Wrexham County Borough Council
Executive Board, Tuesday 10 March 2026 at 10.30am

Capital Programme and Treasury Management Quarter 3 Review 2025/26

Noted Executive 6 papers

AI summaryWrexham Executive Board approved the 2025/26 Quarter 3 Capital Programme at £110,651k, a £1,484k net increase, and noted Treasury Management activity to 31 December 2025.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedProgramme noted and approved, including HRA
Money£110,651k total capital programme 2025/26Net increase of £1,484k from November 2025 approval
What happens nextQ4 monitoring report to followFuture years programme to 2028/29 totals £363.9m
Who it affectsAll council services and HRA residentsEducation, environment, social care and housing schemes

What was decided

The Executive Board approved the Quarter 3 Capital Programme for 2025/26 as set out in Appendices 1 and 2 of report COFI/09/26. Report 3.1

The Executive Board noted and approved the Quarter 3 Treasury Management Activity in Appendix 3. Report 3.2

Why

The report complies with Financial Regulation 3.13, which requires the Chief Officer Finance & ICT to monitor and report on the Capital Programme to members. Report P8

Each scheme is fully funded by borrowing supported by the Welsh Government, grants and contributions, capital receipts, and prudential borrowing, and is reviewed quarterly. Report 2.2

What happens next

The 2026/27 programme has risen to £121,575k from £116,261k, reflecting the revised HRA Capital Programme approved in January 2026. Report 4.7

Capital receipts policy continues to apply without ring-fencing, under a new Welsh Government capitalisation direction running from 1 April 2025 to 31 March 2030, and will be reviewed for 2026/27. Report 4.9, 4.10

The money

  • £110,651k Total capital expenditure 2025/26 including HRA Report 2.1, 4.3
  • £1,484k Net increase on previously approved programme Report 2.1, 4.3
  • £978k Net increase on non-HRA projects Report P3
  • £506k Net increase on HRA Capital Programme Report P3, P22
  • £52,945k Total spend to date in Quarter 3, including HRA Report 4.3
  • £25,641k HRA spend to date in Quarter 3 Report 4.3
  • £681k Ysgol Bryn Alyn 3G Pitch Replacement, fully grant funded Report P15, P16
  • £196k National Forest for Wales Landscape Scheme, fully grant funded Report P17, P18
  • £101k Childcare Offer Grant Report P19, P20
  • £42.8m Revised total projected HRA capital expenditure for 2025/26 Report P22
  • £7.809m Wrexham General Capital Funding 2025/26 Report 4.5
  • £791k Increase in GCF from 2024/25 allocation Report 4.5
  • £121,575k Revised 2026/27 capital programme Report 4.7
  • £116,261k Previous 2026/27 capital programme Report 4.7
  • £21.8m Capital receipts funding required for proposed programme Report 4.8, P33
  • £600k Transfer from External Wall Insulation to windows and doors programme Report P24
  • £363.9m Total programme to 2028/29 including HRA Report 5.2

Options considered

  • Chosen: Approve the Quarter 3 Capital Programme 2025/26 and Treasury Management Activity. Required to comply with Financial Regulation 3.13 and reflect updated grant funding and rephasing Report 3.1, 3.2, P8

Implications

  • Financial: Total 2025/26 capital programme is £110.7m, with £363.9m planned to 2028/29 including HRA. Report 5.2
  • Risk: Risks include capital receipts not being delivered to planned levels, reduced General Capital funding, and project overspends. Report 5.6, P45
  • Legal: Significant legal implications of individual projects are the subject of separate, project specific reports. Report 5.3
  • Equalities: Impact Assessments are undertaken in relation to specific projects as required. Report 5.5
  • Staffing: There are no direct staffing implications as a result of this report. Report 5.4
  • Other: External Wall Insulation budget has experienced refusals and contractual delays; £600k transferred to support the windows and doors programme, contributing to WHQS 2023 and the Council's decarbonisation journey. Report P24

Who and where

  • HRA tenants and residents (changes to External Wall Insulation and windows and doors programmes) Report P24
  • Pupils and users of Ysgol Bryn Alyn (new 3G pitch replacement) Report P15, P16
  • Childcare providers and families (Childcare Offer Grant) Report P19, P20
  • Welsh Government grant programmes (Optimised Retrofit Programme, National Forest for Wales) Report P18, P22

Timeline

  • 20 February 2025: Welsh Government announced 2025/26 final Revenue and Capital Settlement Report 4.5
  • 1 April 2025 to 31 March 2030: Welsh Government capitalisation direction in place Report 4.10
  • 8 July 2025: Future years' programme approved by Executive Board Report 4.6
  • 16 October 2025: Council notified of grant funding for National Forest for Wales Landscape Scheme Report P18
  • 20 October 2025: Confirmation received that Optimised Retrofit Programme additional funding application of £506k was successful Report P22
  • 11 November 2025: Previous revision of capital programme 2025/26 approved by Executive Board (COFI/37/25) Report 4.1
  • 31 December 2025: Treasury Management activity reported up to this date Report 4.11
  • 20 January 2026: Revised HRA Capital Programme approved by Executive Board (COH/01/26) Report 4.7
  • 10 March 2026: Executive Board considered and approved this report

Plain English for the jargon

  • HRA: Housing Revenue Account, the account covering income and spending on council housing.
  • GCF: General Capital Funding, the main Welsh Government capital grant to local authorities.
  • GCG: General Capital Grant from the Welsh Government.
  • MRA: Major Repairs Allowance, Welsh Government funding for housing repairs.
  • WHQS 2023: Welsh Housing Quality Standard 2023, the standard council homes are required to meet.
  • CIPFA Prudential Code: Professional code requiring local authorities to demonstrate capital plans are affordable, prudent and sustainable.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item106

Resolved

RESOLVED – ( i ) That the Quarter 3 Capital Programme for 2025/26 as detailed in Appendices 1 and 2 of report COFI/09/26 be noted and approved. (ii) That the Quarter 3 Treasury Management Activity in Appendix 3 be noted and approved. Reason for Decisions This report follows an earlier monitoring report in November in compliance with Financial Regulation 3.13 that requires that the Chief Officer Finance & ICT monitors and reports to Members on the Capital Programme.
Word for word from the decision Wrexham published for this meeting. Source: moderngov.wrexham.gov.uk

Follow this further

Built from Wrexham's papers

What the report saysPro

Report to Executive Board

Purpose of the report

To review the 2025/26 Capital Programme position as at the end of Quarter 3 2025/26 and Treasury Management Activity.

Executive summary

2.1The total capital expenditure in 2025/26 including the Housing Revenue Account (HRA) is estimated to be £110,651k as detailed in Appendix 1. This is £1,484k more than the total approved by the Executive Board at its meeting on 11 November 2025 COFI/37/25. The reasons for the net increase are:

 A net increase in spend of £978k on non HRA projects including new or additional grant funding and some re-phasing of spend to future years.  A net increase in spend of £506k in the HRA Capital Programme due to additional grant funding.

2.2Each scheme within the Capital Programme is fully funded by borrowing supported by the Welsh Government, grants and contributions, capital receipts, and prudential borrowing. All schemes are reviewed as part of the quarterly monitoring exercise and the details are included in Appendix 1. 2.3 The resources available to fund the programme comprise Welsh Government un-hypothecated and hypothecated supported borrowing, grants, contributions, capital receipts and prudential system unsupported borrowing.

2.4By their very nature, capital programmes are dynamic and during the course of the year, further funds may be made available for specific schemes. Levels of capital receipts are kept under review to ensure sufficient amounts are realised in line with planning assumptions. Therefore, the current and future years within the programme are subject to changes as schemes develop and funding streams, such as specific grants, are confirmed. However, a significant part of the future programme can be determined now because of confirmed plans and funding being in place. This includes the continuation of annual capital provisions that are funded by General Capital Funding (GCF). 2.5 The future years’ programme was approved by the Executive Board at its meeting on 8 July 2025 and this has been updated in Appendices 2 and 2a to reflect the re-phasing of spend as detailed at paragraph 4.3 of this report.

Recommendations

3.1The Quarter 3 Capital Programme for 2025/26 as detailed in appendices 1 and 2 is noted and approved.

3.2The Quarter 3 Treasury Management Activity in Appendix 3 is noted and approved.

REASONS FOR RECOMMENDATIONS (i) This report follows an earlier monitoring report in November in compliance with Financial Regulation 3.13 that requires that the Chief Officer Finance & ICT monitors and reports to Members on the Capital Programme.

4 BACKGROUND INFORMATION

Capital Programme 2025/26

4.1The Executive Board approved the last revision of the capital programme 2025/26 on 11 November 2025 (COFI/37/25). Appendix 1 provides a summary of expenditure by service, the financing of that expenditure and the variance between the actual programme and the previously approved position.

4.2The revised programme includes

 revised forecasts of expenditure on committed schemes.  projects which have received specific funding or been agreed by the Executive Board.  annual capital provisions.

4.3The revised estimate on all capital schemes is £110,651k, a net increase of £1,484k compared with the projected expenditure reported to the Executive Board in November 2025. Total spend to date in Quarter 3 is £52,945k including £25,641k HRA. The significant changes, detailed in Appendix 1a, are as follows;-

Education and Early Intervention (+681k)

 Ysgol Bryn Alyn 3G Pitch Replacement (+£681k) – This is a new project which is fully grant funded by the Cymru Football Foundation.

Environment and Technical (+£196k)

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Appendix 1Appendix 1 273 KB Download
PDF
Appendix 1aAppendix 1a 84 KB Download
PDF
Appendix 2Appendix 2 469 KB Download
PDF
Appendix 2aAppendix 2a 76 KB Download
PDF
Appendix 3Appendix 3 250 KB Download
PDF
Capital Programme and Treasury Management Quarter 3 Review 2025/26Report 560 KB DownloadRead as text

At this meeting

Whole meeting
102Confirmation of MinutesDecided 103QuestionsOn the agenda 1052025/26 Quarter 3 Revenue Budget UpdateDecided
106Capital Programme and Treasury Management Quarter 3 Review 2025/26This decision

Who was there

8 of 18 attended
DA
Councillor David A BithellVice-Chair, present
TE
Councillor Terry EvansCommittee Member, present
HJ
Councillor Hugh JonesCommittee Member, present
BP
Councillor Beverley Parry-JonesCommittee Member, present
JP
Councillor John PritchardCommittee Member, apologies
MP
Councillor Mark PritchardChair, present
PR
Councillor Paul RobertsCommittee Member, present
RW
Councillor Robert WalshCommittee Member, apologies
NW
Councillor Nigel WilliamsCommittee Member, present
PW
Councillor Phil WynnCommittee Member, present
BA
Councillor Bryan ApsleyGuest, in attendance, virtual
BC
Councillor Brian CameronGuest, in attendance, virtual

All 18 on the meeting page

On this subject at Wrexham

Search all
  1. Capital Programme and Treasury Management Quarter 3 Review 2025/26This decision
  2. 2025/26 Capital Programme Outturn and 2026/27 Quarter 1 Programme UpdateNoted
  3. Education Capital Investment - Sustainable Communities for Learning ProgrammeNoted
  4. 2024/25 Capital Programme Outturn and 2025/26 Quarter 1 Programme UpdateApproved
  5. Capital Programme and Treasury Management quarter 3 review 2024/25Approved
  6. 2023/24 Capital Programme Outturn and 2024/25 Quarter 1 Programme UpdateNoted

More from Wrexham Executive Board

All decisions
MeetingDecisionOutcome
15 Sep 2026 Council Plan - Annual Performance Report 2025/26 and Year 4 Target SettingRESOLVED – ( i ) That the ‘Council Plan Annual Performance Report 2025/26’ as outlined in Appendix A of report CE/14/... Approved Open
15 Sep 2026 Brymbo Sports& Social Complex, Heritage Way, Tanyfron, Wrexham, LL11 5TGRESOLVED – ( i ) That the grant of a new lease be authorised, for a minimum term of 75 years, at a nominal rent of £1... Decided Open
15 Sep 2026 Local Development Plan Delivery AgreementRESOLVED – ( i ) That the Wrexham be approved for submission to the Welsh Government for their approval. (ii) That th... Approved Open
15 Sep 2026 Update: Wrexham UK City of Culture 2029 BidRESOLVED – That the Executive Board continue to demonstrate their full support for Wrexham's bid to become UK City of... Decided Open