budgets 3.1 The following table tracks approved changes to the original budget during the year (excluding fully funded virements).
£
Original Budget £41.327m
Re-phasing from 2022/23 £53.977m
Current Budget £95.304m
3.2The capital expenditure position is summarised in Table 1 below and a detailed breakdown by capital scheme can be found in Appendix A. Table 1 uses rounded figures so there may be slight addition discrepancies. Table 1: Capital Outturn 2023/24 by Fund and Directorate
Re- (Under)/ Forecast Variance phasing Budget Over Outturn to of 2022/23 Forecast 2022/23 Budget Capital Outturn Schemes
£'000 £'000 £'000 £'000 £'000
General Fund Executive Director (Finance and Transformation) 3,256 4,056 800 0 800
Executive Director (Place) 7,593 7,662 69 0 69 Service Director (Property Maintenance and Climate Change) 1,988 1,988 0 0 0
Service Director (Resident and Neighbourhood) 2,277 2,277 0 0 0
General Fund Total 15,115 15,983 869 0 869 Housing Revenue Account Executive Director (Finance and Transformation) 69 69 0 0 0 Executive Director (Place) 34,088 25,686 (8,402) 12,437 4,035 Service Director (Property Maintenance and Climate Change) 45,907 37,058 (8,849) 6,710 (2,139)
Service Director (Resident and Neighbourhood) 125 125 0 0 0 Housing Revenue Account Total 80,190 62,939 (17,252) 19,147 1,896
Grand TOTAL 95,304 78,922 (16,383) 19,147 2,765
3.3There is currently a requirement to re-phase £19.147m split between funds as follows: HRA £19.147m – re-phase budget into 2024/25 General Fund £0 – re-phase budget into 2024/25 Total net re-phasing - £19.147m
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Declarations of interests by membersCouncillor Quinton declared an interest in agenda item 7b, Business Improvement District Welwyn Garden City and recus...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.