CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Bury Metropolitan Borough Council
Cabinet, Wednesday 9 September 2026 at 6.00pm

Care at Home - Request to Delegate the Authority to Contract Awards

Refused Executive 2 papers

AI summaryBury Cabinet delegates Care at Home contract award decisions to senior officers, enabling the open tender under the Procurement Act 2023 to proceed without returning to Cabinet.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeRefusedTo award and seal Care at Home contracts
Moneyc.£12.426m per yearEstimated £62.130m over five years
What happens nextAward expected Dec 2026/Jan 2027Open tender under Procurement Act 2023
Who it affectsAround 700 people dailyVulnerable adults receiving home care

What was decided

Cabinet delegated authority to award Care at Home contracts to the Director of Adult Social Services and Community Commissioning and the Executive Director of Health and Adult Care. Report P9

Cabinet delegated finalisation and sealing of the contracts to the Director of Law and Democratic Services, in consultation with the two adult social care directors. Report P9

Why

The Council must re-tender under the Procurement Act 2023 to stay compliant with procurement law and fair purchasing duties. Report P10, P13

A new contract and service specification will bring updated quality requirements, clearer key performance indicators for monitoring, and a broader scope for innovation. Report P10, P13

What happens next

Complete the open tender exercise, which is already at the Conditions of Participation evaluation stage, with contract award expected in December 2026 or January 2027. Report P8, P16

The delegated officers will run the award process within the parameters already agreed by Cabinet in October 2025, without needing to return to Cabinet. Report P17

The money

  • c.£12.426m Council spend on Care at Home in 2025/26 Report P4, P18
  • approximately £12.426 million Estimated annual expenditure on the new framework Report P18
  • estimated £62.130 million Estimated total over the potential five-year contract term Report P18

Options considered

  • Chosen: Delegate the contract award authority to senior officers. Avoids the need to return to Cabinet and enables the re-tender to progress within the approvals already given. Report P17
  • Rejected: Consider alternative options. Not applicable due to Procurement Law and the requirement to complete a re-tender exercise. Report P11
  • Rejected: Do nothing. Would risk the Council being non-compliant with the Procurement Act 2023. Report P11

Implications

  • Legal: Cabinet can delegate the contract award under the Council's Constitution and Scheme of Delegations, provided the award is within the scope of approvals already given. Report P17
  • Financial: The Adult Social Care budget faces significant pressures in 2026/27; the recommissioning must show value for money and support Medium-Term Financial Strategy savings targets. Report P18
  • Equalities: A full equality impact assessment has been completed; concerns about continuity of care providers and trusted relationships have been identified and will be addressed. Report P14, P19
  • Climate: Providers will be required to demonstrate how they will support the Council's target to be carbon neutral by 2038; no direct impact on biodiversity. Report P15
  • Risk: Risk of non-compliance with the Procurement Act 2023, legal challenges from unsuccessful providers, and delays leaving the Council temporarily out of contract; incumbent providers must support safe handover for up to 12 months after the contract end date. Report P16

Who and where

  • Around 700 people per day receiving Care at Home support in Bury Report P4
  • Vulnerable adults with assessed needs under the Care Act 2014 Report P3
  • Local and other potential providers of home care services Report P14

Timeline

  • October 2021: Current Care at Home service commissioned for 3 years with extension options up to a total of 5 years Report P6
  • 04 November to 15 December 2024: 6-week public consultation on the service Report P8
  • 2024 and 2025: Extension periods granted by Cabinet Report P7
  • October 2025: Cabinet approved the open tender process for a 5-year contract with a 2-year extension option and delegated the service specification Report P8
  • 09 December 2025: Pre-market engagement with providers Report P8
  • 18 May to 07 June 2026: 3-week customer consultation on a proposed change to the payment model Report P8
  • 09 September 2026: Cabinet decision to delegate contract award authority Report P2
  • December 2026/January 2027: Contract anticipated to be awarded Report P16

Plain English for the jargon

  • Care at Home: Council-commissioned support for vulnerable people in their own homes, including personal care, moving and handling, nutrition, hydration and medication, provided under the Care Act 2014.
  • Procurement Act 2023: UK legislation governing how public bodies must run fair purchasing processes and tenders.
  • Conditions of Participation: The first stage of the new procurement process under the Procurement Act 2023, used to assess which bidders can take part in the tender.
  • MTFS: Medium-Term Financial Strategy, the Council's plan for managing its budget and savings over several years.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemCA.61

Resolved

Decision(s) Cabinet - Delegated the authority to contract awards to the Director of Adult Social Services and Community Commissioning and the Executive Director of Health and Adult Care. - Delegated finalisation and sealing of the contracts to the Director of Law and Democratic Services in consultation with the Director of Adult Social Services and Community Commissioning and the Executive Director of Health and Adult Care. Reasons for decision(s) - The Council has a legal duty to follow Procurement Law and fair purchasing processes and must complete a re-tender process to ensure compliance with the legislation (Procurement Act 2023). Additional benefits include a new contract and service specification with updated quality requirements enabling us to ensure high standards for the customers, clearer key performance indicators for robust contract monitoring, and a broader scope for innovation. Alternative options considered and rejected - Alternative options are not applicable due to Procurement Law and the requirement to complete a re-tender exercise (Procurement Act 2023). Should the Council decide to do nothing, we would risk being non-compliant with the legislation.
Word for word from the decision Bury published for this meeting. Source: councildecisions.bury.gov.uk

Follow this further

Built from Bury's papers

What the report saysPro

Report to Cabinet

Classification: Decision Type: Open Key

Date: 09 September Report to: Cabinet 2026 Care at Home – Request to Delegate the Authority to Contract Subject: Awards Report of Cabinet Member for Adult Care, Health and Public Service Reform

Summary The Care at Home service supports the vulnerable people of Bury with their assessed needs under the Care Act 2014. This includes support with personal care, moving and handling, nutrition and hydration, and medication.

The Council spend on Care at Home in 2025/26 was c.£12.426m, the service supports approximately 700 people each day and delivers circa 10,000 hours of home care each week.

Care at Home contracts normally last approximately 5 years, the expenditure incurred over this period is significant and for this reason, the process of designing the specification and identifying providers is in depth, comprehensive, and lengthy.

The current service was commissioned in October 2021 for a period of 3 years with an option to extend by a further period or periods of up to 24 months provided that the total term of the contract does not exceed a total of 5 years.

The extension periods were granted by Cabinet in 2024 and 2025, and during the past 2 years the Community Commissioning Team has engaged with all key stakeholders:

• A 6-week public consultation ran from Monday 04 November to Sunday 15 December 2024 and the analysed consultation findings along with desktop research informed the updated service specification. • Following pre-market engagement with providers on 09 December 2025, a further 3-week customer consultation ran from Monday 18 May to Sunday 07 June 2026 regarding a proposal to change the payment model. The Community Commissioning Team and the Corporate Procurement Team are now in a strong position to run an open tender exercise under the Procurement Act 2023 with the Conditions of Participation stage already underway. The approval to commence this open tender process for a 5-year contract with the option to extend for a further 2-year period was approved by Cabinet in October 2025. The approval to delegate the authority to approve the service specification to the Director of Adult Social Services and Community Commissioning was also approved by Cabinet in October 2025. Recommendation(s)

1. Delegate the authority to contract awards to the Director of Adult Social Services and Community Commissioning and the Executive Director of Health and Adult Care. 2. Delegate finalisation and sealing of the contracts to the Director of Law and Democratic Services in consultation with the Director of Adult Social Services and Community Commissioning and the Executive Director of Health and Adult Care.

Reasons for recommendation(s) The Council has a legal duty to follow Procurement Law and fair purchasing processes and must complete a re-tender process to ensure compliance with the legislation (Procurement Act 2023). Additional benefits include a new contract and service specification with updated quality requirements enabling us to ensure high standards for the customers, clearer key performance indicators for robust contract monitoring, and a broader scope for innovation.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Care at Home: Request to Delegate the Authority to Contract AwardsDecisions 168 KB DownloadRead as text
PDF
Care at Home EIA Final: 05.08.2026: for September CabinetDecisions 354 KB Download

At this meeting

Whole meeting

Who was there

8 of 17 attended
EO
Councillor Eamonn O'BrienChair, present
AA
Councillor Ayesha ArifCommittee Member, present
RG
Councillor Richard GoldCommittee Member, present
GM
Councillor Gavin McGillCommittee Member, present
CM
Councillor Charlotte MorrisCommittee Member, present
LS
Councillor Lucy SmithCommittee Member, present
TT
Councillor Tamoor TariqCommittee Member, present
ST
Councillor Sean ThorpeCommittee Member, present
SW
Councillor Sandra WalmsleyCommittee Member, apologies due to council business
LR
Lynne RidsdaleOfficer, expected
JD
Jacqui DennisOfficer, expected
NK
Neil KissockOfficer, expected

All 17 on the meeting page

On this subject at Bury

Search all
  1. Care at Home - Request to Delegate the Authority to Contract AwardsThis decision
  2. Care at Home – Request for Contract Extension and Re-TenderApproved
  3. Care at Home Tender ApprovalApproved
  4. Care at Home ReviewApproved
  5. Adult Social Care - Care at Home Re-tenderApproved
  6. Care Home VisitsAgreed

More from Bury Cabinet

All decisions
MeetingDecisionOutcome
14 Oct 2026 Review and amendments to Bury Council's Housing Allocations PolicyDecision(s) Cabinet: · Approved the amendments to the Allocations policy. Reasons for decision(s) · The council has p... Approved Open
14 Oct 2026 Northern Gateway Western Access scheme: Stage 3 Contract Sum, External Professional Team Contract Extension, and Acceptance of Investment Zone Grant Funding.Decision(s) Cabinet: a. Delegated final acceptance of Balfour Beatty Civil Engineering Ltd Stage 3 contract sum, up t... Approved Open
14 Oct 2026 New Persona Shareholder Agreement - PART ADecision(s) Cabinet · Approved to adopt the new Persona Shareholder Agreement Reasons for decision(s) · To explore th... Approved Open
14 Oct 2026 Extension of Lease for St Monica's - Part ADecision(s) Cabinet: a. Approved the current heads of terms for the grant of the new lease and associated indemnity a... Approved Open
14 Oct 2026 Proposed creation of an End-to-End Greater Manchester Fostering HubDecision(s) Cabinet: · Endorsed the proposal for the transition from the current Greater Manchester Fostering Recruit... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies