Prestwich Regeneration

Agreed Executive 1 paper

Cabinet agreed this item on Wednesday 4 December 2024. Below is the council's own wording, with the papers it was decided on.

ItemCA.273

Resolved

Cabinet: Agree consent for the Council (as 50% of the JV [LLP]) to provide approval to the JV [LLP] to appoint and enter into a building contract with VINCI as the main contractor to deliver Phase 1A (Travel Hub). Accepted the tender report recommendation that VINCI undertake the main works at a sum contained within Part B, subject to the agreement of any contract amendments and clarifications, and within the previously approved cost envelope Delegated authority to the Director of Law and Democratic Services in consultation with the Executive Director of Place to finalise and execute the building contract (noting that approval to be able to negotiate and complete detailed legal and procurement agreements associated with the delivery of the Scheme was given on 16th July 2024), consultant appointments, warranties and any other related ancillary agreements. Delegate authority to the Director of Law and Democratic Services in consultation with the Executive Director of Place to execute the Pagabo Client Access Agreement on behalf of the Council as a Member of the JV [LLP]. Reasons for recommendation(s) The use of Pagabo alongside objective criteria assessment is a PCR compliant procurement route which gives the ability to award the contract under this framework to deliver the main construction works for Phase 1A. This also ensures the successful completion of the strategic enablement phase of the Scheme that will unlock the next development phases in Prestwich. The use of a PCR compliant framework reduces the need to undertake a full tender process and significantly reduces the time required to appoint a main contractor. It also facilitates access to contractors of an appropriate tier and level of experience to deliver the travel hub. This ensures that Phase 1A is delivered competently, within the expected timescales and reduces risk of contractor failure. Through the procurement process, VINCI were able to offer the ability to deliver at the scale and complexity needed, demonstrated they had the ability to contract with the JV [LLP] terms and were able to evidence the financial standing to secure deliverability. Their financial standing was assessed as good, and they are considered a sustainable enterprise. Secured delivery of the Travel Hub ... view the full minutes text for item CA.273
Word for word from the decision Bury published for this meeting. Source: councildecisions.bury.gov.uk

Follow this further

Built from Bury's papers

What the report saysPro

Report to Cabinet

Summary

1.1The purpose of this report is to seek approval from Cabinet for the Prestwich Regeneration LLP (the Joint Venture company [JV]) of which the Council are 50%, to appoint the main contractor for the main works for the delivery of Phase 1A (Travel Hub) of the Prestwich Village Regeneration Scheme (the Scheme).

1.2This report is the second stage and a follow-up to the Cabinet report 16th July 2024 where approval was given for the legal structure and procurement strategy to appoint the Developer for the Scheme, which in turn will secure the services of a contractor using a Public Contracts Regulations 2015 (PCR) compliant procurement route.

1.3As confirmed in the previous Cabinet report, the JV [LLP] will be appointed by the Council as the Developer for the Scheme. Muse Places Ltd (Muse) will undertake this role on behalf of the JV [LLP]. Muse is a member of the Morgan Sindall Consortium LLP. Their appointment is via the Pagabo Developer Led Framework and Muse will in turn, enter into a sub-Development Agreement with the JV [LLP].

1.4The recommended PCR compliant route to procure the Main Contractor to deliver Phase 1A is the Pagabo Major Construction Works Framework (Pagabo).

1.5The Council has scrutinised the recommended procurement strategy for the main contractor works provided by Muse. Acceptance of the recommended procurement strategy has been subject to both framework conditions and objective assessment criteria in line with the PCR. The contractor selected following due diligence to deliver Phase 1A is VINCI Construction UK Limited (VINCI).

1.6The procurement route as explained above also dovetails with the approval by Cabinet of the funding strategy on 16 th July 2024 and enables the delivery of Phase 1A to be within the approved £14m cost envelope. 1.7 The proposed timescale for the delivery of Phase 1A is 71 weeks commencing January 2025, with completion in May 2026.

Recommendation(s) It is recommended that Cabinet: 2.1 Give consent for the Council (as 50% of the JV [LLP]) to provide approval to the JV [LLP] to appoint and enter into a building contract with VINCI as the main contractor to deliver Phase 1A (Travel Hub).

2.2Accept the tender report recommendation that VINCI undertake the main works at a sum contained within Part B, subject to the agreement of any contract amendments and clarifications, and within the previously approved cost envelope of £14m (inclusive of fees and other project management costs).

2.3Delegate authority to the Director of Law and Democratic Services in consultation with the Executive Director of Place to finalise and execute the building contract (noting that approval to be able to negotiate and complete detailed legal and procurement agreements associated with the delivery of the Scheme was given on 16th July 2024), consultant appointments, warranties and any other related ancillary agreements.

2.4Delegate authority to the Director of Law and Democratic Services in consultation with the Executive Director of Place to execute the Pagabo Client Access Agreement on behalf of the Council as a Member of the JV [LLP].

Reasons for recommendation(s)

3.1The use of Pagabo alongside objective criteria assessment is a PCR compliant procurement route which gives the ability to award the contract under this framework to deliver the main construction works for Phase 1A. This also ensures the successful completion of the strategic enablement phase of the Scheme that will unlock the next development phases in Prestwich.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Prestwich RegenerationDecisions 413 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 20 attended
EO
Councillor Eamonn O'BrienChair, present
CC
Councillor Clare CumminsCommittee Member, apologies
CM
Councillor Charlotte MorrisCommittee Member, present
AQ
Councillor Alan QuinnCommittee Member, apologies
TR
Councillor Tahir RafiqCommittee Member, present
LS
Councillor Lucy SmithCommittee Member, present
TT
Councillor Tamoor TariqCommittee Member, present
ST
Councillor Sean ThorpeCommittee Member, present
SW
Councillor Sandra WalmsleyCommittee Member, present
LR
Lynne RidsdaleOfficer, expected
JD
Jacqui DennisOfficer, expected
PM
Paul McKevittOfficer, expected

All 20 on the meeting page

On this subject at Bury

Search all
  1. Prestwich RegenerationThis decision
  2. Prestwich Village Regeneration Project: Phase 1A (Travel Hub) - Operations StrategyApproved
  3. Prestwich Village Regeneration Project: Delivery of Phase 1A (Travel Hub) - Additional Funding RequestApproved
  4. Prestwich Village Regeneration Project: Phases 1B & 2 Appointment of Pre-Construction Services Agreement Contractor Part AApproved
  5. Prestwich Village Regeneration Project: Delegated Authority to Appoint the Third-Party Operator for Phase 1A (Travel Hub)Approved
  6. Prestwich Village Regeneration Project: Phase 1B & 2 Appointment of Demolition Contractor - Part AApproved

More from Bury Cabinet

All decisions
MeetingDecisionOutcome
14 Oct 2026 Review and amendments to Bury Council's Housing Allocations PolicyDecision(s) Cabinet: · Approved the amendments to the Allocations policy. Reasons for decision(s) · The council has p... Approved Open
14 Oct 2026 Northern Gateway Western Access scheme: Stage 3 Contract Sum, External Professional Team Contract Extension, and Acceptance of Investment Zone Grant Funding.Decision(s) Cabinet: a. Delegated final acceptance of Balfour Beatty Civil Engineering Ltd Stage 3 contract sum, up t... Approved Open
14 Oct 2026 New Persona Shareholder Agreement - PART ADecision(s) Cabinet · Approved to adopt the new Persona Shareholder Agreement Reasons for decision(s) · To explore th... Approved Open
14 Oct 2026 Extension of Lease for St Monica's - Part ADecision(s) Cabinet: a. Approved the current heads of terms for the grant of the new lease and associated indemnity a... Approved Open
14 Oct 2026 Proposed creation of an End-to-End Greater Manchester Fostering HubDecision(s) Cabinet: · Endorsed the proposal for the transition from the current Greater Manchester Fostering Recruit... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies