That the Board noted that: - A number of risks have been realised on the scheme, including high voltage underground cables and the effects of inflation, which have put the project budget under significant pressure. - To mitigate financial risk, construction works have been paused and the site is being reinstated to pre-works condition and will be opened to the public. - The future delivery of the scheme is being determined to ensure sufficient budget is available. - Public communications have been completed , via a letter drop, site notices and website updates, explaining that due to realised risks, construction work on the defence has stopped.
Word for word from the decision Gosport published for this meeting.Source: democracy.gosport.gov.uk
1.1The proposed scheme at Alverstoke will reduce flood risk to 130 properties in Alverstoke over the next 50 years. The preferred contractor was approved by the Community Board 10th February 2021 Construction of the scheme started in January 2022, with an estimated six-months duration.
1.2During construction a number of risks were realised, and a decision was made in April 2022 to pause construction works on site to ensure the mandated budget was not exceeded. In September 2022, reinstatement works to return the site to pre-works condition will be completed. The site will then be opened to the public. These actions avoid putting the council at excessive risk. 1.3 Upon resolving the outstanding risks and funding needs, it is intended that the works will resume as quickly as possible, but the outcome cannot be known at this stage. The optimum way forward will need to be developed in consultation with the Environment Agency to establish a suitable funding route. 2.0 Report
2.1Scheme Design:
The proposed scheme at Alverstoke will provide flood defence to a 1 in 100 year event (1% Annual Exceedance Probability) up to 2060.
The defence comprises a circa 1m high reinforced concrete wall at the western end of the lake, with tapering tie-ins at the northern and southern ends. The northern end of the defence requires construction on private land. The wall has a textured finish to the lake face to complement the existing wall at this location. A floodgate completes the defence across Little Anglesey Road.
2.2Progress Update:
Construction works started in mid-January 2022.
During construction a number of risks were realised which have impacted the project significantly:
The location of two high voltages cables which significantly impact the safety of the construction, the works programme and costs. The civil engineering sector is facing unprecedented challenges from cost inflation and the supply of construction materials. An immediate request was made to the Environment Agency for additional funds. An official decision has not yet been received and is now outside of the timeframe needed to maintain progress on site.
The following actions were taken to mitigate the risk that the mandated budget would be exceeded:
Construction works were paused in mid-April 2022 while investigations were undertaken. Then suspended in June 2022. Further engagement has been undertaken with the utility provider regarding the high voltage cables. The site is being reinstated to pre-works condition and is planned to be opened to the public by mid-September 2022. The Contractor will demobilise following reinstatement. Risk impacts continue to be assessed and solutions developed. The project will continue to endeavour to secure additional funding as required. 2.3 Stakeholder communications:
The following actions have been taken:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.