Cabinet: Approved the delivery of Enabling Works and Main Works packages to be undertaken by Vinci Construction UK Ltd. Agreed the interim tender report recommendation that Vinci Construction UK Ltd undertake the Enabling Works and Main Works packages at the provisional contract sum set out in Part B of this report, and delegate final acceptance of a final contract sum up to a provisional maximum of £25,088,003.87 to the Director of Law and Democratic Services in consultation with the Executive Director of Place and Director of Finance and the Council Leader and Cabinet Member for Strategic Growth. Agreed to delegate finalisation and sealing of the Enabling Works and Main Works Contract including any clarifications to the Director of Law and Democratic Services in consultation with the Executive Director of Place and the Council Leader and Cabinet Member for Strategic Growth. Reasons for recommendation(s): Approval of the Enabling Works package is required for the Bury Market & Flexi Hall project to deliver various preparatory works on site. These works are required to be completed in advance, to ensure the Main Works construction phase can start on time in line with the agreed project programme, associated scheme cash flow and DLUHC Levelling Up grant spend deadline. Approval also extends to the Main Works package for the Bury Market & Flexi Hall project to progress to a construction phase without delay and to avoid jeopardising development delivery and grant funding expenditure obligations. Key considerations within this document have informed the Enabling Works and Main Works contract sum, the scope and methodology for carrying out the associated Enabling Works and Main Works packages and their phasing in line with the agreed project programme and grant funding agreement. Alternative options considered and rejected: ... view the full minutes text for item CA.188
Word for word from the decision Bury published for this meeting.Source: councildecisions.bury.gov.uk
Report to: Cabinet Date: 10 July 2024 Bury Market & Flexi Hall – Enabling Works & Main Works tendered Subject: cost / approval to progress Enabling Works & Main Works packages (Part A) Report of Leader and Cabinet Member for Strategic Growth
Summary 1.1 The purpose of this report is to advise Cabinet of the Enabling Works and Main Works packages, that in line with the Bury Market & Flexi Hall project programme, will now need to be instructed through the Enabling Works and Main Works Contract. The project documents and programme milestones that inform and outline these Enabling and Main Works packages, and the associated interim tender price report, are appended to Part B of this paper.
1.2The contract encompasses an initial period of Enabling Works because these advanced, preparatory works are required to be undertaken in sufficient time to ensure the construction site is ready for development delivery (which is the Main Works package). The initial period of Enabling Works will commence during August 2024 and continue until May 2025, and in doing so will overlap with the start of the Main Works package that is due to commence on site during October 2024. This sequential programming of Enabling Works and Main Works packages maximises cost and time programme efficiencies, whilst allowing the Council and Vinci Construction UK Ltd to smoothly transition from the current Pre-Construction Service Agreement (PCSA) in line with the agreed project programme. The Enabling and Main Works packages are outlined in the project programme and the interim tender price report which are appended to Part B of this paper.
1.3The works packages included within the proposed Enabling Works and Main Works Contract, have been market tested and independently verified, and the interim tender report is appended to Part B of this paper.
1.4The Enabling Works and Main Works packages also align with the cashflow spending commitments outlined in the agreed Levelling Up Fund Memorandum of Understanding (MOU), and ensure the project is complaint with the stipulation that all grant monies awarded from the fund are fully defrayed by March 2026, which is the proposed, revised spend deadline.
1.5Since confirmation of the Levelling Up funding award in October 2021, the project has been subject to a quarterly reporting cycle to the Department of Levelling Up, Housing & Communities (DLUHC). The scheme’s cashflow
1 forecast, delivery programme and risk management plan outlined in these returns have consistently reflected a Main Works construction programme which is phased to facilitate an initial series of advanced, preparatory works (the Enabling Works package).
Recommendation(s) 2.1 It is recommended that Cabinet: Approve the delivery of Enabling Works and Main Works packages to be undertaken by Vinci Construction UK Ltd. Accept the interim tender report recommendation that Vinci Construction UK Ltd undertake the Enabling Works and Main Works packages at the provisional contract sum set out in Part B of this report, and delegate final acceptance of a final contract sum up to a provisional maximum of £25,088,003.87 to the Director of Law and Democratic Services in consultation with the Executive Director of Place and Director of Finance and the Council Leader and Cabinet Member for Strategic Growth. Delegate finalisation and sealing of the Enabling Works and Main Works Contract including any clarifications to the Director of Law and Democratic Services in consultation with the Executive Director of Place and the Council Leader and Cabinet Member for Strategic Growth.
Reasons for recommendation(s)
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.