Resolved that – (i) subject to the approval of the Big Lottery Fund the City Council accepts the revised lowest tender offer of £348,821 from Blakedown Sport and Play Limited and enters into a contract for the construction of the Cardinal Heenan RC High School floodlit synthetic pitch; (ii) the City Council incur professional fees and disbursements (planning and building regulations fees and site investigation costs) from Weightman and Bullen Architects of £33,574; (iii) a contingency figure of £24,605 is included within the overall total project costs; (iv) the City Council accepts the revised conditional grant offer of £407,000 from the Big Lottery Fund to fund the total project costs; and (v) the City Councils Capital Programme be adjusted to reflect the total expenditure on this project for a sum up to £407,000 phased over financial years 2005/6 to 2007/8 as set out in the report submitted. CHS/40
Word for word from the decision Liverpool published for this meeting.Source: councillors.liverpool.gov.uk
This scheme has previously been approved by the Executive Board (LL/74) and forms part of the approved Capital Programme. The original proposals included the provision of a floodlit synthetic pitch (Phase One) and associated changing accommodation (Phase Two) funded via a grant from the Big Lottery Fund and a contribution from the school. Due to funding restrictions the school has advised the LEA that they can no longer provide a financial contribution to the project therefore; officers recommended to the Big Lottery Fund (i) the withdrawal of the Phase Two element of the project and (ii) a request for a revised allocation of the grant funding to fund (100%) the total project costs for the Phase One works. Subsequently, the City Council has received a conditional grant approval from the Big Lottery Fund for a revised grant of £407,000 to fund the total project costs. The City Council’s BLF PE and Sport Portfolio has therefore been amended accordingly in order to reflect the revised costs. These amendments will be reported separately by the BLF PE and Sport Portfolio Manager.
The tendering process was undertaken in September 2005 and tenders for a ‘Traditional’ contract (including options for pitch dimensions) were issued to six construction firms in accordance with City Council Standing Orders. The pre-tender estimate was circa £400k and the lowest tender submitted (for Pitch Option B 75m x 50m pitch) was by Blakedown Sport and Play Limited in the sum of £341,361.00 however; due to the protracted discussions with the Big Lottery Fund regarding the withdrawal of the Phase Two element of the project, their tender expired on the 9th December 2005. The Contractor has confirmed that their tender remains open until the end of February 2006 although they have indicated an increase in costs of £12,460 to cover this period giving a revised tender figure of £348,821.
This revised contract sum is still the lowest tender taking into account the same processes that would have been undertaken with the next lowest tenderer.
Professional fees and disbursements amount to £33,574. The Big Lottery Fund has requested an additional Contingency figure of £24,605 (approximately 6.5%) to be included within the total project costs.
To ensure that the construction contract documentation can be completed prior to a start on site will require officers to act immediately upon receipt of Executive Board approval as the contractor cannot guarantee to hold his current tender price after the end of February 2006.
In addition, officers must also report the tendering process to the Big Lottery Fund as part of their funding conditions for their approval prior to commencing construction work.
Subject to the necessary City Council and Big Lottery Fund approvals it is anticipated that a start on site can be made at the end of March 2006 with a construction period of 16 weeks.
Executive Director recommendation; Colin Hilton recommends that –
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.