Resolved

Resolved that the loan of £93,018 be approved to complete the refurbishment of Old Swan Library to finance the:- (i) replacement of new furniture and fittings; and (ii) purchase of a Radio Frequency Identification System (RFID). L/16
Word for word from the decision Liverpool published for this meeting. Source: councillors.liverpool.gov.uk

Follow this further

Built from Liverpool's papers

What the report saysPro

Report to Executive Board, 3 pages

Executive summary

The purpose of this report is to seek approval for a loan to finance the interior refurbishment of Old Swan Library and to purchase a new radio frequency identification self issue and stock management system for the library (RFID).

The intention is to modernise the library and improve customer services by introducing an improved layout and RFID system that will provide more space for books and an additional eight public computers offering free internet, e- mail, word processing, spreadsheet and scanning services.

Old Swan Library opened in 1913. It was improved in the 1960s, but the shelving and furniture is now worn out and are urgently in need of replacement and an increasing number of complaints about the condition of the library have been received. The scheme refurbishes and modernises the facility as a reader-friendly library with ICT facilities fit for the 21st century.

This project is not part of a capital scheme.

The current furniture and fittings are owned by the Library Service.

An appraisal of the funding options between leasing and borrowing has been carried out and borrowing is considered to be a cheaper option than an operating lease. A loan of £93,018 is required to finance the library refurbishment and purchase an RFID system. The loan will be repaid over 10 years for the furniture and fittings and 5 years for the RFID and stock management system.

The repayments would be: -

£16,589 in years 1 - 5 £5,121 in years 5 - 10

The annual repayment will be financed from the existing Library Service revenue budget. Executive Members/Directors recommendation (Warren Bradley/Keith Turner/Colin Hilton/Phil Halsall

The loan of £93,018 is approved to complete the refurbishment of Old Swan Library to finance the:-

a) replacement of new furniture & fittings; and

b) purchase of a Radio Frequency Identification System (RFID)

Key Decision?

No.

Forward Plan/3 days notice/special urgency:

No.

Implementation effective from:

24 February 2006.

Timescale for action:

Library refurbishment to be completed by March 2006.

Reason(s) for Recommendation:

1. To replace worn out library furnishings, modernise the service and increase usage of Old Swan Library.

2. To introduce an RFID self issue and stock management system to improve customer services and increase efficiency in back office processes.

Alternative options considered

Continue to operate with worn out furnishings and fittings; receive a growing number of complaints; risk accident claims as the flooring and furniture ages further and becomes a health and safety risk to the public.

Consultation

1. Financial Services advised on finance options.

2. Keith Grundy, Principal Treasury Officer - recommended a loan option rather than using an operating lease.

3. Procurement Unit advised on the selection of suppliers. Financial implications:

The loan will be financed from the current library revenue budget.

Best Value:

Leading national library furniture suppliers were invited to submit designs and estimates and best value principles were applied in selecting the preferred design.

Equality implications

The library furniture is designed to be accessible by people of all ages including elderly and disabled people.

Corporate strategy:

The library refurbishment aims to support and deliver the City Council Main Aims of improving customer services and achieving best value.

Budget and Policy Framework:

The loan scheme will assist the Library Service to deliver an improved facility within a balanced budget in 2005 - 2006.

Community safety implications:

The refurbishment will provide a safer and more welcoming environment for the public at Old Swan Library.

Report attached:

None.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Old Swan Library Refurbishment (L/15)Report 3 pages DownloadRead as text

At this meeting

Whole meeting
149Minutes of the Last MeetingApproved 150Local Performance Service AgreementAgreed 151Annual Audit and Inspection LetterNoted
152aOld Swan Library Refurbishment (L/15)This decision
152bCentral Library PFI Scheme (L/16)Approved 152c40,44,46 & 50 Percy Street, 53-67 Upper Parliament Street and 1-9 Parliament Street (RES/72)Decided 152dFormer Lee Manor School and Sports Centre (RES/73)Decided 152eDetermination of Collection Fund Estimated Balances and Council Tax tax base (RES/74)Decided 152fGranby Toxteth Master Plan (RT/1)Noted 152gSkelhorne Street Traffic Flow (RT/2)Approved 152hCity Focus SRB Delivery Plan 2005/06 Programme Amendments (RT/3)Approved 152iExcellence in Liverpool (CHS/37)Approved 152jBig Lottery Fund (BLF) PE and Sport - Capital Programme Update (CHS/38)Approved 152kCardinal Heenan RC High School – Floodlit Synthetic Pitch Tender Approval (CHS/39)Approved 152lConsultation on the future of Campion Catholic High School (CHS/40)Noted 152mChildren Centre 2nd Phase Strategy (2006-08) (CHS/41)Approved 152nTo close Whitethorn Special School and Greenways Special School (CHS/42)Approved 152oSafer & Stronger Communities Fund (SC&CS/1)Agreed 153Madryn Street Residents - Three Parks Neighbourhood Committee - 18 January 2006Deferred 154Licensing Objections - Liverpool East Neighbourhood Committee - 11 January 2006Agreed 155Traffic and Highways Committee - City Council 25 JanuaryApproved 157aPicton 50m Swimming Pool – Interim Payment to Contractors (L/22)Decided 157bGrounds Procurement Acceptance of Tenders (EH/1)Agreed 158Exclusion of Press and PublicDecided 159aSale of Council Land at Gilead Street, Kensington (NH/1)Approved 159bLand at Northumberland Street (NH/2)Approved

On this subject at Liverpool

Search all
  1. Old Swan Library Refurbishment (L/15)This decision
  2. Edge Lane Retail Park, to the east of Montrose Way, Liverpool L13 1EW (Old Swan Ward)Approved
  3. 56 Derwent Road East, Liverpool L13 6QR (Old Swan Ward)Approved
  4. Dales of Liverpool, Prescot Road, Old Swan, Liverpool L13 3AT (Old Swan Ward)Approved
  5. Former 'Ian Skelly' Site/Carpetworld, land bounded by Edge Lane, Edge Lane Drive, Mill Lane, Binns Road, Borax Street, Liverpool L13 4AH (Old Swan Ward)Approved
  6. 694 Queens Drive, Liverpool 13 (Old Swan Ward)Approved

More from Liverpool Executive Board

All decisions
MeetingDecisionOutcome
23 Apr 2010 Minutes of the Last MeetingResolved that the minutes of the meeting held on 9 April 2010 be approved as a true record. Approved Open
23 Apr 2010 New Growth Point - Revised Programme of Development (SSC/43)Resolved that - (i) authority be granted for capital and revenue projects as identified as ‘Priority 1’ in Appendix 1... Decided Open
23 Apr 2010 2010/11 Housing Market Renewal Fund (HMRF) (SSC/44)Resolved that - (i) authority be granted for the Executive Director (Regeneration) to accept a Housing Market Renewal... Decided Open
23 Apr 2010 Refresh of Children and Young People's Plan 2010/11 (ESE/41)Resolved that it be recommended to the City Council that the recommendation and views of the Education and Skills Sel... Approved Open
23 Apr 2010 Croxteth Primary New Build School - Final Business Case (ESE/42)Resolved that - (i) in accordance with the decision (Minute No. 50(b)) of the Executive Board of 12 September 2008 th... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies