Bury Metropolitan Borough Council
Cabinet, Tuesday 16 July 2024 at 5.00pm

Proposed Major Works Programme for the Councils housing stock 2024/25

Approved Executive 1 paper

Cabinet approved this item on Tuesday 16 July 2024. Below is the council's own wording, with the papers it was decided on.

ItemCA.190

Resolved

Cabinet: Acknowledged the proposed Capital Programme to be funded within the HRA, estimated at £19,841,760 and recommends to Council that it be approved. Subject to Council approval, authorised external competitive procurement to be commenced in respect of the respective schemes identified within the Capital Programme on a compliant basis in accordance with the Public Contracts Regulations 2015 and the Council’s Contract Procedure Rules 2022. Requested reports back on the individual schemes with recommendations as to contract awards at the conclusion of the respective procurement processes. Noted that whilst the target completion date for the respective contract works is the end of the current financial year, the duration of some contracts and the associated expenditure will run into 2025/26 and that further updates will be provided to Cabinet as part of the Budget reporting process. Approved payments to Green Grants Install Limited for decarbonisation works under the Social Housing Decarbonisation Fund (SHDF) Wave 1 and 2 programmes grant funded by the GMCA and delegates to the Director of Law and Governance authority to facilitate the necessary contractual arrangements. Reasons for recommendations: To enable work to the Council’s housing stock to be undertaken. A requirement of the Regulator of Social Housing is to have “accurate, up to date and evidenced understanding of the condition of homes that reliably informs their provision of good quality, well maintained and safe homes for tenants.”. The 2024/25 programme of work has been developed to address this need. Alternative options considered and rejected: This is an asset led programme, undertaking work where it is needed and not geographically based. The focus for the 2024/25 is on dealing with long standing issues, delayed projects, and backlogs to ensure compliance with regulatory standards. To ensure an improved approach to longer term planning from 2025/26 onwards, including the introduction of a cyclical painting and repairs programme, a full stock condition survey is currently being completed.
Word for word from the decision Bury published for this meeting. Source: councildecisions.bury.gov.uk

Follow this further

Built from Bury's papers

What the report saysPro

Report to Cabinet

Summary

1.1In February 2024 the Council took back direct management of its housing stock with the transfer of Six Town Housing’s principal responsibilities to it. A review of the capital works programme has been quickly undertaken to ensure compliance with regulatory standards and in recognition of the backlog of work that has been identified during the transfer process.

1.2The 2024/25 housing major works budget was approved during the Annual Budget Setting at February Council in the sum of £23.1m. This report sets out a proposed major works programme with an estimated cost of £19.8m, to be funded through the Housing Review Account (HRA).

1.3The proposed work will improve homes, increase energy efficiency and through the replacement of key components reduce the need for routine repairs. It supports meeting the decent homes standard and reducing associated risks with elemental failures e.g. water ingress, damp and trip hazards.

1.4As noted in previous update reports to Cabinet, in recent years environmental work has been lacking and tenants have expressed dissatisfaction with communal outdoor spaces and boundary treatments. This programme makes provision for environmental work which will be shaped by tenants in their neighbourhoods. The proposed programme also addresses the backlog of adaptations for tenants.

1.5Developing the 2024/25 programme has been delayed because of the transfer from Six Town Housing (STH). This report asks for Cabinet to recommend that the revised scheme is approved by Council, to be procured and delivered through Council processes, as per the Constitution.

1.6While the ongoing survey of all the Councils housing stock will inform future budgets, the 2024/25 programme is based on verified information from the previous surveys undertaken by STH and feedback from tenant engagement.

1.7With regards to the delivery of this Capital Programme, the involvement of tenants in the specification and contractor selection will be developed as part of the Council's broader approach to Tenant Engagement and Involvement.

Recommendations

1 2.1 That Cabinet:

a. Acknowledges the proposed Capital Programme to be funded within the HRA, estimated at £19,841,760 and recommends to Council that it be approved.

b. Subject to Council approval, authorises external competitive procurement to be commenced in respect of the respective schemes identified within the Capital Programme on a compliant basis in accordance with the Public Contracts Regulations 2015 and the Council’s Contract Procedure Rules 2022.

c. Requests reports back on the individual schemes with recommendations as to contract awards at the conclusion of the respective procurement processes.

d. Notes that whilst the target completion date for the respective contract works is the end of the current financial year, the duration of some contracts and the associated expenditure will run into 2025/26 and that further updates will be provided to Cabinet as part of the Budget reporting process.

e. Approves payments to Green Grants Install Limited for decarbonisation works under the Social Housing Decarbonisation Fund (SHDF) Wave 1 and 2 programmes grant funded by the GMCA and delegates to the Director of Law and Governance authority to facilitate the necessary contractual arrangements.

Reasons for recommendations

3.1To enable work to the Council’s housing stock to be undertaken.

3.2A requirement of the Regulator of Social Housing is to have “accurate, up to date and evidenced understanding of the condition of homes that reliably informs their provision of good quality, well maintained and safe homes for tenants.”. The 2024/25 programme of work has been developed to address this need.

4. Alternative options considered and rejected

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Proposed Major Works Programme for the Councils housing stock 2024/25Decisions 339 KB DownloadRead as text

At this meeting

Whole meeting
CA.186MinutesOn the agenda CA.187Prestwich funding - Part ANoted CA.188Bury Market & Flexi Hall Levelling Up scheme – enabling and main works contract - Part AApproved CA.189Buy Back & Acquisitions Policy & Procedures 2024 - 2028Agreed
CA.190Proposed Major Works Programme for the Councils housing stock 2024/25This decision
CA.191PRU Phase 2 Whitefield Centre - Part AApproved CA.192Objections to the proposed disposal of Public Open Space - Land off Manchester Road/Radcliffe Road, BuryAgreed CA.193Six Town Housing Board GovernanceApproved CA.194The Acceptance of the Lowest Tender for the Replacement of Existing Street Lighting Lanterns with LED Lanterns (Phase 3) - Part AApproved CA.195Top Park, Ramsbottom 3G football pitchApproved CA.196Year End/Quarter Four Corporate Plan Performance Report 2023/24 and submission of the productivity planNoted CA.197Star Academy Radcliffe – Capital costs - Part AApproved CA.198Budget Update ReportNoted CA.199Radcliffe School FundingRefused CA.200Implementation of the Children's Services leadership restructureNoted CA.201Exclusion of Press and PublicDecided CA.202The Acceptance of the Lowest Tender for the Replacement of Existing Street Lighting Lanterns with LED Lanterns (Phase 3) - Part BPrivate CA.203Bury Market & Flexi Hall Levelling Up scheme – enabling and main works contract - Part BPrivate CA.204PRU Phase 2 Whitefield Centre - Part BPrivate CA.205Star Academy Radcliffe – Capital costs - Part BPrivate CA.206Prestwich funding - Part BPrivate

Who was there

15 of 20 attended
EO
Councillor Eamonn O'BrienChair, present
CC
Councillor Clare CumminsCommittee Member, present
CM
Councillor Charlotte MorrisCommittee Member, apologies
AQ
Councillor Alan QuinnCommittee Member, present
TR
Councillor Tahir RafiqCommittee Member, present
LS
Councillor Lucy SmithCommittee Member, present
TT
Councillor Tamoor TariqCommittee Member, present
ST
Councillor Sean ThorpeCommittee Member, present
SW
Councillor Sandra WalmsleyCommittee Member, present
LR
Lynne RidsdaleOfficer, present
JD
Jacqui DennisOfficer, present
PM
Paul McKevittOfficer, expected

All 20 on the meeting page

More from Bury Cabinet

All decisions
MeetingDecisionOutcome
14 Oct 2026 Review and amendments to Bury Council's Housing Allocations PolicyDecision(s) Cabinet: · Approved the amendments to the Allocations policy. Reasons for decision(s) · The council has p... Approved Open
14 Oct 2026 Northern Gateway Western Access scheme: Stage 3 Contract Sum, External Professional Team Contract Extension, and Acceptance of Investment Zone Grant Funding.Decision(s) Cabinet: a. Delegated final acceptance of Balfour Beatty Civil Engineering Ltd Stage 3 contract sum, up t... Approved Open
14 Oct 2026 New Persona Shareholder Agreement - PART ADecision(s) Cabinet · Approved to adopt the new Persona Shareholder Agreement Reasons for decision(s) · To explore th... Approved Open
14 Oct 2026 Extension of Lease for St Monica's - Part ADecision(s) Cabinet: a. Approved the current heads of terms for the grant of the new lease and associated indemnity a... Approved Open
14 Oct 2026 Proposed creation of an End-to-End Greater Manchester Fostering HubDecision(s) Cabinet: · Endorsed the proposal for the transition from the current Greater Manchester Fostering Recruit... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies