RESOLVED – That the rolling programme for 2022/223 to 2024/25, as detailed in appendices 2 and 3 to report COFI/30/22 be approved. Reason for decision This report follows an earlier monitoring report in July in compliance with Financial Regulation 3.13 that requires that the Chief Officer Finance & ICT monitors and reports to Members on the Capital Programme.
Word for word from the decision Wrexham published for this meeting.Source: moderngov.wrexham.gov.uk
To review the 2022/23 – 2024/25 Capital Programme position as at the end of quarter 2 2022/23.
Executive summary
2.1The total capital expenditure in 2022/23 including the Housing Revenue Account (HRA) is estimated to be £103,424k. This is £1,183k more than the total approved by the Executive Board at its meeting on 12 July 2022 (COFI/17/22). The main reasons for the net increase are:
A net increase in spend including grant funding of £1,852k supporting non HRA projects Slippage of spend on non HRA projects from 2022/23 to future years of £669k
2.2The Capital Programme is fully funded by borrowing supported by the Welsh Government, grants and contributions, capital receipts and prudential borrowing and interest free loans from Salix.
2.3On 20 September 2022 the Executive Board (CE/49/22) received an update on the progress of the Wrexham Museum/Welsh Football Museum project. The report approved additional capital funding of £1m to be allocated to the project from previously unallocated capital funding in 2022/23. 3 RECOMMENDATION
3.1The rolling programme for 2022/223 to 2024/25 as detailed in appendices 2 and 3 is approved.
Reason for recommendation
(i) This report follows an earlier monitoring report in July in compliance with Financial Regulation 3.13 that requires that the Chief Officer Finance & ICT monitors and reports to Members on the Capital Programme.
4. BACKGROUND INFORMATION
Capital Programme 2022/23
4.1The Executive Board approved the last revision of the capital programme 2022/23 to 2024/25 on 12 July 2022 (COFI/17/22). Appendix 1 provides a summary of expenditure by service, the financing of that expenditure and the variance between the actual programme and the previously approved position.
4.2The revised estimate of expenditure on all capital schemes is £103,424k, a net increase of £1,183k compared with the projected expenditure reported to the Executive Board in July. The significant changes are as follows;-
Slippage of Expenditure to Future Years
4.3Changes to the phasing of expenditure have resulted in £669k of spending originally planned in 2022/23 to be rescheduled to future years. Projects where significant slippage has occurred are set out below:
ICT Infrastructure Modernisation (-£270k). Due to urgent requests and other projects taking longer than expected part of this allocation is now anticipated to be utilised in 2023/24.
Pontcysyllte Aqueduct & Canal World Heritage Site (-£399k). The allocation, which is now profiled to be utilised in 2023/24, is being used as match funding towards the Authority’s Levelling-up Fund award.
Other Changes
4.4Other variations between the revised capital programme reported in July and the actual expenditure account for a net increase in non HRA planned spending of £1,852k. The main reasons are as follows:
Wrexham Museum/Welsh Football Museum (-£1,000k). Following approval of previously unallocated capital funding towards the Welsh Football Museum, the funding will be required to support capital expenditure in 2024/25 and 2025/26.
Wrexham Town Centre Conservation/Heritage Scheme (-£290k). Additional grant from Welsh Government has been received for work to the indoor markets (see paragraph 4.17). The work to the markets will be prioritised this year with the previously allocated funding moved into 2023/24.
Office Accommodation Review (+£307k). The refurbishment of Crown Buildings/Wellbeing Hub was completed in March 2022 with the final payments and retention due to be paid in 2022/23. The anticipated underspend on the scheme has been carried forward to Phase 4 of the OAR as outlined in Executive Board on 7 December 2021(COHE/50/21), together with funding brought forward from 2023/24.
Universal Free School Meals (+£1,500k). Award of grant funding from Welsh Government (see paragraph 4.18).
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.