RESOLVED – ( i ) That the allocation of Welsh Government General Capital Funding in 2024/25 recommended by the Corporate Land and Buildings Strategy Group shown in paragraph 4.24 of report COFI/38/20 be approved. (ii) That t he allocation of the Heritage and Community Well Being Annual Capital Provision outlined in paragraph 4.26 of report COFI/38/20 be approved. (iii) That the allocation of £150k to ICT Infrastructure as outlined in paragraph 2.4 of report COFI/38/20 be approved. (iv) That the rolling programme for 2020/21 to 2024/25 as detailed in appendices 2 and 3 of report COFI/38/20 be approved. (v) That the capital programme be reviewed by the Executive Board in February 2021. (vi) That the Semi Annual Treasury Management Activity in Appendix 4 of report COFI/38/20 be noted. (vii) That the change to the reporting criteria and the revised Treasury Management Policy Statement and Treasury Management Practices in Appendix 5 of report COFI/38/20 be noted. Reasons for decisions ( i ) This report follows an earlier monitoring report in July in compliance with Financial Regulation 3.13 that requires that the Chief Officer Finance & ICT monitors and reports to Members on the Capital Programme. (ii) Local Authorities are required under the Local Government Act 2003 to comply with the CIPFA Prudential Code for Capital Finance. (iii) To comply with the CIPFA Code of Practice on Treasury Management and the Council’s Treasury Management policy
Word for word from the decision Wrexham published for this meeting.Source: moderngov.wrexham.gov.uk
To review the 2020/21 – 2024/25 Capital Programme and semi-annual Treasury Management Activity and revised Treasury Management Policy Statement and Practices.
Executive summary
2.1The total capital expenditure in 2020/21 including the Housing Revenue Account (HRA) is estimated to be £67,738k. This is £1,254k more than the total approved by the Executive Board at its meeting on 14 July 2020 (COFI/23/20). The main reasons for the net increase are:
• Slippage of spend on non HRA projects from 2020/21 to 2021/22 of £1,781k. • A net increase in spend of £2,867k on non HRA projects. • A net increase in spend in the HRA capital programme of £168k.
2.2The Capital Programme is fully funded by borrowing supported by the Welsh Government, grants and contributions, capital receipts and prudential borrowing and interest free loans from Welsh Government and Salix.
2.3The Joint Member/Officer Corporate Land and Buildings Strategy Group has recommended projects to be allocated Welsh Government General Capital Funding in 2024/25.
2.4Executive Board (HCCS/73/16) on 11 October 2016 approved that the Authority should adopt a centralised model for ICT and invest in a comprehensive infrastructure redesign and refresh. Further expenditure is required on both the firewall and network connectivity in order to increase resilience across the Authority’s ICT Infrastructure. It is proposed to allocate an additional £150k from previously unallocated Welsh General Capital Funding to the scheme.
Recommendations
3.1The allocation of Welsh Government General Capital Funding in 2024/25 recommended by the Corporate Land and Buildings Strategy Group shown in paragraph 4.24 is approved.
3.2The allocation of the Heritage and Community Well Being Annual Capital Provision outlined in paragraph 4.26 is approved.
3.3The allocation of £150k to ICT Infrastructure as outlined in paragraph 2.4 is approved.
3.4The rolling programme for 2020/21 to 2024/25 as detailed in appendices 2 and 3 is approved.
3.5The capital programme is next reviewed and reported to the Executive Board in February 2021.
3.6The Semi Annual Treasury Management Activity in Appendix 4 are noted.
3.7The change to the reporting criteria and the revised Treasury Management Policy Statement and Treasury Management Practices in Appendix 5 are noted.
Reasons for recommendations
(i) This report follows an earlier monitoring report in July in compliance with Financial Regulation 3.13 that requires that the Chief Officer Finance & ICT monitors and reports to Members on the Capital Programme.
(ii) Local Authorities are required under the Local Government Act 2003 to comply with the CIPFA Prudential Code for Capital Finance.
(iii) To comply with the CIPFA Code of Practice on Treasury Management and the Council’s Treasury Management policy
4. BACKGROUND INFORMATION
Capital Programme 2020/21
4.1The Executive Board approved the last revision of the capital programme 2019/20 to 2023/24 on 14 July 2020 (COFI/23/20). Appendix 1 provides a summary of expenditure by service, the financing of that expenditure and the variance between the actual programme and the previously approved position.
4.2The revised estimate of expenditure on all capital schemes is £67,738k, a net increase of £1,254k compared with the projected expenditure reported to the Executive Board in July. The significant changes are as follows;-
Slippage of Expenditure to 2021/22
4.3Changes to the phasing of expenditure have resulted in £1,781k of spending originally planned in 2020/21 to be rescheduled to 2021/22. Projects where significant slippage has occurred are set out below:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.