Contract awards in respect of the HRA Capital Investment Programme 2026/27 and Carbon Reduction - Sustainability Improvement Measures

Approved Executive 1 paper

AI summaryCabinet approves £2,520,090.72 contract extension with A.Connolly for 140 Bent Hill properties and £2,608,261.32 contract award to Next Energy Solutions for three Programme B estates, supporting the housing retrofit to meet EPC C by 2030.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedOne 12-month extension, one new 8-month award with extension options
Money£2,520,090.72 and £2,608,261.32Initial term values, both inclusive of VAT
What happens next8th and 25th September 2026Contract start dates for the two awards
Who it affectsCouncil housing tenants140 at Bent Hill, 125 across three Programme B estates

What was decided

Cabinet approved a 12-month extension of the A.Connolly Limited contract for the Bent Hill estate, Prestwich, Sedgley Ward, covering 140 properties from 8th September 2026, at a total estimated value of £2,520,090.72 inclusive of VAT. Report P3, P7

Cabinet approved a contract award to Next Energy Solutions Ltd for Programme B, covering Goshen Estate (95 properties), Knowles St Estate (6) and Sumner Avenue Estate (24), with an initial 8-month term from 25th September 2026 at £2,608,261.32 inclusive of VAT, and two optional 12-month extensions from 1st April 2027 at the Council's discretion. Report P4, P7, P11, P12, P13

Each of the two potential 12-month extensions of the Next Energy contract is estimated at £3,912,391.98 inclusive of VAT, calculated on a pro rata annualised basis from the initial term figure. Report P5, P6, P7, P8

Why

The primary reason is to continue the Bury Council housing retrofit programme, which aims to help achieve Energy Performance Certificate C by 2030, reduce energy consumption and cut carbon emissions. Report P9

Retrofit surveys are underway to support a Social Housing/Warm Homes Fund Wave 3 grant application, which is considered essential to support HRA capital investment. Report P9, P16

Funding for the schemes was provided in the HRA Capital Investment Plan budget of £5.6m for Carbon reduction schemes approved by Cabinet in February 2026. Report P3, P21

What happens next

A.Connolly's extended contract begins on 8th September 2026 and the Next Energy initial term is proposed to start on 25th September 2026, with extension options exercisable from 1st April 2027. Report P3, P4, P7

Retrofit assessments continue ahead of a Warm Homes Social Housing Fund bid to GMCA, planned for submission in July 2026. Report P16

Social value commitments, including winter warmer packs, swift boxes, work with Bury College, litter picks, skip days and food bank donations, will be agreed at contract award meetings. Report P17

The money

  • £5.6m HRA Carbon reduction budget approved by Cabinet on 11th February 2026 Report P3
  • £2,520,090.72 A.Connolly 12-month extension, inclusive of VAT Report P3, P7
  • £2,608,261.32 Next Energy initial 8-month term, inclusive of VAT Report P4, P7
  • £3,912,391.98 Next Energy first 12-month extension, inclusive of VAT Report P5, P7
  • £3,912,391.98 Next Energy second 12-month extension, inclusive of VAT Report P6, P7
  • up to £7,000 Possible grant funding per EPC D or below rated property Report P15
  • circa £299 per year Estimated saving on tenant energy bills per property Report P18

Options considered

  • Rejected: Do nothing. Schemes needed to meet legislative EPC C by 2030 and Net Zero aims under GMHP by 2038 Report P10
  • Rejected: Deliver in-house via Repairs Direct. Specialist scope of work and lack of suitable skills and capacity in the in-house contractor Report P10
  • Rejected: Re-tender the A.Connolly Bent Hill scheme. Would involve a significantly extended procurement process in both time and cost Report P10

Implications

  • Financial: Initial term values sit within the £5.6m Carbon reduction budget approved as part of the HRA Capital Investment Plan for 2026/27. Report P3, P21
  • Legal: A.Connolly extension is permissible under the original contract terms and the Public Contracts Regulations 2015; Next Energy award used the GMCA911 framework under the Procurement Act 2023. Report P20
  • Equalities: The proposal does not affect one protected characteristic over another and aims to advance equality by tackling fuel poverty through improved energy efficiency. Report P17, P20
  • Climate: Works support reaching EPC C by 2030 and wider Net Zero aims, with circa 0.68 tonnes of CO2 saved per property per year, of which around 0.30 tonnes is from solar PV. Report P18
  • Risk: Stock condition surveys are 88% complete; without Cabinet approval the Council cannot address Decent Homes Standard thermal comfort failures or progress toward EPC targets. Report P19
  • Other: Bury Council Housing works with Bolton and Bury Swifts to mitigate impact on migrating birds, including installation of swift boxes and joint community events such as Summer Wings. Report P18

Who and where

  • 140 tenants on the Bent Hill estate, Prestwich, Sedgley Ward (Programme A) Report P3, P10
  • 95 tenants on the Goshen Estate, Redvales Ward (Programme B) Report P11
  • 24 tenants on the Sumner Avenue Estate, Radcliffe North and Ainsworth Ward (Programme B) Report P13
  • 6 tenants on the Knowles St Estate, Redbank Ward (Programme B) Report P12
  • 70 households borough-wide failing the Decent Homes Standard thermal comfort test, in Redvales, Ramsbottom, Besses, North Manor and Bury East Report P7, P14

Timeline

  • 11th February 2026: Cabinet approved the HRA Capital Works Programme and £5.6m budget for Carbon reduction schemes for 2026/27 Report P3
  • July 2026: Planned submission of Warm Homes Social Housing Fund bid to GMCA Report P16
  • 8th September 2026: A.Connolly contract extension begins for 12 months Report P3, P7
  • 9th September 2026: Cabinet decision date Report P2
  • 25th September 2026: Proposed start of Next Energy initial 8-month term Report P4, P7
  • 1st April 2027: First opportunity to exercise Next Energy extension options Report P4, P7
  • by 2030: Target date for all Council homes to reach EPC C Report P9, P18

Plain English for the jargon

  • EPC C: Energy Performance Certificate band C, the minimum energy efficiency target for Council homes by 2030.
  • HRA: Housing Revenue Account, the ring-fenced account for council housing income and spending.
  • GMHP: Greater Manchester Housing Plan, the regional framework for housing retrofit and net zero by 2038.
  • GMCA911: GMCA Net Zero Housing Retrofit Framework Agreement, used to procure Programme B works via Lot 13 Turnkey Solutions.
  • HHSRS: Housing Health and Safety Rating System, the statutory hazard assessment under the Housing Act 2004.
  • MEES: Minimum Energy Efficiency Standards for rented properties under the Energy Efficiency (Private Rented Property) (England and Wales) Regulations 2015.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemCA.59

Resolved

Decision(s): Cabinet: - Approved an extension of the existing contract between the Council and A.Connolly Limited (Company number 03860866) in respect of Bent Hill estate, Prestwich, Sedgley Ward – 140 properties, which forms part of Programme A, for a further term of 12 months commencing on 8th September 2026 and a total estimated contract value of £2,520,090.72 (inclusive of VAT). - A contract award to Next Energy Solutions Ltd (Company number 10147744), in respect of the Estates comprising of Programme B and as outlined at 2.1, for an initial term of 8 months (proposed commencement date of 25th September 2026 and the option to extend for a further two years taken as 12-month increments from 1st April 2027, at the Council’s sole discretion. The total estimated contract value for the initial term is £2,608,261.32 (inclusive of VAT). The total estimated future contract values in the event the options to extend are utilised by the Council are as follows: o First 12-month extension: £3,912,391.98 (inclusive of VAT) o Second 12-month extension: £3,912,391.98 (inclusive of VAT) - The estimated future contract values for the extension periods represent annualised values calculated on a pro rata basis from the initial term figure. Reasons for decision(s) - The primary reason for requesting the contract extension with A.Connolly and contract award to Next Energy is to ensure continuation of the Bury Council Housing retrofit programme, which is aimed at helping to achieve Energy Performance Certificate (“EPC”) C by 2030 along with aims to reduce energy consumption and carbon emissions. Retrofit surveys are underway in preparation for Social Housing/Warm Homes Fund (Wave 3) grant application which is essential to support HRA capital investment. Alternative options considered and rejected - Do nothing: The energy schemes are necessary to help achieve legislative requirements of EPC C by 2030 and Net Zero ambitions in line with GMHP by 2038. - Deliver Inhouse: Due to the specialist scope of work within these contracts there is both a lack of suitable skills and capacity for the in-house contractor (Repairs Direct). - Re- tender: This option was considered for A.Connolly relating to the Bent Hill scheme and would be possible; however, this would involve a significantly extended procurement process in both time and cost.
Word for word from the decision Bury published for this meeting. Source: councildecisions.bury.gov.uk

Follow this further

Built from Bury's papers

What the report saysPro

Report to Cabinet

Classification: Decision Type: Open Key

Date: 09 September Report to: Cabinet 2026 Contract awards in respect of the HRA Capital Investment Subject: Programme 2026/27 and Carbon Reduction - Sustainability Improvement Measures Report of Cabinet Member for Housing Services

Summary 1. On 11th February 2026 Cabinet approved the Housing Revenue Account (“HRA”) Capital Works Programme for 2026/27 and a budget of £5.6m for Carbon reduction schemes - Sustainability Improvement Measures. 2. The purpose of the current report is to seek formal approval of the following contract awards for Carbon reduction schemes below: a) An extension of the existing contract between the Council and A.Connolly Limited (Company number 03860866) (“A.Connolly”) for a further term of 12 months commencing on 8th September 2026 and total estimated contract value of £2,520,090.72 (inclusive of VAT). During the period of extension, the work carried out by A.Connolly will be in respect of the Bent Hill estate Prestwich Sedgely Ward - 140 properties, which forms part of Programme A.

b) A contract award to Next Energy Solutions Ltd (Company number 10147744) (“Next Energy”) in respect of the estates mentioned below at 2.1 which comprise of Programme B, for an initial term of 8 months (proposed commencement date of 25th September 2026 and the option to extend for two further years taken as 12 month increments, from 1st April 2027 at the Council’s sole discretion. The total estimated contract value for the initial term is £2,608,261.32 inclusive of VAT. 3. The total estimated future contract values in the event the options to extend are utilised by the Council are as follows:

• First 12-month extension: £3,912,391.98 (inclusive of VAT)

• Second 12-month extension: £3,912,391.98 (inclusive of VAT)

4. The estimated future contract values for the extension periods represent annualised values calculated on a pro rata basis from the initial term figure. 5. The Estates comprising of Programme B are: • 2.1.2 Goshen Estate, Redvales Ward - 95 properties • 2.1.3 Knowles St Estate, Redbank Ward - 6 properties • 2.1.4 Sumner Avenue Estate, Radcliffe North and Ainsworth Ward - 24 properties 6. Decent Homes Standard - Thermal Comfort fails for 70 properties throughout the borough. These are located within the Redvales, Ramsbottom, Besses, North Manor, Bury East areas. Recommendation(s) 7. Cabinet is asked to approve the following: 7.1 An extension of the existing contract between the Council and A.Connolly Limited (Company number 03860866) in respect of Bent Hill estate, Prestwich, Sedgley Ward – 140 properties, which forms part of Programme A, for a further term of 12 months commencing on 8th September 2026 and a total estimated contract value of £2,520,090.72 (inclusive of VAT). 7.2 A contract award to Next Energy Solutions Ltd (Company number 10147744), in respect of the Estates comprising of Programme B and as outlined at 2.1, for an initial term of 8 months (proposed commencement date of 25th September 2026 and the option to extend for a further two years taken as 12-month increments from 1st April 2027, at the Council’s sole discretion. The total estimated contract value for the initial term is £2,608,261.32 (inclusive of VAT). The total estimated future contract values in the event the options to extend are utilised by the Council are as follows: • First 12-month extension: £3,912,391.98 (inclusive of VAT) • Second 12-month extension: £3,912,391.98 (inclusive of VAT)

The estimated future contract values for the extension periods represent annualised values calculated on a pro rata basis from the initial term figure.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Contract awards in respect of the HRA Capital Investment Programme 2026/27 and Carbon Reduction: Sustainability Improvement MeasuresDecisions 304 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 17 attended
EO
Councillor Eamonn O'BrienChair, present
AA
Councillor Ayesha ArifCommittee Member, present
RG
Councillor Richard GoldCommittee Member, present
GM
Councillor Gavin McGillCommittee Member, present
CM
Councillor Charlotte MorrisCommittee Member, present
LS
Councillor Lucy SmithCommittee Member, present
TT
Councillor Tamoor TariqCommittee Member, present
ST
Councillor Sean ThorpeCommittee Member, present
SW
Councillor Sandra WalmsleyCommittee Member, apologies due to council business
LR
Lynne RidsdaleOfficer, expected
JD
Jacqui DennisOfficer, expected
NK
Neil KissockOfficer, expected

All 17 on the meeting page

On this subject at Bury

Search all
  1. Contract awards in respect of the HRA Capital Investment Programme 2026/27 and Carbon Reduction - Sustainability Improvement MeasuresThis decision
  2. Care at Home - Request to Delegate the Authority to Contract AwardsRefused
  3. Contract awards in respect of the HRA Capital Investment Programme 2026/27 and Carbon Reduction - Sustainability Improvement MeasuresAgreed

More from Bury Cabinet

All decisions
MeetingDecisionOutcome
14 Oct 2026 Review and amendments to Bury Council's Housing Allocations PolicyDecision(s) Cabinet: · Approved the amendments to the Allocations policy. Reasons for decision(s) · The council has p... Approved Open
14 Oct 2026 Northern Gateway Western Access scheme: Stage 3 Contract Sum, External Professional Team Contract Extension, and Acceptance of Investment Zone Grant Funding.Decision(s) Cabinet: a. Delegated final acceptance of Balfour Beatty Civil Engineering Ltd Stage 3 contract sum, up t... Approved Open
14 Oct 2026 New Persona Shareholder Agreement - PART ADecision(s) Cabinet · Approved to adopt the new Persona Shareholder Agreement Reasons for decision(s) · To explore th... Approved Open
14 Oct 2026 Extension of Lease for St Monica's - Part ADecision(s) Cabinet: a. Approved the current heads of terms for the grant of the new lease and associated indemnity a... Approved Open
14 Oct 2026 Proposed creation of an End-to-End Greater Manchester Fostering HubDecision(s) Cabinet: · Endorsed the proposal for the transition from the current Greater Manchester Fostering Recruit... Noted Open