Resolved that – (i) the final proposal for the traffic flow reversal and also the alterations to the Elliot Street junction be approved; (ii) the sum of £250,000 of general capital resources be vired from the CCMS budget to the Skelhorne Street scheme; (iii) authority be granted to commit the expenditure of £500,000; (iv) the City Centre Projects Team Manager be appointed as the nominated officer for administering the contract and expenditure; and (v) subject to the total project costs (including fees) not exceeding £500,000 authority be granted to accept the tender and subsequently appoint a contractor ( Birse Civils ), and authority be given to commit these expenditures on the Skelhorne Street project. RT/3
Word for word from the decision Liverpool published for this meeting.Source: councillors.liverpool.gov.uk
The purpose of this report is to provide an update on the Skelhorne Street flow reversal and the associated alterations to the Elliot Street junction, including the scope, scale and remit of the proposals and final cost estimates and to seek authority to implement the scheme.
The reversal of traffic flow on Skelhorne Street is an essential element of the City Centre Movement Strategy (CCMS). This reversal of flow will cater for traffic accessing Lime Street Station via Renshaw Street and Copperas Hill or for traffic from the north via Seymour Street and Copperas Hill.
The principal objective is to reduce through traffic on Lime Street in front of Lime Street Station, leaving more opportunity for bus movements in that location which is the busiest in the city. In order that the traffic on Lime Street northbound can be further reduced, a bus lane is planned on the only lane in that direction. This will encourage drivers to use the Copperas Hill route as described above. It is planned to have the works completed by the end of April 2006, although traffic flow direction is due to change in March. Extensive advertising of this change over is planned and consultation with bus operators has taken place to enable them to plan alternative interim and long term route changes.
An additional advantage of the reversal of traffic flow is that Network Rail will be able to transfer all vehicular access to the station from Lord Nelson Street to Skelhorne Street. This will enable them to effectively close off the Lord Nelson Street access to vehicular traffic and utilise the vacant space for internal station development. The switch of taxis and on street parking will not be possible until the end of 2006. Access to St John’s Centre car park and the Holiday Inn Hotel will be maintained throughout the works from Lime Street but the predominant access in the final layout will be from Skelhorne Street. This will form an improved access arrangement for servicing vehicles and will further relieve traffic flows on Lime Street.
One of the CCMS Framework Contractors has been providing input to the design stages of the scheme and has prepared a Task Order submission. It is anticipated that the Task Order should be agreed and signed off in February to enable an early start on site.
The sum of £250,000 is already included within the approved 2005/06 Transportation Capital Programme in the City Centre Movement Strategy Programme. An additional £250,000 is now required to deliver this project and it is proposed that this resource is moved from the CCMS scheme budget.
Executive Member/Director recommendation (Councillors Peter Millea and Keith Turner / Charlie Parker)
Recommended that -
1) The final proposal for the traffic flow reversal and also the alterations to the Elliot Street junction be approved.
2) The sum of £250,000 of general capital resources be vired from the CCMS budget to the Skelhorne Street scheme
3) Authority be given to commit the expenditure of £ 500,000.
4) The City Centre Projects Team Manager will be appointed as the nominated officer for administering the contract and expenditure.
5) Subject to the total project costs (including fees) not exceeding £500,000 authority be given to accept the tender and subsequently appoint a contractor (Birse Civils), and authority be given to commit these expenditures on the Skelhorne Street project.
Key Decision:
Yes
Forward Plan:
No – appropriate notices will be published in accordance with the constitution Implementation effective from:
24 February 2006
Timescale for action:
The project is due to start in February 2006 to achieve maximum spend against capital budget during the current financial year.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.