That the Board noted: - A number of risks have been realised on the scheme, including a badger sett and the effects of inflation, which have put the project budget under significant pressure. - To mitigate financial risk, construction works have been paused and the site is being reinstated to pre-works condition and will be opened to the public. - The future delivery of the scheme is being determined, supported by assessments to ensure sufficient budget is available. - Public communications have been completed , via a letter drop and website updates, explaining that due to realised risks, construction work on the defence has stopped.
Word for word from the decision Gosport published for this meeting.Source: democracy.gosport.gov.uk
1.1The proposed scheme will reduce flood risk to 211 properties in Forton over the next 50 years. The preferred contractor was approved by the Community Board 10th February 2021. Construction of the scheme started in April 2022, with an estimated four-month duration.
1.2During construction a number of risks were realised, and a decision was made in April 2022 to pause construction works on site to ensure the mandated budget was not exceeded. In September 2022, the site will be reinstated back to pre-works condition and will be re-opened, to avoid putting the council at excessive risk.
1.3Upon resolving the outstanding risks and funding needs, it is intended that the works will resume as quickly as possible, but this outcome cannot be known at this stage. The optimum way forward will need to be developed in consultation with the Environment Agency to establish a suitable funding route. 2.0 Report
2.1Scheme Design:
The proposed scheme at Forton will provide a flood defence to a 1 in 100- year event (1% Annual Exceedance Probability) up to 2060.
The defence comprises a 1.1m high, and 240m long reinforced concrete wall set back from the quay edge. This links to higher ground in the north and south where there are two low level ‘raised road humps’ to provide the levels needed for flood protection and allow vehicles to cross the defence. At the southern end, ‘demountable flood boards’ will be used on the road hump to provide extra flood defence height during specified tidal events.
2.2Progress Update:
Construction works started in April 2022.
During construction a number of risks were realised which have impacted the project significantly:
The location of a badger sett discovered on site and the need to construct a new artificial badger sett to replace this. This will involve planning applications and environmental licences, and specialist advice to ensure we comply with environmental law. The civil engineering sector is facing unprecedented challenges from cost inflation and the supply of construction materials. An immediate request was made to the Environment Agency for additional funds. An official decision has not yet been received and is now outside of the timeframe needed to maintain progress on site.
The following actions were taken to mitigate the risks that the mandated budget would be exceeded:
Engagement has been undertaken with the specialist badger consultant regarding the location and presence of badgers on site. Construction works were paused in mid-April 2022 and suspended in June 2022. The site is planned to be reinstated to pre-works condition in September 2022. The contractor will demobilise following reinstatement. The badger issues continue to be assessed and solutions developed. The project will continue to endeavour to secure additional funding as required. 2.3 Stakeholder Communications:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.