Construction of Flood Defence Structures at Alverstoke

Noted Committee 1 paper

Community & Environment Board noted this item on Wednesday 21 September 2022. Below is the council's own wording, with the papers it was decided on.

Item14

Resolved

That the Board noted that: - A number of risks have been realised on the scheme, including high voltage underground cables and the effects of inflation, which have put the project budget under significant pressure. - To mitigate financial risk, construction works have been paused and the site is being reinstated to pre-works condition and will be opened to the public. - The future delivery of the scheme is being determined to ensure sufficient budget is available. - Public communications have been completed , via a letter drop, site notices and website updates, explaining that due to realised risks, construction work on the defence has stopped.
Word for word from the decision Gosport published for this meeting. Source: democracy.gosport.gov.uk

Follow this further

Built from Gosport's papers

What the report saysPro

Report to Community & Environment Board

Background

1.1The proposed scheme at Alverstoke will reduce flood risk to 130 properties in Alverstoke over the next 50 years. The preferred contractor was approved by the Community Board 10th February 2021 Construction of the scheme started in January 2022, with an estimated six-months duration.

1.2During construction a number of risks were realised, and a decision was made in April 2022 to pause construction works on site to ensure the mandated budget was not exceeded. In September 2022, reinstatement works to return the site to pre-works condition will be completed. The site will then be opened to the public. These actions avoid putting the council at excessive risk. 1.3 Upon resolving the outstanding risks and funding needs, it is intended that the works will resume as quickly as possible, but the outcome cannot be known at this stage. The optimum way forward will need to be developed in consultation with the Environment Agency to establish a suitable funding route. 2.0 Report

2.1Scheme Design:

The proposed scheme at Alverstoke will provide flood defence to a 1 in 100 year event (1% Annual Exceedance Probability) up to 2060.

The defence comprises a circa 1m high reinforced concrete wall at the western end of the lake, with tapering tie-ins at the northern and southern ends. The northern end of the defence requires construction on private land. The wall has a textured finish to the lake face to complement the existing wall at this location. A floodgate completes the defence across Little Anglesey Road.

2.2Progress Update:

Construction works started in mid-January 2022.

During construction a number of risks were realised which have impacted the project significantly:

 The location of two high voltages cables which significantly impact the safety of the construction, the works programme and costs.  The civil engineering sector is facing unprecedented challenges from cost inflation and the supply of construction materials.  An immediate request was made to the Environment Agency for additional funds. An official decision has not yet been received and is now outside of the timeframe needed to maintain progress on site.

The following actions were taken to mitigate the risk that the mandated budget would be exceeded:

 Construction works were paused in mid-April 2022 while investigations were undertaken. Then suspended in June 2022.  Further engagement has been undertaken with the utility provider regarding the high voltage cables.  The site is being reinstated to pre-works condition and is planned to be opened to the public by mid-September 2022.  The Contractor will demobilise following reinstatement.  Risk impacts continue to be assessed and solutions developed.  The project will continue to endeavour to secure additional funding as required. 2.3 Stakeholder communications:

The following actions have been taken:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Construction of Flood Defence Structures at AlverstokeReport 225 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 8 attended
MZ
Councillor Mrs Zoe HugginsCommittee Member, present
JW
Councillor Julie WesterbyChairman, present
MJ
Councillor Mrs June CullyCommittee Member, present
MJ
Councillor Murray JohnstonCommittee Member, present
MD
Councillor Miss Dawn KellyVice-Chair, present
BM
Councillor Bob MaynardCommittee Member, apologies, sent representative
MM
Councillor Mrs Margaret MorganCommittee Member, present
PC
Councillor Peter ChegwynCommittee Member, present as substitute

On this subject at Gosport

Search all
  1. Construction of Flood Defence Structures at AlverstokeThis decision
  2. Construction of Flood Defence Structures at FortonNoted
  3. Construction of Flood Defence Structures at FortonApproved
  4. Construction of Flood Defence Structures at FortonNoted
  5. Construction of Flood Defence Structures at AlverstokeNoted
  6. Construction of Flood Defence Structures at AlverstokeNoted

More from Gosport Community & Environment Board

All decisions
MeetingDecisionOutcome
16 Sep 2026 Minutes of the meeting of the board held on 17 June 2026 and 15 July 2026That the minutes of the meetings held on 17 June 2026 and 15 July 2026 were signed as a true and correct record. Decided Open
16 Sep 2026 Project Integra Joint Municipal Waste management Strategy- A Resources and Waste Strategy for HampshireThat the Board approved: i) The revised project Integra Joint Municipal Waste Management Strategy 2026 to 2035 (A Res... Approved Open
17 Jun 2026 Election of ChairmanThat Councillor Ricketts is elected as Chairman for the municipal year 2026-2027 Decided Open
17 Jun 2026 Election of Vice ChairmanThat Councillor Bond was elected as Vice Chairman for the municipal year 2026-2027 Decided Open
17 Jun 2026 Minutes of the meeting of the board held on 25 February 2026That the minutes of the meeting held on 25 February were signed as a true and correct record. Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies