CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Argyll and Bute Council

ARGYLL AND BUTE CONNECTIVITY REPORT 2026

Noted Committee 1 paper

AI summaryArgyll and Bute councillors note digital connectivity report: £157m Project Gigabit funding covers the area, with around 90% fibre availability expected once rollouts combine.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedCommittee received the connectivity update report
Money£157mProject Gigabit value for Rest of Scotland/Highlands and Islands
What happens nextJanuary 2027PSTN analogue to digital switchover deadline
Who it affectsArgyll and Bute residents and businessesFixed broadband, mobile and landline users across the area

What was decided

The Environment, Development and Infrastructure Committee noted the connectivity report submitted by the Executive Director with responsibility for Development and Economic Growth. Report 2.1

Members were updated that digital infrastructure roll-out continues through R100, Project Gigabit and commercial investment, primarily by BT Openreach. Report 3.1, 3.2, 3.3

The Committee was advised that once funded programmes and commercial build are combined, fibre availability across the area is expected to be around 90%. Report 3.4, P8

Why

Modern digital infrastructure is described as critical for the area's economy and for attracting and retaining population. Report 3.1, 5.1

Delivery has not been as fast as the Council would like, given the area's geography and sparse population, and the area continues to lag behind other parts of the UK. Report 3.2

Mobile signal mapping using refuse vehicles found that Argyll and Bute has the worst geographic mobile coverage in the UK. Report 3.14, 3.15, 3.16

What happens next

Council officers will continue to press BT Openreach and both Governments for assurance that telecare, landline and emergency communications will be maintained during power cuts after the 2027 switchover. Report 3.13, 3.10, 3.11

Mobile coverage data gathered from refuse vehicles will be used to lobby Government and mobile operators for further investment. Report 3.16

The Council is looking to install Starlink as a resilience measure and is tracking Direct-to-Device satellite technology as a possible solution for rural connectivity gaps. Report 3.9

The money

  • £157m Project Gigabit contract value for the Rest of Scotland/Highlands and Islands area covering Argyll and Bute Report 3.3

Options considered

  • Rejected: Install a Battery Backup Unit (BBU) to power the broadband router and Optical Network Terminal during a power cut. Listed as one of two practical mitigations discussed for full fibre premises after the PSTN switchover, not a formal committee option Report 3.11
  • Rejected: Use a hybrid phone with inbuilt battery and mobile SIM to maintain service during a power cut. Second mitigation discussed in the report for premises that lose power after the analogue to digital switchover Report 3.11

Implications

  • Financial: No financial implications arise directly from this report. Report 5.2
  • Legal: No legal implications arise from this report. Report 5.3
  • Risk: Reliance on new technology, commercial operator decisions and grant funding creates uncertainty over the extent of infrastructure improvements. Report 5.6
  • Equalities: Uneven roll-out of new technology could create inequalities in access to digital services supporting business and personal development. Report 5.9
  • Other: Fairer Scotland Duty: fixed and mobile coverage across Argyll and Bute should be equitable with the rest of Scotland. Report 5.8
  • Other: Island Communities: areas without digital infrastructure may become less attractive places to live and work, affecting population growth aims. Report 5.11
  • Climate: Better online access can reduce the need to travel, lowering individual carbon footprints. Report 5.7
  • Staffing: Improved connectivity will benefit council staff delivering services in remote communities in terms of accessibility and safety. Report 5.4

Who and where

  • Residents and businesses across Argyll and Bute using fixed broadband, mobile and landline services Report 3.1, P46
  • Households and businesses in the ten exchange areas being worked on by Openreach in 2026, including Lochgilphead, Kilcreggan, Campbeltown, Carradale, Dunoon, Glenbarr, Kilkenzie, Kilchrenan, Taynuilt and Arden Report 3.4, P7
  • Premises in 20 exchange areas scheduled for Openreach funded build in 2027, including Rothesay, Inverary, Arrochar, Bowmore, Port Ellen, Toward and others Report 3.5, P11
  • Users of telecare, intruder alarms and other devices connected to existing phone sockets, who must check compatibility with the new digital service Report P50, P57
  • Mobile users across the council's four administrative areas, where coverage is described as the worst geographic mobile coverage in the UK Report 3.15, 3.16

Timeline

  • Financial year end 2025/26: Full fibre footprint figures reported by exchange across Argyll and Bute, ranging from 0% to 100% Report 3.6, P14
  • 2026: Openreach working on funded build in ten named exchange areas Report 3.4, P7
  • 2027: Openreach contracted funded build planned in a further 20 exchange areas Report 3.5, P11
  • January 2027: Final deadline for the UK-wide switchover from the analogue Public Switched Telephone Network to digital services Report 3.10, P46

Plain English for the jargon

  • R100: Scottish Government programme to deliver superfast broadband to 100% of premises in Scotland.
  • Project Gigabit: UK Government programme to deliver gigabit-capable broadband to premises not covered by commercial roll-out.
  • PSTN: Public Switched Telephone Network, the analogue copper landline system being switched off by January 2027.
  • LEO satellite: Low Earth Orbit satellite, used by services such as Starlink to provide broadband.
  • D2D: Direct to Device, technology letting ordinary smartphones connect to LEO satellites when terrestrial mobile signal fails.
  • BBU: Battery Backup Unit that can power a fibre router and Optical Network Terminal for a limited time during a power cut.
  • ONT: Optical Network Terminal, the box at a premises that ends a full fibre connection.
  • ISP: Internet Service Provider.
  • MNO: Mobile Network Operator.
  • SOA: Single Outcome Agreement, the Council's main strategic planning document.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item12

Resolved

Decision The Environment, Development and Infrastructure Committee noted the report. (Reference: Report by Executive Director with responsibility for Development and Economic Growth, dated 8 May 2026, submitted)
Word for word from the decision Argyll and Bute published for this meeting. Source: www.argyll-bute.gov.uk

Follow this further

Built from Argyll and Bute's papers

What the report saysPro

Report to Environment, Development and Infrastructure Committee

Recommendations

2.1It is recommended that the Environment, Development and Infrastructure Committee consider this report. 3.0 DETAIL & BACKGROUND

3.1The roll out of digital infrastructure continues across Argyll and Bute delivered primarily through the Government subsidised schemes of R100 and Project Gigabit together with commercial investment from BT Openreach and other commercial companies such as Virgin. As members are aware the availability of modern fit for purpose digital infrastructure is critical for the future of our economy and to help attract and retain our population.

3.2Delivery of both the Government programmes by BT Openreach and their sub- contractors is continuing but not at the pace we would like to see given the geography of our area and the complexity of delivery. That said, communities continue to be connected. Current progress can be found through the following link. Faster broadband in Scotland

3.3Both the UK and Scottish Governments are working very closely with Openreach to maximise Value for Money (VfM) between R100 and Project Gigabit classifying them as Funded Programmes and Commercial Build. R100 was initially due to be completed by 2021/22 but this was seen quickly as being unrealistic and so it has proved to be. Project Gigabit has been added since and Argyll and Bute is now included in in the Rest of Scotland/Highlands and islands area with a value of £157m.

3.4Openreach are currently working on the following exchange areas across Argyll and Bute included in Table 1:

Table 1 Source - 2026 Openreach Exchange Upgrades

Exchange Lochgilphead Kilcreggan Campbeltown Carradale Dunoon Glenbarr Kilkenzie Kilchrenan Taynuilt Arden

It is anticipated that availability will be around 90% once each funded programme and commercial build are combined

3.5Moving forward into 2027, Openreach have contracted funded build in the following exchange areas:

Table 2 Source - 2027 Openreach Planned Exchange Upgrades

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
ARGYLL AND BUTE CONNECTIVITY REPORT 2026Report 296 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

13 of 20 attended
IP
Councillor Iain PatersonMember, apologies
JS
Julieann SmallSecretary, expected
KM
Katie McKenzieSecretary, expected
HM
Hazel MacInnesSecretary, expected
FM
Fiona McCallumSecretary, expected
JA
Councillor John ArmourChair, present
GH
Councillor Graham HardieMember, present
WH
Councillor Willie HumeMember, present
AK
Councillor Andrew KainMember, present
JL
Councillor Jim LynchMember, present
TM
Councillor Tommy MacPhersonMember, apologies
IM
Councillor Ian MacQuireMember, present

All 20 on the meeting page

On this subject at Argyll and Bute

Search all
  1. ARGYLL AND BUTE CONNECTIVITY REPORT 2026This decision
  2. Argyll and bute outcomes and improvement plan - priorities updateNoted
  3. Argyll and Bute Climate Action NetworkNoted
  4. Argyll and bute improvement plan - priorities updateNoted
  5. Argyll and bute improvement plan - priorities updateNoted
  6. Argyll and bute harbour board workplanNoted

More from Argyll and Bute Environment, Development and Infrastructure Committee

All decisions
MeetingDecisionOutcome
9 Oct 2026 A816 bealach mor permanent solution updateDecision The Environment, Development and Infrastructure Committee noted the following key points – 1. the £1.1m appr... Noted Open
9 Oct 2026 Review of public convenience estateDecision The Environment, Development and Infrastructure Committee – 1. noted the findings of the updated baseline re... Noted Open
9 Oct 2026 Review of roads and infrastructure services updateDecision The Environment, Development and Infrastructure Committee – 1. noted the progress to date on the RIS Review;... Noted Open
9 Oct 2026 Winter service policy 2026/27Decision The Environment, Development and Infrastructure Committee – 1. approved the 2026/27 Winter Maintenance Polic... Approved Open
9 Oct 2026 Waste management updateDecision The Environment, Development and Infrastructure Committee noted the content of the report. (Reference: Repor... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies