Cabinet: Approved the award of a contract to E.ON Energy Solutions Ltd in the sum set out in Part B of this Report. Agreed to delegate authority to the Executive Director of Operations in consultation with the Director of Law and Governance to negotiate and execute the contract Reasons for recommendation(s): A mini competition was undertaken, via The Chest, in accordance with the terms of the GMCA Street Lighting Electrical Connections Framework. The Framework includes the provision of electrical connections to street lights (and other associated highway furniture) such as new connections, disconnections and transfers. The Framework is a compliant procurement process under the Public Contracts Regulations 2015. Four eligible companies were invited to participate and E.ON submitted the most competitive price Alternative options considered and rejected: The inhouse were considered. However, they do not have the capacity to carry out this work on top of their day-to-day commitments. There is the option to do nothing. However, this will not replace old, and expensive to operate/maintain, street lighting lanterns and achieve the energy savings required.
Word for word from the decision Bury published for this meeting.Source: councildecisions.bury.gov.uk
1. The purpose of this report is to request Cabinet approval to accept the lowest tender submitted for the Replacement of Existing Street Lighting Lanterns with LED Lanterns (Phase 3) by E.ON Energy Solutions Ltd. Recommendation(s)
2. To approve the award of a contract to E.ON Energy Solutions Ltd in the sum set out in Part B of this Report.
3. To delegate authority to the Executive Director of Operations in consultation with the Director of Law and Governance to negotiate and execute the contract. Reasons for recommendation(s)
4. A mini competition was undertaken, via The Chest, in accordance with the terms of the GMCA Street Lighting Electrical Connections Framework. The Framework includes the provision of electrical connections to street lights (and other associated highway furniture) such as new connections, disconnections and transfers. The Framework is a compliant procurement process under the Public Contracts Regulations 2015.
5. Four eligible companies were invited to participate and E.ON submitted the most competitive price.
Alternative options considered and rejected
6. The inhouse were considered. However, they do not have the capacity to carry out this work on top of their day-to-day commitments.
7. There is the option to do nothing. However, this will not replace old, and expensive to operate/maintain, street lighting lanterns and achieve the energy savings required. _________________________________________________________ Report Author and Contact Details: Name: Philip Hewitt Position: Group Engineer (Street Lighting & Operations) Department: Operations E-mail: [email protected] ________________________________________________________________ Background 8. A mini competition was undertaken, via The Chest, as part of the GMCA Connections Framework for which four eligible companies were invited to participate.
This was to engage a suitable contractor to carry out the replacement of existing street lighting lanterns with Led lanterns for the already approved £1,460,000 capital programme.
The contract was run on a 60% quality 40% price basis with the results as follows:-
Weighted Price Weighted Name Total Score Score Quality Score EoN 40.00 52.00 92.00 J. McCann 36.13 47.00 83.13
Altitude Services 39.30 41.00 80.30
Jones Lighting 37.11 42.00 79.11
The programme, known as Phase 3, is to swap around 3,000 old street lighting lanterns for LED on 8m columns and above, staring with the classified roads within the Borough.
Estimated time for completion is December 2025, but we are hopeful we may be able to complete the works before this time. _________________________________________________________ Links with the Corporate Priorities: Please summarise how this links to the Let’s Do It Strategy.
9. _________________________________________________________ Equality Impact and Considerations: Please provide an explanation of the outcome(s) of an initial or full EIA and make specific reference regarding the protected characteristic of Looked After Children. Intranet link to EIA documents is here.
10. Not applicable as this report is to award the contract for an already approved capital programme.
Environmental Impact and Considerations: Please provide an explanation of the Environmental impact of this decision. Please include the impact on both Carbon emissions (contact [email protected] for advice) and Biodiversity (contact [email protected] for advice)
11. Not applicable as this report is to award the contract for an already approved capital programme.
Assessment and Mitigation of Risk: Risk / opportunity Mitigation
_________________________________________________________ Legal Implications: To be completed by the Council’s Monitoring Officer.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.