Development Control Committee, Monday 8 December 2025 at 1.30pm

HPK/2025/0312 - Land off Hallsteads Close, Dove Holes

Approved Planning 1 paper

AI summaryHigh Peak Borough Council's Development Control Committee approved revised construction and delivery hours at the 83-home Hallsteads Close site in Dove Holes, with weekday work from 07:30 to 17:00 and Saturday work from 08:30 to 14:00.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedVariation of condition on 83-dwelling scheme approved with revised hours
MoneyNo new Section 106 requiredExisting S106 covers planning obligations and applies to this application
What happens nextDecision notice to be issuedHead of Development Services authorised to amend wording
Who it affectsResidents near Hallsteads Close and developerClosest homes are 133, 121a Hallsteads and Hallsteads Farm

What was decided

Planning permission was granted, varying the construction and delivery hours condition on the 83-dwelling scheme at Land off Hallsteads Close, Dove Holes. Report P40

Condition 27 sets weekday construction and deliveries from 07:30 to 17:00, Saturday from 08:30 to 14:00, with no working on Sundays or Bank Holidays, and a separate condition prevents visible dust beyond the site boundary. Report P41, 7.6

The Head of Development Services was given delegated authority, in consultation with the Chair, to make minor wording changes to conditions, informatives, obligations or reasons before the decision is issued. Report P42

Why

Officers considered the revised hours would not unduly harm residential amenity, because the nearest properties are at least 15 metres from the closest plots and the weekday finish moves earlier to 17:00. Report 7.4, 7.5, 7.6, 7.7

The Environmental Health Officer accepted the earlier weekday start but recommended an 08:30 Saturday start to protect weekend quiet, which was adopted, with Saturday finishing extended to 14:00. Report P11, P12, 7.6

The proposal was found to accord with the High Peak Local Plan, in particular Policy EQ6 on amenity and Policy CF7 on planning obligations, and the scheme contributes to housing supply and affordable housing. Report 7.3, 7.13, P39

What happens next

The decision notice will be issued, with delegated authority to the Head of Development Services to finalise wording. Report P42

The developer must continue to comply with the previously discharged pre-commencement conditions, including the construction management plan, drainage, ecology, archaeology, and the Network Rail Basic Asset Protection Agreement. Report 7.11, 7.12, P19, P41

The money

  • £40,620.20 Existing S106 contribution towards off-site outdoor sports facilities, index linked Report 7.1, 7.13
  • £15,963 Existing S106 contribution towards off-site play facilities, index linked Report 7.1, 7.13

Options considered

  • Chosen: Grant planning permission as recommended with revised hours. Scheme complies with the development plan and revised hours would not unduly harm neighbours Report P40, 7.7, P39
  • Rejected: Refuse planning permission. No material harm identified to justify refusal Report 7.6, 7.7, P39

Implications

  • Legal: A new planning permission is granted under section 73, replacing the relevant conditions on HPK/2019/0028; the existing S106 agreement continues to apply. Report 7.1, 7.13, P40
  • Other: Construction activity can start at 07:30 weekdays, an hour earlier than the original consent, but must finish an hour earlier at 17:00. Report 7.4, 7.6, P41
  • Other: Network Rail's Basic Asset Protection Agreement governs how works near the railway line are carried out, separately from this permission. Report P19, 7.12
  • Risk: Condition 26 requires no visible dust beyond the site boundary, and other conditions control noise, vibration, piling and the construction management plan. Report P41, 7.11

Who and where

  • Residents of nearby properties on Hallsteads, including 133, 121a and Hallsteads Farm Report 7.5, 7.6
  • The applicant and developer of the 83-dwelling scheme Report 7.1, 7.2, P40
  • Network Rail as a neighbour and through the Asset Protection Agreement Report P19, 7.12
  • Future occupants of the 83 dwellings, including 25 affordable homes Report 7.1, 7.10

Timeline

  • June 2022: Original planning permission HPK/2019/0028 granted for 83 dwellings Report 7.1
  • 17th September 2025: Expiry of neighbour letter consultation (reconsultation) Report P1
  • 25th September 2025: Expiry of press notice consultation Report P1
  • 30th September 2025: Expiry of site notice consultation (reconsultation) Report P1
  • 8 December 2025: Development Control Committee resolves to grant permission

Plain English for the jargon

  • Section 73 application: An application to vary or remove conditions attached to an existing planning permission
  • Section 106 agreement: A legal agreement between a developer and the council used to secure planning obligations such as affordable housing or financial contributions
  • Pre-commencement condition: A planning condition that must be discharged and approved before development can lawfully begin
  • DOC reference: A council reference for the formal discharge of a planning condition
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item26/73

Resolved

That planning permission be granted as set out in the report; and 2. That in the event of any changes being needed to the wording of the Committee’s decision (such as to delete, vary or add conditions/ informatives /planning obligations or reasons for approval/refusal) prior to the decision being issued, the Head of Development Services be delegated authority to do so in consultation with the Chair of the Committee, provided that the changes do not exceed the substantive nature of the Committee’s decision.
Word for word from the decision High Peak published for this meeting. Source: democracy.highpeak.gov.uk

Follow this further

Built from High Peak's papers

What the report saysPro

Report to Development Control Committee

HIGH PEAK BOROUGH COUNCIL DEVELOPMENT CONTROL COMMITTEE

8th December 2025

Application HPK/2025/0312 No: Location Land off Hallsteads Close, Dove Holes Proposal Application for variation of condition 26 in relation to HPK/2019/0028

Applicant HJK Construction (Northern) Limited Agent WSP Parish/ward Chapel-en-le-Frith/ Date registered: 15/08/2025 Limestone Peak If you have a question about this report please contact: Jane Colley, email: [email protected]

REFERRAL

The application is before committee as the application comprises major development and the committee has previously dealt with planning applications associated with the wider housing site.

