City of York Council

TSAR Traffic Signal Refurbishment – Junction of Malton Road / New Lane

Approved Executive 10 papers

Decision Session - Executive Member for Transport - Expired approved this item on Tuesday 13 December 2022. Below is the council's own wording, with the papers it was decided on.

Item43

Resolved

i. Approved progression of the scheme to detailed design and construction, based on Option C ‘Renewal of Traffic Signal Equipment with additional Toucan Crossing Introduction’. Reason: In order to progress the design and construction of the TSAR scheme at Malton Road / New Lane. i. Approved progression of the scheme to detailed design and construction, based on Option C ‘Renewal of Traffic Signal Equipment with additional Toucan Crossing Introduction’. Reason: In order to progress the design and construction of the TSAR scheme at Malton Road / New Lane.
Word for word from the decision York published for this meeting. Source: democracy.york.gov.uk

Follow this further

Built from York's papers

What the report saysPro

Report to Decision Session - Executive Member for Transport - Expired, 28 pages

Summary

1. The traffic signalling equipment at this site is life expired, has become difficult and costly to maintain and needs to be replaced.

2. The TSAR (Traffic Signal Asset Renewal) programme is the means by which life expired traffic signal assets across the city are refurbished.

3. Although the programme is primarily about asset renewal, there is scope to take advantage of ‘easy wins’ whilst refurbishing the equipment. To that end, design proposals aimed at improvements for pedestrians and cyclists moving through the junction and providing links to existing cycle infrastructure to the northwest of the junction in accordance with the Travel Hierarchy of Transport Users adopted by CYC as part of Local Transport Plan 3 are being put forward.

4. An initial proposed design which included the reallocation of carriageway space on New Lane to provide a mandatory northbound cycle lane to link with an existing on carriageway cycle lane as well as kerbline changes aimed at reducing cyclist/[pedestrian conflict in the North Western corner of the junction was developed and shared for consultation with local ward councillors and external stakeholders representing active travel mode users and equalities groups.

5. Ward councillors responded to indicate that the carriageway changes proposed in this initial design were a cause for concern and did not address local issues which are proposed to be more pressing at the junction. Safety issues for cyclists entering the carriageway of New Lane without traffic signal control whilst motor vehicle traffic also enters the road as part of the proposed layout changes was a key focus, alongside a desire for the introduction of a third signal controlled crossing at the junction providing a more direct route between the Southern foot/cycle way of Malton Road and New Lane.

6. Based on this response, a further three design proposals were compiled which reflected the suggestions proposed during consultation as well as informing slight revisions to the original design proposal to provide light segregation of the new northbound cycle lane and an increase in the size of the foot/cycle way areas around the proposed Toucan crossing waiting areas.

7. The Four Design Proposals include:

 Design Proposal A – Renewal of Traffic Signal Equipment and minor civils works  Design Proposal B – Renewal of Traffic Signal Equipment and reallocation of New Lane Carriageway space to Active Travel Modes  Design Proposal C – Renewal of Traffic Signal Equipment with additional Toucan Crossing Introduction  Design Proposal D – Renewal of Traffic Signal Equipment, Reallocation of New Lane Carriageway space to Active Travel Modes and additional Toucan Crossing Installation

8. A second round of consultation was undertaken on these four design proposals with responses indicating that ward councillors would favour the introduction of Design Proposal C whereas Stakeholders representing Active Travel users would prefer Design Proposal D.

9. A decision is required to approve which of the proposed schemes should be taken forward to detailed design and construction.

Recommendations

10. The Executive Member is asked to:

Approve progression of the scheme to detailed design and construction, based on one of the scheme proposals described within this report.

Reason:

In order to progress the design and construction of the TSAR scheme at Malton Road / New Lane. Background

11. The TSAR (Traffic Signal Asset Renewal) programme has been in place since 2015 and is responsible for the replacement of life expired traffic signal assets around York.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
CYC_TST-YK2237-P-000 (P01) DESIGN PROPOSAL AAppendix A 1 pages Download
PDF
CYC_TST-YK2237-P-001 (P01) DESIGN PROPOSAL BAppendix B 1 pages Download
PDF
CYC_TST-YK2237-P-002 (P01) DESIGN PROPOSAL CAppendix C 1 pages Download
PDF
CYC_TST-YK2237-P-003 (P01): DESIGN PROPOSAL DAppendix D 1 pages Download
PDF
Consultation TSAR YK2237 Compiled FinalAppendix E 13 pages Download
PDF
TSAR Malton Road New Lane EIA FinalAppendix F 16 pages Download
PDF
TSAR Traffic Signal Refurbishment: Junction of Malton Road / New LaneReport 28 pages DownloadRead as text
PDF
View as HTML (43./6) 76 KBAppendix 76 KB Copy on its way
PDF
View as HTML (43./7) 104 KBAppendix 104 KB Copy on its way
PDF
View item 43. as HTML 187 KBReport 187 KB Copy on its way

At this meeting

Whole meeting

On this subject at York

Search all
  1. TSAR Traffic Signal Refurbishment – Junction of Malton Road / New LaneThis decision
  2. TSAR Traffic Signal Refurbishment – Barbican Road/Paragon StreetApproved
  3. TSAR Traffic Signal Refurbishment - Clifton Moorgate / Hurricane Way YK2239Approved
  4. TSAR Traffic Signal Refurbishment - Clifton Moorgate / Hurricane Way YK2239Deferred
  5. TSAR Traffic Signal Refurbishment - Wigginton Road / Crichton Avenue YK2221Approved
  6. TSAR Traffic Signal Refurbishment - Hull Road/Osbaldwick Link RoadApproved

More from York Decision Session - Executive Member for Transport - Expired

All decisions
MeetingDecisionOutcome
21 Mar 2023 Acomb Road Safety Updatei. That the council promote and relaunch the existing campaign to recruit a school crossing patroller on Acomb Road; ... Noted Open
21 Mar 2023 Active Travel Programme Updatei. Noted the update on the progress of the Active Travel Programme contained within this report; Reason: To provide i... Noted Open
21 Mar 2023 Active Travel Programme – Hospital Fields Road Schemei. Approved the advertisement of amendments to the Traffic Regulation Order (TRO) to implement the parking restrictio... Approved Open
21 Mar 2023 Resident Parking (Recommendations from Scrutiny)i. Noted the response to the scrutiny recommendations detailed within paragraph 25 of this report; ii. Noted that the... Noted Open
14 Mar 2023 Exclusion of Press and PublicThat the press and public be excluded from the meeting during the consideration of annexes D and E for Agenda Items 5... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies