RESOLVED - ( i ) That the allocation of £650k to Crematorium Refurbishment Scheme in 2020/21 as outlined is paragraph 2.4 of report COFI/46/19 be approved. (ii) That the capital outturn for 2018/19 be noted. (iii) That the rolling programme for 2019/20 to 2022/23 as detailed in appendices 2 and 3 be approved. (iv) That the capital programme be next reviewed and reported to the Executive Board in October 2019. Reasons for decisions ( i ) This report follows an earlier monitoring report in February in compliance with Financial Regulation 3.13 that requires that the Chief Officer Finance & ICT monitors and reports to Members on the Capital Programme. (ii) Local Authorities are required under the Local Government Act 2003 to comply with the CIPFA Prudential Code for Capital Finance.
Word for word from the decision Wrexham published for this meeting.Source: moderngov.wrexham.gov.uk
To advise Members of the 2018/19 Capital Programme outturn (the figures are subject to audit) and to review the 2019/20 – 2022/23 Capital programme.
Executive summary
2.1The total capital expenditure in 2018/19 including the Housing Revenue Account (HRA) was £58,004k. This is £11,239k less than the total approved by the Executive Board at its meeting on 12 February 2019 (HF/10/19). The main reasons for the net decrease are:
• Slippage of spend on non HRA projects from 2018/19 to 2019/20 of £5,779k. • A net decrease in spend of £531k on non HRA projects. • A net decrease in spend in the HRA Capital programme of £4,929k.
2.2The Capital Programme is fully funded by borrowing supported by the Welsh Government, grants and contributions, capital receipts and prudential borrowing and interest free loans from Welsh Government and Salix.
2.3On 14 May 2019 the Executive Board (COFI/35/19) approved the transfer of £104k initially to the capital reserve to fund specific projects.
2.4Executive Board 9 February 2016 (HF/09/16) and 11 October 2016 (HF/91/16), approved the allocation of Welsh Government General Capital Funding to projects in 2019/20 and 2020/21. £350k was awarded to refurbish the Crematorium cremators and abatement system in 2019/20 with £200k allocated to the scheme for 2020/21. The current estimated cost is much higher than originally anticipated with a further £650k required in 2020/21. It is proposed to fund the additional costs from £246k previously unallocated funding and £404k from the capital reserve.
Recommendations
3.1The allocation of £650k to Crematorium Refurbishment Scheme in 2020/21 as outlined is paragraph 2.4 is approved.
3.2The capital outturn for 2018/19 is noted.
3.3The rolling programme for 2019/20 to 2022/23 as detailed in appendices 2 and 3 is approved.
3.4The capital programme is next reviewed and reported to the Executive Board in October 2019.
Reasons for recommendations
(i) This report follows an earlier monitoring report in February in compliance with Financial Regulation 3.13 that requires that the Chief Officer Finance & ICT monitors and reports to Members on the Capital Programme.
(ii) Local Authorities are required under the Local Government Act 2003 to comply with the CIPFA Prudential Code for Capital Finance.
4. BACKGROUND INFORMATION
Capital Programme 2018/19
4.1The Executive Board approved the last revision of the capital programme 2018/19 to 2022/23 on 12 February 2019 (HF/10/19). Appendix 1 provides a summary of expenditure by service, the financing of that expenditure and the variance between the actual programme and the previously approved position.
4.2The actual expenditure on all capital schemes was £58,004k, a net decrease of £11,239k compared with the projected expenditure reported to the Executive Board in February 2019. The significant changes are as follows;-
Slippage of Expenditure to 2019/20
4.3Changes to the phasing of expenditure have resulted in £5,779k of spending originally planned in 2018/19 to be rescheduled to 2019/20. Projects where significant slippage has occurred are set out below:
• ICT Infrastructure (-£282k). Due to delays in starting the new build data centre. The tender has now been awarded with payments due in 2019/20.
• Re-roofing work Redwither Tower (-£392k). The scheme was originally delayed but work is now ongoing with an anticipated completion date of July 2019.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.