HPK/2025/0375 - Buxton Opera House, Water Street, Buxton
ApprovedPlanning1 paper
AI summaryHigh Peak Borough Council's Development Control Committee approved a planning application at Buxton Opera House, Water Street, Buxton, subject to a 3 year time limit and compliance with approved plans.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedSubject to 3 year time limit and approved plans
MoneyNot stated
What happens next3 year time limit appliesDevelopment must follow approved plans
Who it affectsBuxton Opera House siteBuxton Opera House, Water Street, Buxton
What was decided
The committee approved the application as set out in the officer report, subject to a 3 year time limit condition and a condition requiring development in accordance with approved plans. Report P1, P2, P3
The committee delegated authority to the Head of Development Services, in consultation with the Chair, to make minor wording changes to the decision before it is issued, provided the substantive nature is not exceeded. Report P4
What happens next
The decision is to be issued with the conditions set out in the report and may be refined in wording by the Head of Development Services under the delegated authority granted. Report P4
Any development would need to commence within the 3 year time limit and proceed in accordance with the approved plans. Report P2, P3
Options considered
Chosen: Approve subject to conditions (3 year time limit and approved plans) Report P1, P2, P3
Implications
Legal: A planning permission would be granted subject to conditions, with delegated authority for non-substantive wording changes before issue. Report P4
Who and where
Buxton Opera House, Water Street, Buxton (the application site) Report P1, P5
Timeline
2025-12-08: Development Control Committee meeting
3 years from issue of decision: Time limit for implementation implied by condition Report P2
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item26/79
Resolved
That the application be approved as set out in the report; and 2. That in the event of any changes being needed to the wording of the Committee’s decision (such as to delete, vary or add conditions/ informatives /planning obligations or reasons for approval/refusal) prior to the decision being issued, the Head of Development Services be delegated authority to do so in consultation with the Chair of the Committee, provided that the changes do not exceed the substantive nature of the Committee’s decision.
Word for word from the decision High Peak published for this meeting.Source: democracy.highpeak.gov.uk
HIGH PEAK BOROUGH COUNCIL DEVELOPMENT CONTROL COMMITTEE
Date 8th December 2025
Application No: HPK/2025/0375 Location Buxton Opera House, Water Street, Buxton Proposal Application for Listed Building Consent for - The proposals include a targeted, intrusive Refurbishment and Demolition (R&D) asbestos survey, as well as an intrusive structural survey Applicant Joanne Brooks, High Peak Borough Council Agent Peter Allan, T.A.D Architects Parish/ward Corbar Ward Date registered 29th September 2025 If you have a question about this report please contact: Rachel Robinson, tel [phone removed] email [email protected]
1. SUMMARY OF RECOMMENDATION
Approve with conditions
1. REASON FOR COMMITTEE DETERMINATION
1.1This application has been brought before the committee as the application site is owned by High Peak Borough Council
2. DESCRIPTION OF THE SITE AND ITS SURROUNDINGS
2.1The Buxton Opera House is a grade II* listed building. In respect to the exterior the official listing description states:
‘Opera house. 1901-03, restored 1979. Designed by Frank Matcham, restored by Derek Sugden of Ove Arup Partners. Coursed rock-faced gritstone with ashlar dressings and Welsh slate roofs. EXTERIOR: 2 storeys plus attic. East symmetrical entrance front has 5 windows with curved ends. Banded pilasters to ground floor with entablature, plain pilasters to upper floors. Central recessed entrance flanked by single fluted and banded Doric columns in-antis, with pair of glazed double doors and canted glazed side panels plus 4 overlights with circular glazing. Above a concave plaster with scrolls. Either side a round headed doorway with fanlight, that to right now blocked. Beyond single canted doorways with double panel doors. Central 3 bays covered by ornate iron and glass canopy supported on 2 columns each topped by an octagonal lantern. Above large central Diocletian window in moulded surround with keystone and curved balustrade, flanked by plain sashes in moulded surrounds with keystones. Topped by ramped
1 parapet inscribed OPERA HOUSE with coat-of-arms above, flanked by balustrades with urn finials. Beyond curved sides have 2 plain sashes in moulded surrounds. Above, on either side 2 circular domed towers with paired squat Doric columns and 4 glazing bar windows, topped with entablature, ramped parapet and pedimented finials. Ribbed lead dome to each tower surmounted by ball finial. North front to Water Street has irregular stepped frontage in 3 blocks each stepped forward to right. Left block, 3-storey and 4 windows, has curved projecting porch supported on 2 wooden columns and 2 double doors, above to right semi-circular projection with 3 windows and shallow lead bell- canted dome. Windows in moulded vertical panels those to first floor with blind round heads. Curved section to right has 2 windows to top floor. Central block, 2 storeys and 2 windows, has central canted porch with double doors to centre and left each topped with a pediment, right has external staircase wall. Above 2 Venetian windows. Right block, 3 storeys and 5 windows, has large segment headed doorway with keystone and double panel doors. Above a circular window with ornate iron hanging lantern flanked by thin pilasters and topped by pediment. To left single sash to each floor. To right 3 pairs of plain sashes to each floor, upper floors flanked by thin pilasters and topped by pediments. Beyond to right canted corner with large doorway with lintel inscribed STAGE ENTRANCE and above 3 plain sashes, above again 3 round headed sashes. Topped by ramped parapet with 6 ball finials, set back hipped roof topped by octagonal glass and iron lantern with pyramidal roof and finial.’
2.2The application relates to the flat roof elements of the Opera House, which currently consists of a predominantly asphalt roof.
2.3Buxton Opera House is located within the Buxton built-up area boundary and within the Buxton Central Conservation area.
3. DESCRIPTION OF THE PROPOSAL
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.