Resolved that – (i) the revised BLF PE and Sport Portfolio be approved and that, the City Councils Capital Programme be adjusted to reflect the revised expenditure phased over years 2004/05 to 2007/8 as detailed in Appendix A to the report submitted; and (ii) further reports be submitted to Executive Board on a periodic basis and after tendering for the main works contracts (where appropriate). CHS/39
Word for word from the decision Liverpool published for this meeting.Source: councillors.liverpool.gov.uk
CITY STATUS – PUBLIC CHS/38 Portfolio: Children Services / Leisure, Executive Members: Sport and Culture / Resources Councillor Warren Bradley Councillor Paul Clein Councillor Keith Turner
Date of submission: Subject: Big Lottery Fund (BLF) PE 20 January / 1 & 7 February 2006 and Sport - Capital Programme Update
Report No. CHS/04/06 Contact Officers: Background papers: None Stephen Tiffany Ext 233 8135 Mike Kearney Ext 233 6329
Executive summary: The purpose of this report is to update members of the amendments to the BLF PE and Sport Portfolio since the Stage 2 submissions to the Big Lottery Fund and to seek authority for the re-allocation of grant within the Portfolio.
Background: Members are aware that at its meeting on 28 May 2004 the Executive Board approved report DE/025/04 (this report identified eleven priority schemes) which outlined the revised principles of the BLF for PE and Sports Initiative in relation to the allocation of £9.217m made to the City Council in November 2001. Further reports (DE/070/04 and DE/12/05) in November’04 and March’05 respectively highlighted the unavoidable changes to the Portfolio. This report elaborates on these changes and indicates the current position in relation to the delivery of the City Council’s amended BLF PE and Sport Portfolio. Members will be aware that the projects at Gateacre CC School and Booker Avenue CP School have been withdrawn from the Portfolio.
Progress to date: Since the last report, the priority schemes as agreed by the BLF PE and Sport Steering Group have all been submitted to the Big Lottery Fund for appraisal. Each scheme has now been assessed by the BLF technical panel. Subsequently, the BLF PE and Sport Portfolio Management Steering Group recommended the approval of the City Council’s revised BLF PE and Sport Portfolio as detailed in Appendix A.
The projects nominated below will become therefore, priorities for development by the City Council. Details of the phasing are given to the Appendix along with the current estimates of cost.
Priority Schemes: 1. Alsop High School: Construction of new dual-use community leisure facility on the site of the existing Queens Drive Recreation Centre. Total estimated cost £5,538,975. BLF PE and Sport application submitted October 2003. Application approved 19 April 2004. Total grant allocation £4,636,975. Demolition work of existing swimming pool completed at the end of December 2004. Construction of the new facilities started end of March 2005 with completion estimated in Autumn 2006.
2. Archbishop Beck RC High School: Construction of new indoor tennis centre and ancillary accommodation at Rice Lane Recreation Ground. Total estimated cost £1,452,405. BLF PE and Sport application submitted July 2003. Application approved February 2004. Total grant allocation £1,082,405. Project completed November 2005. A further grant of £233,100 has been obtained from the Big Lottery Fund for the development of floodlit outdoor courts (Phase Two) to be constructed adjacent to the indoor facility. Construction Tenders to be issued in February 2006. Project completion estimated for end of August 2006. Revised total estimated cost £1,685,505. Revised Total Grant Allocation £1,315,505
3. Cardinal Heenan RC High School: Construction of new synthetic turf pitch (Phase One) within school site. Total estimated cost of Phase One £407,000. BLF PE and Sport application for Phase One only submitted August 2005. Application approved December 2005. Total grant request £407,000. Construction work on Phase One is due to start late spring 2006 with completion end of June 2006. The proposals to construct the new changing accommodation (Phase Two) have been withdrawn from the Portfolio due to funding difficulties with the School and the Football Foundation. Changing accommodation will now be provided from the existing provision contained within the school site.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.