Cabinet: Approved the funding of capital costs as set out in Part B of this report, Agreed that the cost of the CYCLOPS junction and active travel elements cab be met from the Council’s Capital Programme Reasons for recommendation(s): To enable confirmation of the Council’s commitment to meet its financial obligations enabling the scheme to construct the new school to progress. Alternative options considered and rejected: Confirmation of the Council’s commitment to meet its financial obligations are essential to enable delivery of the project to construct the new school.
Word for word from the decision Bury published for this meeting.Source: councildecisions.bury.gov.uk
1.1On the 15th March 2023 (CA.147) Cabinet approved the funding of indicative costs to meet the Council’s financial obligations in relation to delivery by the Department for Education (DfE) of the project to construct the new secondary school in Radcliffe.
1.2The DfE has now received confirmed contract costs for the project, including the access road and junction works, the costs of which fall to the Council.
1.3Cabinet is requested to approve revised funding arrangements in respect of its financial obligations.
2.0Recommendation(s)
That Cabinet:
Approve the funding of capital costs as set out in Part B of this report,
Agree that the cost of the CYCLOPS junction and active travel elements met from the Council’s Capital Programme
Reasons for recommendation(s) To enable confirmation of the Council’s commitment to meet its financial obligations enabling the scheme to construct the new school to progress.
Alternative options considered and rejected
Confirmation of the Council’s commitment to meet its financial obligations are essential to enable delivery of the project to construct the new school. _________________________________________________________ Report Author and Contact Details:
Name: Paul Cooke Position: Strategic Lead (Education) Department: Children’s Services E-mail: [email protected]
3.1Cabinet has received several reports in recent years in respect of the process and arrangements that will lead to the establishment of the new secondary school in Radcliffe (Star Academy).
3.1On the 15th March 2023 (CA.147) Cabinet approved the funding of indicative costs to meet the Council’s financial obligations in relation to delivery of the project, to be met from the Children’s Services schools capital programme; capital receipts/borrowing; and the Greater Manchester City Region Sustainable Transport Settlement.
3.2These financial obligations relate to the construction of a new access road; construction of the related junction from the access road to Spring Lane (CYCLOPS); Site clearance & construction of all-weather pitch; and a contribution to the cost of provision of modular accommodation.
3.3The report set out any conditions relating to each item, and the manner in which they would be funded.
3.4The construction of the new access road to be funded from the Children’s Services capital programme; the construction of the CYCLOPS junction and active travel elements to be funded from the GM City Region Sustainable Transport Settlement; the contribution towards the modular accommodation to be funded from capital receipts or borrowing but at a capped cost; and the site clearance and construction of all-weather pitch to be funded from the Children’s Services capital programme, but only in the event that the Council failed to provide the DfE with vacant possession of the Spring Lane site by 1st March 2024.
3.5Indicative costs for each item were set out in the report, with the exception of the CYCLOPS junction, with details to be confirmed.
3.6Vacant possession of the Spring Lane site was achieved by the 1 st March 2024 and so the costs relating to that item will no longer fall to the Council.
3.7In respect of modular accommodation, whilst the costs in relation to the provision of this has increased significantly, the Council’s capital costs were capped at the outset, and there is no additional impact on the Council. The modular accommodation has been procured by the DfE with the units being delivered to site from late June, ready for occupation in September 2024. 3.8 The DFE has now received confirmed contract costs for delivery of the substantive project to construct the permanent school building and associated infra-structure.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.