RESOLVED - (i) That t he Capital Programme outturn, as detailed in appendices 1 and 1a to report COFI/26/25, be approved. (ii) That the Quarter 1 and future years’ programme as detailed in appendices 2 and 2a be approved. Reason for decisions This report follows an earlier monitoring report in March in compliance with Financial Regulation 3.13 that requires that the Chief Officer Finance & ICT monitors and reports to Members on the Capital Programm e.
Word for word from the decision Wrexham published for this meeting.Source: moderngov.wrexham.gov.uk
To advise Members of the 2024/25 Capital Programme Outturn and to review the 2025/26 and future years’ capital programme position as at the end of Quarter 1 2025/26.
Executive summary
2.1The total capital expenditure in 2024/25 including the Housing Revenue Account (HRA) was £76,506k as detailed in Appendix 1. This is £15,257k less than the total approved by the Executive Board at its meeting on 11 March 2025 COFI/05/25. The reasons for the net decrease are:
A net decrease in spend of £11,452k on non HRA projects including new or additional grant funding and some re-phasing of spend to future years. A net decrease in spend of £3,805k in the HRA capital programme.
2.2Each scheme within the Capital Programme is fully funded by borrowing supported by the Welsh Government, grants and contributions, capital receipts, and prudential borrowing. All schemes are reviewed as part of the quarterly monitoring exercise and the details are included in Appendices 1 and 1a.
2.3The resources available to fund the programme comprise Welsh Government un-hypothecated and hypothecated supported borrowing, grants, contributions, capital receipts and prudential system unsupported borrowing. 2.4 By their very nature, capital programmes are dynamic and during the course of the year, further funds may be made available for specific schemes. Levels of capital receipts are kept under review to ensure sufficient amounts are realised in line with planning assumptions. Therefore the current and future years within the programme are subject to changes as schemes develop and funding streams, such as specific grants, are confirmed. However, a significant part of the future programme can be determined now because of confirmed plans and funding being in place. This includes the continuation of annual capital provisions that are funded by General Capital Funding (GCF).
2.5Future year capital allocations of £6.86m were approved in March (COFI/05/25). As previously reported, requests for capital project funding have now been submitted by services and have been assessed. As a consequence, a further £6m of schemes have been allocated in 2025/26, a further £5.3m in 2026/27, £3.2m in 2027/28 and a further £4.2m in 2028/29. This includes an additional £2m per annum of support for highway maintenance and infrastructure improvements for the 2025/26 – 2028/29 period. The results of this exercise are reflected in Appendix 2a.
2.6Welsh Government have confirmed that a new capitalisation direction will be in place from 1 April 2025 to 31 March 2030. The revised capital receipts policy approved by Executive Board in March 2025 (COFI/05/25) will remain in place for 2025/26. The policy will be reviewed for 2026/27, taking account of the revenue budget position at that time and the funding requirements of the capital programme.
Recommendations
3.1The Capital Programme outturn as detailed in appendices 1 and 1a is noted and approved.
3.2The Quarter 1 and future years’ programme as detailed in appendices 2 and 2a is approved.
Reason for recommendations
This report follows an earlier monitoring report in March in compliance with Financial Regulation 3.13 that requires that the Chief Officer Finance & ICT monitors and reports to Members on the Capital Programme.
4 BACKGROUND INFORMATION Capital Programme 2024/25
4.1The Executive Board approved the last revision of the capital programme 2024/25 on 11 March 2025 (COFI/05/25). Appendix 1 provides a summary of expenditure by service, the financing of that expenditure and the variance between the actual programme and the previously approved position.
4.2The actual expenditure on all capital schemes is £76,506k, a net decrease of £15,257k compared with the projected expenditure at quarter 3. The significant changes are as follows;-
Economy & Planning (-£2,897k)
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.