1. Summary of Recommendations

APPROVAL, subject to conditions

2. DESCRIPTION OF THE SITE AND ITS SURROUNDINGS

2.1The application site comprises a rectangular shaped area of land which is some 2.3 ha in area, located on the north – western side of Dove Holes, adjacent to properties which face onto the A6. Works are currently underway pursuant to HPK/2019/0028 for 83 houses. The site was formerly used for the grazing of animals. A drystone wall forms the boundary on all sides.

2.2The site is bordered by the railway line to the west, residential properties to the south and Public Footpath 129 which aligns to the northern boundary.

2.3The site lies within the built-up area boundary for Dove Holes as defined in the Chapel-en-le-Frith Neighbourhood Plan. 3. DESCRIPTION OF THE PROPOSAL

3.1This application seeks consent for the variation of condition 26 of HPK/2019/0028, to amend the working and delivery times for the development.

3.2Condition 26 of HPK/2029/0028 currently states:

26. All construction and delivery times shall take place between:

• 08:30 – 18:00 (Monday to Friday) • 08:30 – 14:00 (Saturdays) • No working is permitted on Sundays or Bank Holidays

Reason: In the interests of the residential amenities of the neighbouring properties and in accordance with Policy EQ6 of the High Peak Local Plan and the NPPF.

3.3As originally proposed the applicant sought to amend the working and delivery times to:

26. All construction and delivery times shall take place between:

• 07:30 – 17:00 (Monday to Friday) • 07:30 – 13:00 (Saturdays) • No working is permitted on Sundays or Bank Holidays

3.4However following discussions with the Councils Environmental Health Officer, it is now proposed to amend the working and delivery times to:

All construction and delivery times shall take place between:

• 07:30 – 17:00 (Monday to Friday) • 08:30 – 14:00 (Saturdays) • No working is permitted on Sundays or Bank Holidays

3.5Details of the planning application, plans and consultee responses can be view at: Planning Application - High Peak Borough Council

4. RELEVANT PLANNING HISTORY

4.1The site has been the subject to the following planning history:

DOC/2025/0053 – Discharge of condition 8 – Approved 21.11.2025

DOC/2025/0021 – Discharge of conditions 17 and 19 – Approved 25.6.2025

DOC/2025/0020 - Discharge of conditions 30, 31, 32 and 33 – Approved 25.6.2025

DOC/2024/0120 – Discharge of conditions 15, 24 and 28 – Approved 25.6.2025 DOC/2023/0091 – Discharge of conditions 8, 15, 17, 19, 22, 24, 31, 33, 35 and 36 – Split decision 19.6.2024

DOC/2023/0052 – Discharge of conditions 23, 24, 26b, 30 and 33 – Refused 8.9.2023

DOC/2022/0060 – Discharge of conditions 3, 5, 14, 15, 17-19, 22, 25, 26, 27, 28, 32 and 34 – Split decision 18/08/2023

HPK/2019/0028 - Erection of residential development 83 no units including housing, bungalows and flats with sub station and pumping station including car parking and associated landscaping with affordable housing – Approved 27.06.2022

HPK/2016/0484 - Application for approval of reserved matters for the erection of housing including 25 affordable units with flats, shop and car parking, substation and pumping stations (includes 4 bungalows) pursuant to outline planning permission HPK/2013/0417 – Approved 23.01.2017

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
HPK/2025/0312: Land off Hallsteads Close, Dove HolesReport 162 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

11 of 23 attended
RM
Councillor Robert McKeownChair, present
SE
Councillor Simon EvansVice-Chair, apologies
AB
Councillor Alan BarrowCommittee Member, present
CF
Councillor Charlotte FarrellCommittee Member, present
SG
Councillor Stewart GardnerCommittee Member, apologies
LG
Councillor Linda GroobyCommittee Member, present
PH
Councillor Paul HardyCommittee Member, present as substitute
AH
Councillor Adrian HopkinsonCommittee Member, apologies, sent representative
IH
Councillor Ian HuddlestoneCommittee Member, present
DL
Councillor David LomaxCommittee Member, present
PR
Councillor Peter RobertsCommittee Member, present
GS
Councillor Gillian ScottCommittee Member, present

All 23 on the meeting page

On this subject at High Peak

Search all
  1. HPK/2025/0312 - Land off Hallsteads Close, Dove HolesThis decision
  2. HPK/2026/0146 - Land at St Georges Rd, New Mills DerbyshireRefused
  3. HPK/2023/0328 - Portland Nursing Home, 8 Park Road, BuxtonApproved
  4. HPK/2025/0340 - Hargate Hill Equestrian Centre Hargate Hill, Glossop - Retrospective application for change of use of land for the siting of caravans for residential occupation with associated developmentRefused
  5. HPK/2025/0447 - Land at Crossings Road, Chapel-en-le-FrithApproved
  6. HPK/2024/0496 - Land off Brown Edge Close, BuxtonApproved

More from High Peak Development Control Committee

All decisions
MeetingDecisionOutcome
10 Aug 2026 Minutes of the previous meetingThat the minutes of the meeting held on 13 July 2026 be approved as a correct record. Approved Open
10 Aug 2026 Update SheetThat the update sheet be noted. Noted Open
10 Aug 2026 Planning ApplicationsThat the report be noted. Noted Open
10 Aug 2026 HPK/2026/0134 - The Natural Baths, The Crescent, BuxtonThat the application be approved as set out in the report, subject to the amended condition from DCC Archaeology as s... Approved Open
10 Aug 2026 HPK/2026/0184 - Buxton Opera House, Water Street, Buxton, DerbyshireThat Listed Building Consent be granted as set out in the report: 2. That in the event of any changes being needed to... Approved Open