City of York Council
Executive, Thursday 26 September 2019 at 5.30pm

York Outer Ring Road Improvements Update

Noted Executive 4 papers

Executive noted this item on Thursday 26 September 2019. Below is the council's own wording, with the papers it was decided on.

Item48

Resolved

( i ) That the potential grant award of around £26m from the Department for Transport ( DfT ) for upgrading the A1237 (Phase 1 Dualling : Rawcliffe to Hopgrove ), and the need to co-ordinate planning and design work on the current junction upgrade programme, be noted. Reason: To confirm that the Executive is aware of the potential impacts of co-ordinating design and construction on the YORR programme. (ii) That the inclusion in Transport for the North’s Regional Evidence Base submission to the DfT of a scheme to dual the A1237 from A19 Rawcliffe to B1223 Wetherby Road (Phase 2 Dualling : Rawcliffe to Wetherby Road) be noted. Reason: To confirm that the Executive has been informed about the current status of proposals for dualling sections of the A1237 York Outer Ring Road (YORR). (iii) That officers be instructed to investigate options for the introduction of further measures across the city to lock in the sustainable transport and environmental benefits that could result from the increased capacity provided by dualling the A1237. Reason: To ensure that the potential for significant sustainable transport and environment benefits resulting from the dualling of the YORR are investigated further, with options presented to Members for future decision. (iv) That, subject to Council approval of the recommended budget (Minute 51 refers), approval be given to procure a contractor to undertake the civil engineering and associated construction works and authority be delegated to the Assistant Director for Transport, Highways and Environment, in consultation with the Assistant Director of Legal & Governance or his / her delegated officers, to take such steps as are necessary to award and enter into the resulting contract, with the final layout being subject to the approval of the Executive Member for Transport following consideration of a report reviewing the landscaping, drainage and highway integration for east-west cyclingand walking routes and options for the Hurricaine Way B&Q junction. Reason: To enable the procurement process for a contractor to be undertaken and the resulting contract awarded. (v) That officers be requested to identify opportunities to reduce the City of York Council’s contribution through external funding (HIF, developer contributions etc.) which, if successful, will reduce overall CYC borrowing. Reason: To reduce the council’s overall financial contribution. (vi) That approval be given in principle to pursue a Compulsory Purchase Order (CPO) using powers contained in Part XII of the Highways Act 19802 to acquire the land edged red on the plan attached as Annex C to the report, which is required to deliver the Monks Cross Junction improvements. Reason: To enable Executive to consider a report in December seeking authority to make the Order, should continuing negotiations to acquire the land not be successful. (vii) That authority be delegated to the Assistant Director of Transport, Highways and Environment to take all steps necessary to prepare for the CPO referred to in resolution (vi) above, this delegatin to include: · negotiation of easements and temporary rights where freehold ownership is not required, e.g. for drainage ... ( i ) That the potential grant award of around £26m from the Department for Transport ( DfT ) for upgrading the A1237 (Phase 1 Dualling : Rawcliffe to Hopgrove ), and the need to co-ordinate planning and design work on the current junction upgrade programme, be noted. Reason: To confirm that the Executive is aware of the potential impacts of co-ordinating design and construction on the YORR programme. (ii) That the inclusion in Transport for the North’s Regional Evidence Base submission to the DfT of a scheme to dual the A1237 from A19 Rawcliffe to B1223 Wetherby Road (Phase 2 Dualling : Rawcliffe to Wetherby Road) be noted. Reason: To confirm that the Executive has been informed about the current status of proposals for dualling sections of the A1237 York Outer Ring Road (YORR). (iii) That officers be instructed to investigate options for the introduction of further measures across the city to lock in the sustainable transport and environmental benefits that could result from the increased capacity provided by dualling the A1237. Reason: To ensure that the potential for significant sustainable transport and environment benefits resulting from the dualling of the YORR are investigated further, with options presented to Members for future decision. (iv) That, subject to Council approval of the recommended budget (Minute 51 refers) , approval be given to procure a contractor to undertake the civil engineering and associated construction works and authority be delegated to the Assistant Director for Transport, Highways and Environment, in consultation with the Assistant Director of Legal & Governance or his / her delegated officers, to take such steps as are necessary to award and ... view the full minutes text for item 48.
Word for word from the decision York published for this meeting. Source: democracy.york.gov.uk

Follow this further

Built from York's papers

What the report saysPro

Report to Executive, 19 pages

Summary

1. Planning and development work for the York Outer Ring Road (YORR) Improvement scheme commenced in 2017 and the first junction upgrade was completed in early 2019. As the scheme is evolving, the phasing of the six remaining junctions is subject to various changing conditions and challenges.

2. Various opportunities for the provision of grant funding from Central Government for enhancing the capacity of the Outer Ring Road are being progressed by City of York Council (CYC) and Transport for the North. Currently no decisions have been made at Central Government level to confirm whether these bids have been successful.

3. A decision is needed on funding to enable the construction of an enhanced junction and underpass at the A1237/Clifton Moor roundabout which would provide access and pedestrian/cycle facilities to a site allocated for housing in the draft Local Plan.

4. To facilitate the acquisition of necessary land and/or rights over land, against a background of some protracted land acquisition negotiations, Executive Members are asked approve the principle of pursuing a Compulsory Purchase Order using powers contained in Part XII of the Highways Act 1980 to acquire the land edged red on the plan attached to this report at Annex C required to deliver the Monks Cross Junction improvements. A separate report requesting the endorsement of the making of one or more Compulsory Purchase Orders will be brought to Executive in due course. Officers would endeavour to continue negotiations with landowners during any Compulsory Purchase Order process. Recommendations

5. The Executive are requested to:

1) Note the potential grant award from the DfT of c. £26m for upgrading the A1237 (Phase 1 Dualling (Rawcliffe to Hopgrove)) and the need to co-ordinate planning and design work on the current junction upgrade programme.

Reason: To be aware of the potential impacts of co-ordinating the design and construction on the YORR Programme.

2) Note the inclusion of a scheme to dual the A1237 from A19 Rawcliffe to B1223 Wetherby Road (Phase 2 Dualling (Rawcliffe to Wetherby Road)) in Transport for the North’s Regional Evidence Base submission to the Department for Transport.

Reason: To inform Executive about the current status of proposals for dualling sections of the A1237 YORR.

3) Instruct Officers to investigate options for the introduction of further measures across the city to lock in the sustainable transport and environmental benefits which could result from the increased capacity provided by dualling the A1237.

Reason: To ensure that the potential for significant sustainable transport and environmental benefits resulting from the dualling of the ORR are investigated further with options presented to Members for future decision.

4) Recommend to Council to approve a budget of £7.0m for the ‘enhanced option’ upgrading of the A1237/ Clifton Moor junction. This is to be funded from £2m West Yorkshire Transport Fund contribution and £5m prudential borrowing. The revenue costs of which to be incorporated within 2020/21 Revenue Budget.

Reason: To enable the construction of an upgraded junction which will be future proofed to provide access to a proposed new development site shown in the Draft Local Plan for approximately 1350 new homes, new cycle and pedestrian networks and accommodate dualling of the A1237. In addition delivering a single enhanced scheme will minimise traffic disruption and abortive work which would result from delivering the WYTF and development schemes separately.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Clifton Mr 3 arm 2017Appendix A 1 pages Download
PDF
Clifton Mr 4 arm 2019Appendix B 1 pages Download
PDF
CPO Plan 10-09-2019 rev 0Appendix C 1 pages Download
PDF
York Outer Ring Road Improvements UpdateReport 19 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at York

Search all
  1. York Outer Ring Road Improvements UpdateThis decision
  2. Major Projects (Station Gateway and York Outer Ring Road Business Case)Approved
  3. York Outer Ring Road (YORR) - Proposed A1237 (Rawcliffe to Little Hopgrove) Dualling - Update on Progress and Proposed Utility Diversions (6:32 pm)Noted
  4. York Outer Ring Road (YORR) – Phase 1 Dualling – Evaluation of the Consultation Process and Resolution to Submit a Planning ApplicationNoted
  5. York Outer Ring Road Phase 1 Dualling - Resolution in principle to promote a Compulsory Purchase Order and associated Side Roads Order.Noted
  6. York Outer Ring Road Phase 1 Dualling - Procurement Strategy, Approach to Public Engagement and LandscapingApproved

More from York Executive

All decisions
MeetingDecisionOutcome
3 Nov 2026 Minutes (4:46pm)That the Minutes of the Executive meeting held on 6 October 2026 be approved and signed as a correct record. Approved Open
3 Nov 2026 Capital Programme Monitor Update 2 Report (4:47pm)Resolved (unanimously) that Executive: i. In relation to the overall programme: · Recommended to Full Council the adj... Noted Open
3 Nov 2026 Q2 2026-27 Finance and Performance Monitor (4:47pm)Resolved (unanimously) that Executive: i. Noted the finance and performance information. ii. Noted that work will con... Noted Open
3 Nov 2026 Treasury Management Quarter 2 Prudential Indicators (4:47pm)Resolved (unanimously) that Executive: · Noted the 2026/27 Treasury Management activity up to the period ending 30th ... Noted Open
3 Nov 2026 Medium Term Financial Strategy Update (4:47pm)Resolved (unanimously) that Executive: · Agreed the Medium Term Financial Strategy as outlined in this report · In re... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies