Resolved
Decision The Environment, Development and Infrastructure Committee noted the update provided in the report. (Reference: Report by Executive Director with responsibility for Roads and Infrastructure dated 10 September 2020, submitted)
Environment, Development and Infrastructure Committee noted this item on Thursday 10 September 2020. Below is the council's own wording, with the papers it was decided on.
Resolved
Decision The Environment, Development and Infrastructure Committee noted the update provided in the report. (Reference: Report by Executive Director with responsibility for Roads and Infrastructure dated 10 September 2020, submitted)
1.1In March 2020 the Environment, Development and Infrastructure (EDI) Committee endorsed the programme of capital works for roads reconstruction and footway schemes for 2020/21.
1.2This report provides an update of the Roads and Infrastructure Services operational capital and revenue matters relating to roads activities throughout the Council area.
1.3It is recommended that Members consider the update provided in the report.
1 ARGYLL AND BUTE COUNCIL ENVIRONMENT, DEVELOPMENT AND INFRASTRUCTURE COMMITTEE
ROADS AND INFRASTRUCTURE SERVICES 10 SEPTEMBER 2020
UPDATE ON ROADS CAPITAL RECONSTRUCTION PROGRAMME 2020/21
2.0INTRODUCTION
2.1In March 2020 the Environment, Development and Infrastructure (EDI) Committee endorsed the programme of capital works for roads reconstruction and footway schemes for 2020/21.
2.2This report provides an update of the Roads and Infrastructure Services operational capital and revenue matters relating to roads activities throughout the Council area.
3.1It is recommended that Members consider the update provided in the report.
4.0DETAILS
4.1The focus of the roads reconstruction programme has been to recover the network through the delivery of a mix of carriageway resurfacing schemes, patching/surface dressing and in-situ road surface recycling, which follow the principles set out within the Roads Asset Management Plan. 4.2 However, due to the Covid-19 pandemic much of the cyclic and ‘normal’ works carried out by our teams for the first months of this financial year has been reprioritised following Scotland entering lockdown on 23rd March 2020. 4.3 As we entered lockdown, service delivery was reprioritised to ensure that our teams could safely deliver a reduced set of services. These services included: amended refuse collection routes, provision of burial and cremation services, continued inspection of key infrastructure with appropriate repairs, a reduced ferry service etc. Non-essential works were stopped in line with government guidance.
4.4The 2020/21 Capital Programme was restarted in the latter part of July and has been revised with a number of preparatory schemes being carried out which will enable surface dressing to be applied in 2021. This in effect moves us to a two year capital investment programme due to delay in commencing the programme due to Covid restrictions. The total value of works which have been put back to financial year 2021/22 is £2.194M.
4.5The annual Capital programme of work for Roads due to COVID-19 was postponed however as of 20 July 2020 and in line with Scottish Government phased route plan and 2 the Scottish Road Works Commissionaire guidance we began Capital Works week commencing 20 July 2020. The capital programme has been modified by moving the surface dressing works into next financial year and focusing on a reduced resurfacing programme which includes a mix of traditional resurfacing, surface dressing preparatory works and insitu recycling. Surface dressing is not being delivered this year as there would have been insufficient time for the stone chips to adequately embed into the receiving road surface. The embedment of surface dressing chips requires the warmer summer temperatures which soften the underlying road material allowing the chips to become bedded in with the action of passing traffic.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Updated Roads Reconstruction Programme per areaAppendix 1 | 173 KB | Download |
PDF |
UPDATE ON ROADS CAPITAL RECONSTRUCTION PROGRAMME 2020/21Report | 129 KB | DownloadRead as text |
Follow Environment, Development and Infrastructure Committee at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 9 Oct 2026 | A816 bealach mor permanent solution updateDecision The Environment, Development and Infrastructure Committee noted the following key points – 1. the £1.1m appr... | Noted | Open |
| 9 Oct 2026 | Review of public convenience estateDecision The Environment, Development and Infrastructure Committee – 1. noted the findings of the updated baseline re... | Noted | Open |
| 9 Oct 2026 | Review of roads and infrastructure services updateDecision The Environment, Development and Infrastructure Committee – 1. noted the progress to date on the RIS Review;... | Noted | Open |
| 9 Oct 2026 | Winter service policy 2026/27Decision The Environment, Development and Infrastructure Committee – 1. approved the 2026/27 Winter Maintenance Polic... | Approved | Open |
| 9 Oct 2026 | Waste management updateDecision The Environment, Development and Infrastructure Committee noted the content of the report. (Reference: Repor... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.