York Outer Ring Road Improvements Update

Approved Executive

Executive approved this item on Thursday 26 September 2019. Below is the council's own wording, with the papers it was decided on.

Item50

Resolved

Recommended: That Council approve a budget of £7m for the ‘enhanced option’ upgrading of the Clifton Moor junction, to be funded from £2m West Yorkshire Transport Fund contribution and £5m prudential borrowing, the revenue costs of which will be incorporated in the 2020/21 Revenue Budget. Reason: To enable the construction of an upgraded junction which will be future proofed to provide access to a proposed new development site, shown in the Draft Local Plan, for approximately 1,350 new homes, new cycle and pedestrian networks, and accommodating dualling of the A1237; in addition, delivering a single enhanced scheme will minimise traffic disruption and the abortive work that would result from delivering the WYTF and development schemes separately.
Word for word from the decision York published for this meeting. Source: democracy.york.gov.uk

Follow this further

Built from York's papers

Papers for this item

Kept in our archive, download once signed in

No papers were published with this item. The decision above is the council's full record of it.

At this meeting

Whole meeting

On this subject at York

Search all
  1. York Outer Ring Road Improvements UpdateThis decision
  2. Major Projects (Station Gateway and York Outer Ring Road Business Case)Approved
  3. York Outer Ring Road (YORR) - Proposed A1237 (Rawcliffe to Little Hopgrove) Dualling - Update on Progress and Proposed Utility Diversions (6:32 pm)Noted
  4. York Outer Ring Road (YORR) – Phase 1 Dualling – Evaluation of the Consultation Process and Resolution to Submit a Planning ApplicationNoted
  5. York Outer Ring Road Phase 1 Dualling - Resolution in principle to promote a Compulsory Purchase Order and associated Side Roads Order.Noted
  6. York Outer Ring Road Phase 1 Dualling - Procurement Strategy, Approach to Public Engagement and LandscapingApproved

More from York Executive

All decisions
MeetingDecisionOutcome
3 Nov 2026 Minutes (4:46pm)That the Minutes of the Executive meeting held on 6 October 2026 be approved and signed as a correct record. Approved Open
3 Nov 2026 Capital Programme Monitor Update 2 Report (4:47pm)Resolved (unanimously) that Executive: i. In relation to the overall programme: · Recommended to Full Council the adj... Noted Open
3 Nov 2026 Q2 2026-27 Finance and Performance Monitor (4:47pm)Resolved (unanimously) that Executive: i. Noted the finance and performance information. ii. Noted that work will con... Noted Open
3 Nov 2026 Treasury Management Quarter 2 Prudential Indicators (4:47pm)Resolved (unanimously) that Executive: · Noted the 2026/27 Treasury Management activity up to the period ending 30th ... Noted Open
3 Nov 2026 Medium Term Financial Strategy Update (4:47pm)Resolved (unanimously) that Executive: · Agreed the Medium Term Financial Strategy as outlined in this report · In re... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies